Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.1 CrAccepted-AOC | ₹6.1 Cr | 1 | Accepted-AOC L1 |
| 2 | 2₹6.3 Cr+₹21.2 L (3.51%)Rejected-Finance FARIDPUR PACHKHORA BALLIA U P | BALLIA | BALLIA | UTTAR PRADESH | ₹6.3 Cr+₹21.2 L (3.51%) | 2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | M/S LODHI ENTERPRISES L1 | Pratap Construction L2 |
|---|---|---|---|---|---|
| 1.00 | Cutting heavy under growth and bushes upto 7.5 cm dia including removal of roots with collection and removal. | 24,702.5 | M2 | 5 ₹1,23,512.5 | 1 ₹24,702.5 Lowest |
| 2.00 | Earth work in Mar,Kabar, Rankar and Kankar Mixed Soil in Digging/Cutting including lead up to 30 m.and Lift up to 1.5 m including dressing, making Profile and Manual Compaction But Excluding mechanical Compaction. | 9,722 | M3 | 60 ₹5,83,320 Lowest | 60 ₹5,83,320 Lowest |
| 3.00 | Earth work in Mar, Kabar,Rankar and Kankar Mixed Soil in Filling or Embankment including lead up to 195 m.and Lift up to 1.5 m including dressing, making Profile and Manual Compaction But Excluding mechanical Compaction. | 68,215.89 | M3 | 110 ₹75,03,747.9 Lowest | 160 ₹1,09,14,542.4 |
| 4.00 | Dismantling bricks or stone work in lime or cement mortar and including stacking of material as directed by the ingineer -in-charge within a distance of 60 metres. | 1,045.89 | M3 | 200 ₹2,09,178 Lowest | 400 ₹4,18,356 |
| 5.00 | Excavation 0f Foundation in Mar, Kabar, Rankar and Kankar mixed soils including lead upto 30 meter and lift upto 1.5 m including filling, watering, ramming, of excavated earth into the trenches or upto the space and sides of the foundation trenches or into the plinth and removel and disposal of surplus earth as directed by Engineer-in-charge up to a distance of 30 m from the foundation. | 3,126.88 | M3 | 90 ₹2,81,419.2 | 60 ₹1,87,612.8 Lowest |
| 6.00 | Laying P.C.C. M-10 (1:3:6) with cement coarse sand of F.M. not less than 2.5 and crused hard stone grit of size 4.75 to 20 mm including lead 30 m lift 1.5 m, mechanical mixing & mechanical vibrator but execluding cost of centring and shuttering required for proper completion of work including cost of all material T&P, labour etc. | 988.13 | M3 | 3,840 ₹37,94,419.2 Lowest | 4,000 ₹39,52,520 |
| 7.00 | Class-150 brick work in 1:4 With cement , coarse sand including cost of all material labour T&P etc. | 1,582.25 | M3 | 5,500 ₹87,02,375 | 4,300 ₹68,03,675 Lowest |
| 8.00 | Centering & shuttering for R.C.C. work in slab and bed block including all Material & Labour and T & P etc. | 8,045.35 | M2 | 250 ₹20,11,337.5 Lowest | 300 ₹24,13,605 |
| 9.00 | Laying C.C. M-20 (1:1.5:3) with cement coarse sand of F.M. not less than 2.5 and crused hard stone grit of size 4.75 to 20 mm including lead 30 m lift 1.5 m, mechanical mixing & mechanical vibrator but execluding cost of centring and shuttering required for proper completion of work including cost of all material T&P, labour etc. | 377.26 | M3 | 5,800 ₹21,88,108 | 5,000 ₹18,86,300 Lowest |
| 10.00 | Cutting bending and placing TMT steel bar for reinforcement with cost of binding wire with required for proper completion of work including cost of materials , labours, T&P, etc. | 30.43 | M.T | 65,000 ₹19,77,950 Lowest | 67,000 ₹20,38,810 |
Tender Value
₹7.7 Cr
EMD Value
₹15.4 L
Closing Date
17 Aug 2026, 11:00 amClosed
Superintending Engineer, IVth Circle Irrigation Wo
Office of the Superintending Engineer, IVth Circle Irrigation Work, Jhansi
LOT-06 Restoration of Tikariya Dy. from Km 0.000 to Km 24.400 under the Dhasan Canal System in District Hamirpur.
2026_UPIDC_1167957_11
03/SE-IV/2026-27
Open Tender
Civil Works
Item Rate
540 days
RATH
Please refer Tender documents.
2 documents required · 2 mandatory
₹7,000
₹15.4 L
16 Sept 2026
10 Aug 2026
17 Aug 2026
10 Aug 2026
17 Aug 2026
10 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting heavy under growth and bushes upto 7.5 cm dia including removal of roots with collection and removal. | 24,702.5 | M2 | 5.5 | ₹1,35,863.75 |
| 2 | Earth work in Mar,Kabar, Rankar and Kankar Mixed Soil in Digging/Cutting including lead up to 30 m.and Lift up to 1.5 m including dressing, making Profile and Manual Compaction But Excluding mechanical Compaction. | 9,722 | M3 | 71.2 | ₹6,92,206.4 |
| 3 | Earth work in Mar, Kabar,Rankar and Kankar Mixed Soil in Filling or Embankment including lead up to 195 m.and Lift up to 1.5 m including dressing, making Profile and Manual Compaction But Excluding mechanical Compaction. | 68,215.89 | M3 | 188.1 | ₹1,28,31,408.91 |
| 4 | Dismantling bricks or stone work in lime or cement mortar and including stacking of material as directed by the ingineer -in-charge within a distance of 60 metres. | 1,045.89 | M3 | 408 | ₹4,26,723.12 |
| 5 | Excavation 0f Foundation in Mar, Kabar, Rankar and Kankar mixed soils including lead upto 30 meter and lift upto 1.5 m including filling, watering, ramming, of excavated earth into the trenches or upto the space and sides of the foundation trenches or into the plinth and removel and disposal of surplus earth as directed by Engineer-in-charge up to a distance of 30 m from the foundation. | 3,126.88 | M3 | 108.2 | ₹3,38,328.42 |
| 6 | Laying P.C.C. M-10 (1:3:6) with cement coarse sand of F.M. not less than 2.5 and crused hard stone grit of size 4.75 to 20 mm including lead 30 m lift 1.5 m, mechanical mixing & mechanical vibrator but execluding cost of centring and shuttering required for proper completion of work including cost of all material T&P, labour etc. | 988.13 | M3 | 4,948.78 | ₹48,90,037.98 |
| 7 | Class-150 brick work in 1:4 With cement , coarse sand including cost of all material labour T&P etc. | 1,582.25 | M3 | 6,585.79 | ₹1,04,20,366.23 |
| 8 | Centering & shuttering for R.C.C. work in slab and bed block including all Material & Labour and T & P etc. | 8,045.35 | M2 | 497.8 | ₹40,04,975.23 |
| 9 | Laying C.C. M-20 (1:1.5:3) with cement coarse sand of F.M. not less than 2.5 and crused hard stone grit of size 4.75 to 20 mm including lead 30 m lift 1.5 m, mechanical mixing & mechanical vibrator but execluding cost of centring and shuttering required for proper completion of work including cost of all material T&P, labour etc. | 377.26 | M3 | 6,410.58 | ₹24,18,455.41 |
| 10 | Cutting bending and placing TMT steel bar for reinforcement with cost of binding wire with required for proper completion of work including cost of materials , labours, T&P, etc. | 30.43 | M.T | 70,943.6 | ₹21,58,813.75 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.83 MB
BOQ_2209670.xls
BOQ • 0.43 MB
03SEIVNIT2026-27.pdf
Tender Documents • 2.87 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .