Tender Value
₹2.0 L
EMD Value
₹3,920
Closing Date
4 Aug 2026, 4:00 pm
XEN REW Kathua
XEN REW Kathua
Constt of lane from main h/o Purshotam Lal Ward No 2 Panchayat Hardo Muthi Block Barnoti
2026_RDPR_317321_10
e-NIT No.135/REW/K of 2026-27 Dated 22/07/2026
Open Tender
Civil Works
Percentage
90 days
BARNOTI
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Rural Development and Panchayati Raj
₹3,920
22 Jul 2026
22 Jul 2026
5 Aug 2026
22 Jul 2026
4 Aug 2026
22 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth for 1 meter from cutting edge and disposal of surplus excavated earth as directed: | 1.27 | cum | 479.3 | ₹608.71 |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:5:10 mix | - | cum | 4,826.5 | - |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:4:8mix | - | cum | 5,202.9 | - |
| 4 | Earth work in rough excavation, banking excavated earth in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and lift upto 1.5 m in all kinds of soil: | - | cum | 425 | - |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) | - | cum | 5,733.6 | - |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 40 mm nominal size) | - | cum | 0.9 | - |
| 7 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete . | - | kg | 123.2 | - |
| 8 | Providing and laying 60mm thick factory made cement concrete interlocking paver block of M-30 grade made by block making machine
with strong vibratory compaction and of approved size and design/shape laid in required colour and pattern over and including 50mm thick compacted bed of fine sand, filling the joints with coarse sand etc. all complete as per direction of Engineer-in-charge | 100.37 | cum | 816.15 | ₹81,916.98 |
| 9 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) | 1.69 | sqm | 6,591.25 | ₹11,139.21 |
| 10 | Providing and laying DPC 40mm thick specified grade including curing in 1:2:4 | 1.86 | sqm | 346.7 | ₹644.86 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.88 MB
BOQ_1039543.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].