| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹8.6 CrAdmitted-Finance 102 SAIPREM COMPLEX JUNA AUSA ROAD LATUR 413 512 | LATUR | LATUR | MAHARASHTRA | 413512 | +11.00% | ₹8.6 Cr | L1 | Admitted-Finance |
| 2 | L2₹9.0 CrAdmitted-Finance MUMBAI 400023 | MUMBAI | MAHARASHTRA | 400023 | +16.10% | ₹9.0 Cr | L2 | Admitted-Finance |
| 3 | L3₹9.3 CrAdmitted-Finance 413 512 | LATUR | MAHARASHTRA | 413512 | +19.50% | ₹9.3 Cr | L3 | Admitted-Finance |
Tender Value
₹7.8 Cr
EMD Value
₹3.9 L
Closing Date
6 Apr 2026, 5:30 pmClosed
Astt Director Archaeology Dept Nanded
Astt Director Archaeology Dept Nanded
Conservation and Beautification of Ausa Fort , Ausa, Tq.Ausa, Dist.Latur. (Second Call)
2026_TCADM_1291485_1
E Tender/Notice 7/2025-26
Open Tender
Civil Works
730 days
Ausa
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,540
₹3.9 L
Astt Director Archaeology Dept. Nanded
30 Apr 2026
30 Mar 2026
7 Apr 2026
30 Mar 2026
6 Apr 2026
30 Mar 2026
2 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area . | |||||
| 2Cutting down trees including trunks and branches with girths above 30cm to 60cm and stacking the materials neatly with all lifts and lead of 1000m as directed and earth filling in the depression / pit if any. | |||||
| 3Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose. (2) The payment will be made once only for execution of all items for such works. | |||||
| 4Removal of plants/ficus grown by pulling out root system embedded in masnory, cutting stem and application of high/gur/lime formulation as specified by the Architect or other patented chemical biocide treatment such as biocide'Glycel' (isoproplaminesaltofglyphosate) or other chemical as specified by the Engineer in charge etc. complete. | |||||
| 5Dismantling brick masonry in lime or cement mortar and stacking the materials as directed with all leads, lifts etc. | |||||
| 6Excavation for foundation in Hard murum and boulders including removing the excavated material upto a distance of 50 metres, beyond the building area stacking and spreading as directed, dewatering, prepapring the bed for the foundation and necessary back filling, watering, ramming including shoring and strutting etc. complete. (Lift upto 1.5m). By Manual Means | |||||
| 7Excavation for foundation in earth, soil of all types, sand gravel and soft murum, including removing the excavated material upto a distance of 50 m beyond the building area and stacking and spreading as directed, deatering, preparing the bed for the foundation and necessary backfilling, ramming, watering including shoring and strutting, etc. complete. (Lift upto 1.5 m) By Manual Means | |||||
| 8Compacting the hard murum side widths including laying in layers on each side with vibratory roller including artificial watering etc. complete. | |||||
| 9Providing soling using 80 mm size trap metal in 15 cm. layer including filling voids with Crushed sand/grit, ramming, watering etc. complete. | |||||
| 10Providing and laying cast in situ 1:2:4 Lime Concrete of trap/ granite/ quartzite/ gneiss metal for foundation and bedding as per detailed specifications and drawings or as directed including bailing out water, centring, formwork, laying/pumping, compacting, roughening them if special finish is to be provided, finishing if required with fine aggregate, preparing the lime mortar in lime miller and then mixing with coursed aggregate in drum mixer as per specifications including bailing out water, watering etc. complete. | |||||
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.13 MB
BOQ_2219944.xls
BOQ • 0.34 MB
TenderNOTICEausafortpart2__.pdf
Tender Documents • 24.78 MB
Download all tender documents and submit your bid