| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹98.5 LAccepted-AOC | ₹98.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹98.7 L+₹14,811 (0.15%)Rejected-Finance BALUMATH LATEHAR | ₹98.7 L+₹14,811 (0.15%) | L2 | Rejected-Finance L2 |
| 3 | Rejected-Technical BALUMATH LATEHAR | LATEHAR | JHARKHAND | 822111 | - | - | Rejected-Technical NON RESPONSIVE |
| 4 | Rejected-Technical AT LINE MUHALLA CHATRA | - | - | Rejected-Technical NON RESPONSIVE |
Tender Value
₹98.7 L
EMD Value
₹2.0 L
Closing Date
5 Feb 2026, 5:00 pmClosed
EE RDSD LATEHAR
EE RDSD LATEHAR
CONSTRUCTION OF P.C.C. ROAD FROM BAJARTAND TO PANCHAYAT BHAWAN N.H.ROAD (CHATGHAT) IN VILLAGE BALUMATH PANCHYAT BALUMATH BLOCK BALUMATH DIST LATEHAR
2026_RDSPL_109789_1
EE/RDSD/LATEHAR/45/2025-26
Open Tender
Civil Works
Percentage
180 days
LATEHAR
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹2.0 L
Yes
4 Apr 2026
27 Jan 2026
7 Feb 2026
27 Jan 2026
5 Feb 2026
27 Jan 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Stripping, Storing of Top Soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to plant growth. | - | CUM | 74.9 | - |
| 2 | Compacting Original ground supporting sub-grade Loosening of the ground upto a level of 500 mm below the sub-grade level, watered, graded and compacted in layers to meet requirement of Table 300-2 for sub-grade construction.
SOR NO. 3.20 case (i) RDD Earthen B.T. | - | CUM | 52.6 | - |
| 3 | Construction of Subgrade and Earthen Construction of sub-grade and earthen shoulders with approved material obtained from Borrow pits with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Table 300-2. SOR. ITEM NO. 3.18 RDD | - | CUM | 131.3 | - |
| 4 | Granular Sub-Base with Graded Material (Table:- 400-1) Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. SOR. ITEM NO. 4.01 B(iii)RDD | - | CUM | 1,437.6 | - |
| 5 | Cement Concrete Pavement Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with approve grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing | 1 | CUM | 5,360.4 | ₹5,355.04 |
| 6 | Earth work in excavation in foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance up to 50M including all lifts with leveling, ramming the foundation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/I. | 1 | CUM | 151.82 | ₹151.67 |
| 7 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials, labours, royaly and taxes all complete as per building specification and direction of E/l. | - | CUM | 589.51 | - |
| 8 | Providing designation 75B one brick flat soling joints filled with local sand including cost of watering taxes, royalty all complete as per building specification and direction of E/I. | 1 | SQM | 330.34 | ₹330.01 |
| 9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) IN FOUNDATION AND WALL | 1 | CUM | 5,218 | ₹5,212.78 |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | - | CUM | 6,308.87 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.38 MB
Sbd_1.pdf
Tender Documents • 1.22 MB
BOQ_148337.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .