| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹18.3 LAccepted-AOC | 1 | Accepted-AOC offered 19.5 percent rebate on quoted rates and hence was awarded contract | |
| 2 | 2₹23.0 L+₹28,046.80 (1.23%)Rejected-AOC | 2 | Rejected-AOC Did not turn up for negotiations | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹6.7 L
EMD Value
₹13,440
Closing Date
18 Nov 2021, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
DFO Rohru
DFO office, upper market, Rohru, Shimla, H.P. 171207
Construction of forest guard hut at kwar, dodra kwar forest range, rohru forest division
2021_FD_53310_1
tendernotice2021-22/3574
Open Tender
Civil Works - Buildings
Item Rate
365 days
kwar, dodra kwar
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Yes
Payable To DFO Rohru
₹13,440
5 Jan 2022
10 Nov 2021
20 Nov 2021
10 Nov 2021
18 Nov 2021
10 Nov 2021
90 days
Bush cutting and uprooting of vegitation etc.
Cutting in earth work and disposal of excavated earth upto a lead of 20 mtrs. 1/2 pick & 1/2 jumper work site (1.50+0/2+0.75)
Excavation in foundation, trenches etc. in earth work, lift upto 1.50 mtrs. Stackign the excavation soil mnot mor ethan 3 mtr. Clear from the edge of excavation and that returning the stacked soil in 15 cm layers, where required, into plinth sides of foundation etc. cossolidation each deposited layers by ramming and watering and then disposing of all surplus excavated earth as directed within a lead of 20 mtrs. in 1/2 pick and 1/2 jumper work. Left wall, right wall of store, toilet, lobby and vern, Right wall of I/room, Fronte and back wall of kti and lobby, Cross wall of kit and lobby, Back side wall, Wall between bed room, store and toilet, Verendah front wall, Vernadah left wall, Between store and toilet.
Stone soling properly hand packed filling nda consolidation with power road roller to the required grade and camber i/c spreading watering and rolling of brding material murm & earth etc. Above 100 mm thick. Left wall, right wall of store, toilet & vern. right wall of I/room, Fronte and back wall of L/room , Frotn and back wall of kit and lobby, Cross wall of kit and lobby, back side wall, wall between bed room, store and toilet, verandah front wall, verndah left wall, between store and toilet Under floor bed room kitechen lobby, toilet store living room verendah.
Laying cc 1:6:12 in foundation, under floor and pavement i.c ramming and curing complete. Left wal, right wal of store, toilet, lobby and ver., right wall of i/croom, front and back wall of i/room front and back wall of kit and lobby, cross wall of kit and lobby, back kside wall , wall between bed room, store and toilet, verendah front wall, verndah left wall. between store and toilet under floor bed room, kitchedn, lobby, toilet, store living room verendah. Betwen store and toilet Under floor bed room kitchen lobby toilet store living room verendah
Random rubble stone masonry in cement mrtar 1:6 in foundation in cluding dressing of stone.Left wall, 1st step, 2nd step , plinth step , Right wall of store, toilet and lobby, 1st step, 2nd step, pilinth step , right wall of i/room 1st step and 2nd step , front and back wall of i/room 1st step 2nd step plinth step front and back wall of kti and lobby 1st step 2snd step plinth step , cross wall of kit and lobby 1st step 2nd step plinth step back side wall 1st step 2nd step plinth step wall between bed room, store and toilet 1st step 2nd step plinth step , verendah front wall 1st step 2nd step plinth step cerendah left wall, 1st step 2nd step , verendah left wall, 1st step 2nd step plinth step between store and toilet 1st step plinth step
Providing form work of ordinary timber plan king so as to give rought finish i/c centering and shutering, strutting and proppeng etc. height of propping and cement belwo supporting floor to celling not exceeding 4 mtrs. Nd removal of the same for in-situ reinforced. conceret & plain concrete work in Beams , cantilers, lintel et. not exceeding 1 mtrs. In depth left wall , right wal os store, toilet, lobby & ver, right wall of left room , front and back wall of l/room front and back wall of kit and lobby , cross wall of kit and lobby, back side wall, wall between bed room, store and toilet, verendah frotn wall, verandah left wall Beam on lintel level, Left wall, front wall, bak wall of kit, looby and l/room, right and lef twall of l/room, back wall, side wall of store and toilet, right wal of kit, vern. front beam, cross beam slab
Kit self, CB, Alm
RCC work 1:2:4 (1Cement, 2Sand and 4 stone balast 20 mm nominal size) i/c curing complete but excluding cost of form work and reinforcement upto floor two level. Seismic beam at plinth level Left wall, right wall of store, toilet, lobby and ver., right wall of L/room, front and back wall of kit and lobby, cross wall of kit and lobby, back side wall, wall between bed room, store and toilet, verendah front wall, verendah left wall, Beam on lintel level, left wall, front wall, back wall of kit, lobby and l/room, right and left wall of l/room back wall side wall of store and toilet riht wall of kit, vern of store and kit , right wall ofkit, veren frot beam , cross beam, slab, kit self , CB, Alm Beam 1.10 qtl/m3
Providing mild steel/tor steels rein-forecement for RCC work I/c binding placing in position complete upto floor two level.
Slab .90 Qtl/m3
Brick masonry in cement mortar 1:6 in super structure upto 3 mtrs. Height from plinth level i/c curing complete. Left wall, right wall of store, toilet, lobby and verandah, right wall of store, toilet, lobby and ver. Right wall of L/room, back wall, Back wall of lobby nad i/room, right wall of bed room, right wall of kitchen, front wall of kitchen and lobby, ver. pillar, gable front side, gable back side, Deducations Door D, D1, D2 Window W W1, W2, W3 ventilator V, Almirah Alm
Half brick maosnry in 1:4 cement mortar upto floor two level i/c curing complete wall between kitchen and bed room, wall between store and toilet
Woodk work in frames of doors, windows clerestorey windows and other frames wrought, framed and fixed in position in 2nd class deodar wood. Door D, D, D1, D2 Window W, W1, W2, W3 ventilator V, Cup board C.B. Almirah Alm
Preparation and fixing of 40 mm thick panelled glazed or panelled glazed shutter for doors, windows and clerestory windows i/c black enamelled iron butt hinges with necessary screws fitting in 2nd class Deodar wood. Door D, D1, D2, Window W, W1, W2, W3, Ventilator V, Almirah Ak, Cup board CB
Preparation and fixing wire gauge shutters using galvnise with MS wire gauge of I.S designation 85 G wire of dia 0.56 mm for doors & windows and clerestory window iC bright finished/bclak enamelled iron hinges with necessary screws 30 to 40 mm thick. Door D, D1, Window W, W1, W2, W3, Ventilator V
Preparation and fixing wooden plank ceiling with tongued and grooved jointng and wood screws (Frame work/cover fillets to be measured and paid for separately) with 12 mm to 20 mm thick of Deo wood. Bed room, Kitchen, Lobby, Toilet, Store, Living Room, Verendah, Chhajjas.
P/F MS grills of required pattren in wooen fraem windows etc. With M.S. flats/square or round bars with round headed bolts and nuts or by screws i/c red oxide priming coat (With material) Window W, W1, W2, W3, Ventilator V
Providing and fixing 0.60 mm thick prepainted steel sheet in roofing with hot dipped metallic zinc coated sheet with top coat of regular modified polyster (RNP) organic coating of 20 microns over 5 microns primer coating to back coat of polyster of 5 microns over primer coating i/c fixing with prepainted iron J or L hooks, bolts and nuts 6 mm dia metre with prepainted limpet and rubber washers complete with all accesories as required as per the direction of competent authority. Left side, over store/toilet lobby portion, (3.92+1.30/2=2.61) valley of I/room, gabbles of I/room (3.8082=1.90) Verendah (2.75/2+1.37)
Providing and fixing ridges or hips 60 cm overall with 0.60 mm thick prepainted steel sheets in roofin with hot dipped metallic zic coated sheets with top coat of regular modified polyster organic coating of 20 microns over 5 microns primer coating + back coat of polyster of 5 microns over 5 mocrons primer caoting i/c fixign with prepainted iron J or L hooks, bolts and nuts 6 mm dia and prepainted G.I. limpet and bitumen washers complete with all accessories as required as per the direction of competent authority. Main ridges, hip, velleys.
Wall plates on front and back wall, R&L side wall, tie beams in main roof, Rafters for main roof, King post, struts, ridge piece on main roof, Battens for main roof
Providing eaves board 200mm X25 mm thick i/c fiixng in position in 2nd clas deo woo., Front left/right sides and back side
Wood work in frames of false ceiling partition etc. and fixed in position in 2nd class deo wood. 1st floor, bed room, kitchen, lobby, toilet, store, living room, verendah, chhajas
Filling in plinth with sand under floors including watering, ramming consolidating and dressing complete. Bed room, kitchen, lobby, toilet, store, living room, verendah.
Fixing anodized sliding dor bolt anodized transperent or dyed to required colour and shade with bolts nad nuts screws etc. compelte 300X16mm or 250X16 mm
Fixing tower bolt (barrel type) -do- D 300X10 mm or W250 X10 mm. Door shutters for Door D, D1 and D2, Window shutter W, W1, W2, W3, ventilator V Alm and CB
Fixing handles as per abvoe item
Fixing of M.S hooks and eyes
15 mm thick cement plaster in 1:5 (Cement Sand in respective ratios) in fair/rought side of brick walls for plastering up to floor two level i/c arises, internal rounded angles, chamfers and/or rounded not exceedin g10 mm in girth and finished even and smooth i/c scaffolding. In side bed room , kitchen, lobby, toilet, store, living room, verendah, Out side, front/back side, left/right sides, gable frotn side, gable back side vm. Pillar Deducation both side, Door D, D1, D2 Window W, W1, W2, W3 ventilator V
5 Cm (2") thick cement concrete flooring 1:2:4 (1 cement : 2 Sand : 4 stone ballast 12 mm and down aauge) finished with a floating coat of neat cement. Bed room, lobby, store, living room, verendah.
White glazed tiles 6 mm thick in flooring, skirting, treads of steps and landing laid on a bed of covering of 12 mm (1/2") thick cement moratar 1:3 finished with flush painting in white cement. Kit, toilet and kit. shelf.
White glazed tiles 6 mm thick in skirting and risers of steps an dado on 12 mm (1/2") thick cement mortar 1:3 & joined with white cement slurry. Kit 2 (L+B) H, toilet, kit shelf, Deducation D1, D2, W2and W3
Making plinth protection 50 mm thick in cement concrete in 1:3:6 (1 Cement 3 Sand 6.20 ballast) i/c finidshing the top surface of concrete smooth. Building plinth 2 (10.59+8.04) = 37.25 Rmt.
Construction of open surface drain in HDCR stone masonry 15X23 cm U shape in cement mortar 1:6 and inside plastering 20 cm thick with cement mortar 1:3 i/c earth work and laying 10 cm thick cement concrete 1:5:10 and 7.5 cm thick cement 1:2:4 i/c 20 cm thick cement plaster 1:3 and finished with floating coat of neat cement. drain around building i/c out let.
Painting two coats (Excluding priming coat) on new steel and other metal surfaces with enamel / ready mixed/coaltar paint brushing to give an even shade i/c cleaning the surface of all dirt, dust and other foreign matter. As per item No.14 and item no 16
Applying primary coat over new wood and wood based surface after and i/c preparing the surface by throughly oil grease, dirt and other foreign matter (Ready mixed primer/enamel primer/wood filler transparent liquid for varnish) Both side as per item no. 13, 14 and 15
Painting two coasts (Excluding priming coat on new wood and wood based surfaces with enamel/ready mixed flat oil paint brushing to give an evne shade i/c cleaning the surface of all dirt, dust and other foreign matter and sand papering. As per item no 34
Wall painting two coat with oil bound interiar and exteriar weather proof snowcream of approved qualikty and shade on un-decorated wall surface to give an even shade i/c thoroughly brushing the surface free from all kirt, dust foreign matters and sand papering i/c scaffolidng. As per item no. 27 (60% oil bound)
40% snowcem
(Septic tank) Excavation in foundation trenches etc. in earth work.
P/L cement concrete 1:6:12 in bed of septic tank.
RR Stone masonry in 1:4
Half brick masonry in baffle wall in 1:4
P/L RCC 1:2:4
From work
Steel reinforcement @ 100 K.g/Cum
15 mm Cement plastering in 1:6 inside of septic tank
P/L PVC fittings
PVC bends (Reguired degree) with oval access door insertion rubber washer 2 mm thick, bolts and nuts complete.
110 mm dia.
75 mm dia.
PVC Collar
110 mm dia.
75 mm dia.
P/F C.I. cover
P/F rungs
(Site development) Cutting in earth work and disposal of excavated earth upto a lead of 20 meters. 1/2 pick and 1/2 jumper work
Excavation in foundation, trenches etc. in earth work, lift upto 1.50 metre stacking the excavated soil not more than 3 mtrs. Clear from the edge of excavation and that returning the stacked soil in 15 cm layers, where required, into plinth sides of foundation etc. consoidation each deposited layers by rammin gan watering and then disposing of all surpluys excavated earth as directed within a lead of 20 mtrs. In 1/2 pick & 1/2 jumper work.
Laying of cement concrete 1:6:12 in foundation, under floors nad pavement i/c ramming & curing complete. B/wall back side and R/wall L/side.
Construction of retaining walls/breast wall in cement mortar 1:6 as per drawing and technical specifications. In foundation, B/wall back side, R/wall L/side, In plinth, B/wall back side and R/wall L/side.
sandesh chauhan
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .