| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹12.8 LAccepted-Finance | ₹12.8 L | 1 | Accepted-Finance Found Eligible |
| 2 | 2₹13.0 LAccepted-Finance | ₹13.0 L | 2 | Accepted-Finance Found Eligible |
| 3 | 3₹13.2 LAccepted-Finance NOT AVAILABLE | ₹13.2 L | 3 | Accepted-Finance Found Eligible |
| 4 | 4₹13.5 LAccepted-Finance | ₹13.5 L | 4 | Accepted-Finance Found Eligible |
| 5 | 5₹15.5 LAccepted-Finance | ₹15.5 L | 5 | Accepted-Finance Found Eligible |
| Sl No | Description | Qty | Unit | Vishwakarma Enterprises L4 | CUPID INFRA LLP L2 | M/S DAYAL BUILD TECH L1 | N B Engineering and Electric Works L3 | M/S A A ENTERPRISES L5 |
|---|---|---|---|---|---|---|---|---|
| 1.00 | 1 Providing, fitting,installation, testing and commissioning of CT/PT of ratios i.e., 20/5 for 250 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Kah, LIS Kathar, LIS Seriplai, LIS Mukeri, LIS Meeni, LIS Dhakker, LIS NS Pura, LIS Aryanpura 8 nos Complete Job
2 Providing, fitting, installation, testing and commissioning of CT/PT of ratios i.e., 30/5 for 400 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Patyari, LIS Manda 1, LIS Manda 2, LIS Bhagwanachak, LIS Nud.5 nos complete job
3 Providing, fitting, installation, testing and commissioning of CT/PT of ratios i.e., 50/5 for 630 KVA Transformer.The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Ambaran ,LIS Gurha, LIS Nazlachak. 3 nos. complete job
4 Providing, fitting, installation, testing and commissioning of CT/PT for 1000 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The site for installation of CT/PT is LIS Bardoh. 1 no. complete job | 1 | Job | 0 ₹13,50,000 | 0 ₹12,97,000 | 0 ₹12,85,000 | 0 ₹13,20,000 | 0 ₹15,47,000 |
Tender Value
₹16.5 L
EMD Value
₹33,012
Closing Date
16 Feb 2026, 2:00 pmClosed
Executive Engineer MID Akhnoor/Nowshera
Office of Executive Engineer MID Akhnoor/Nowshera
Providing, fitting, installation testing and commissioning of CT/PT for energy meter of various ratios with allied works for various Lift Irrigation Stations of Sub-division, Akhnoor
2026_IFC_302300_1
MID/AN/100
Open Tender
Electrical Works
30 days
Akhnoor
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,000
Executive Engineer MID Akhnoor/Nowshera
₹33,012
Yes
Office of Executive Engineer MID Akhnoor/Nowshera
20 Feb 2026
4 Feb 2026
17 Feb 2026
4 Feb 2026
16 Feb 2026
6 Feb 2026
5 Feb 2026
1 Providing, fitting,installation, testing and commissioning of CT/PT of ratios i.e., 20/5 for 250 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Kah, LIS Kathar, LIS Seriplai, LIS Mukeri, LIS Meeni, LIS Dhakker, LIS NS Pura, LIS Aryanpura 8 nos Complete Job 2 Providing, fitting, installation, testing and commissioning of CT/PT of ratios i.e., 30/5 for 400 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Patyari, LIS Manda 1, LIS Manda 2, LIS Bhagwanachak, LIS Nud.5 nos complete job 3 Providing, fitting, installation, testing and commissioning of CT/PT of ratios i.e., 50/5 for 630 KVA Transformer.The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The sites for installation of CT/PT are LIS Ambaran ,LIS Gurha, LIS Nazlachak. 3 nos. complete job 4 Providing, fitting, installation, testing and commissioning of CT/PT for 1000 KVA Transformer. The CT/PT shall be of reputed make, outdoor, conform to the latest revisions IS 2705 and IS 3156, suitable for metering and protection, vacuum cast epoxy resin with high mechanical strength, flame retardant, moisture resistant, weather proof enclosure, mounting arrangement. The job includes fixing CT/PT on existing structure, secondary wiring, tools, tackles, transportation ,18 months warranty period from date of installation, testing and commissioning at site. The job includes fixing of CT/PT on MS channels with clamps, bolts and nuts. The job also includes providing and laying of 10 core 2.5 sq mm copper cable for CT/PT installation at substation of LIS. The site for installation of CT/PT is LIS Bardoh. 1 no. complete job
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.53 MB
BOQ_981006.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid