| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 LAccepted-AOC | ₹3.0 L | L1 | Accepted-AOC Technically and financially eligible L1 bidder |
| 2 | L2₹3.1 L+₹11,144.43 (3.72%)Rejected-Finance | ₹3.1 L+₹11,144.43 (3.72%) | L2 | Rejected-Finance Not L1 Bidder |
| 3 | L3₹3.4 L+₹39,529.71 (13.2%)Rejected-Finance | ₹3.4 L+₹39,529.71 (13.2%) | L3 | Rejected-Finance Not L1 Bidder |
| 4 | L4₹3.5 L+₹48,092.47 (16.0%)Rejected-Finance | ₹3.5 L+₹48,092.47 (16.0%) | L4 | Rejected-Finance Not L1 Bidder |
| 5 | L5₹4.2 L+₹1.2 L (39.1%)Rejected-Finance | ₹4.2 L+₹1.2 L (39.1%) | L5 | Rejected-Finance Not L1 Bidder |
Tender Value
₹5.8 L
EMD Value
₹7,300
Closing Date
31 Dec 2022, 5:00 pmClosed
STAFF OFFICER (CIVIL), KORBA AREA
Office of the General Manager, South Eastern Coalfields Limited, CIVIL DEPARTMENT, KORBA AREA KORBA- 495 677(CG), Mo-9425533108/ 7587390644
Construction of boundary wall of Higher Secondary School at Manikpur OCP of Korba Area.
2022_SECL_265402_1
SECL/GM/KA/C/e-Tender/22-23/59 Dt. 19.12.2022
Open Tender
Civil Works - Others
Item Rate
90 days
Office of the General Manager Korba Area
As per NIT
3 documents required · 3 mandatory
₹7,300
16 Feb 2023
20 Dec 2022
2 Jan 2023
21 Dec 2022
31 Dec 2022
21 Dec 2022
21 Dec 2022 - 24 Dec 2022
Amount
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar
Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead : Of area beyond 3 sq. metres
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:3:6 (1 Cement : 3 coarse sand(zone-III) : 6 graded stone aggregate 20 mm nominal size).
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size)
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of form for : Columns, Pillars, Piers, Abutments, Posts and Struts
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Cold twisted bars
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level Cold twisted bars
Brick work with clay fly ash brick F.P.S ( non modular) class designation 7.5 in foundation and plinth in cement mortar 1.6 ( 1 cement : 6 coarse sand)
12 mm cement plaster of mix : 1:6 (1 cement: 6 coarse sand)
White washing with lime to give an even shade : Old work (two or more coats) .
Structural steel work in single section, fixed with or without connecting plate,including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : Two or more coats on new work.
Total impact of GST for the purpose of CTC
GOVIND SINGH
SHRIVASTAV ASSOCIATES
PURAN MAL KARSH
K.J. CONSTRUCTION
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_274587.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .