Tender Value
₹5.5 L
EMD Value
₹6,000
Closing Date
21 Jul 2022, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Project Director
DRDA Krishnagiri
Krishnagiri DT - AGAMT 2021-22 - Mathur Block Improvements to Community Burrial Ground at Mandhipatti H/O Sivampatti Package No - TN-04-KRI-143
2022_RDTN_239566_1
Roc_42_2022_R10__20_06_2022
Open Tender
Civil Works - Others
Item Rate
180 days
Krishnagiri
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹6,000
DRDA Krishnagiri
2 Aug 2022
6 Jul 2022
21 Jul 2022
6 Jul 2022
21 Jul 2022
6 Jul 2022
6 Jul 2022
90 days
Amount
Improvements to Community Burrial Ground @ Mandhipatti H/O Sivampatti - Rs.5.50/- Lakhs
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Cement concrete 1:4:8 (one cement, four sand, and Eight hard broken stone) Using 40mm HBG Metal size Hand Broken granite stone Jelly for Foundation and Flooring including labour charges for mixing concrete watering and laying the concrete
Cement concrete 1:2:4 Using 20mm HBG Metal size Hand Broken granite stone Jelly for Foundation and Flooring including labour charges for mixing concrete watering and laying the concrete
Random Rubble Masonry in cement Mortar 1 : 5 for foundation and basement using New Stones including necessary provision for Bond stones with simultaneous flush pointing with the same mortar above ground level complying with standard specifications.
Refilling in foundation and basement with excavated earth in layer of not more than 15cm thick
Refilling in foundation and basement with filling M-Sand in layer of not more than 15cm thick
Dry Brick work in using country bricks ground moulded of size 22 x 11 x 7cm for the following including curing etc., complete complying with standard specifications.
Brick work 1:5 mix in using country bricks ground moulded of size 22 x 11 x 7cm for the following including curing etc., complete complying with standard specifications.
Supplying & Erecting centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all cost
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Cement Concrete 1:1.5:3 (one cement one and half sand and three machine broken stone) using 20 mm ISS HBG metal for RCC works excluding cost and (abrication otreinforcement and centerning shuttering charges but including curing and
Plastering with Cement Mortar 1:3 10mm thick in all floors including mixing mortar, working in all heights curing watering with all leads and lifts for good water etc., complete complying with standard specification.
Plastering with Cement Mortar 1:5 (one cement and five sand ) 12mm thick in all floors including mixing mortar, working in all heights curing watering with all leads and lifts for good water etc., complete complying with standard specification.
Plastering with Cement Mortar 1:4 20mm thick in all floors including mixing mortar, working in all heights curing watering with all leads and lifts for good water etc., complete complying with standard specification.
Finishing the top of roof with one course of machine pressed tiles of size 23 X 23 X 2 cm of approved quality laid in CM 1:3 , 12 mm thick with water proofing compound confirming to IS by 2% weight of cement used & the joint pointed neatly to full depth
White washing two coats using shell lime including cost and conveyance ofall materials to site and all labour charges etc complete
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Construction of Paver Block
Earth work excavation for foundation in all class of soils except hard rock requirng blasting including cost and conveyance of all etc., complete
Paver block Portion
Kerbwall Portion
Cement concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etcusing mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (countrywood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
Cement concrete 1:3:6 mix using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of interlocking concrete(surface Textured) Block pavements thickness 60mm andcompacted over a thin bedding sand layer of 25mm thickness and joints shall be filled by fine sand of specified grading as per table 1500.6 of specification of Rural roads-2014 and Technical specification clause 1504
Providing New pipelin at manthipatti
Earth work excavation for foundation in all class of soils except hard rock requirng blasting including cost and conveyance of all etc., complete
Cost and supply of fixing Motor with specials including all labour charges
63mm OD PVC Pipe 4 Ksc
63MM PVC Bend
63mm PVC Tee
63mm PVC End Cap
Refilling in foundation and basement with excavated earth in layer of not more than 15cm thick
Laying and jointing of pipe, and specials including all labour charges
1000 Litres Capacity HDPE Tank
Provision for name Board
Provision for Chimney Cover slab
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Krishnamurthi M
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .