| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹23.8 LAdmitted-Finance | -40.10% | ₹23.8 L | L1 | Admitted-Finance |
| 2 | L2₹26.6 LAdmitted-Finance | -33.10% | ₹26.6 L | L2 | Admitted-Finance |
| 3 | L3₹26.7 LAdmitted-Finance CHANDIGARH | -32.87% | ₹26.7 L | L3 | Admitted-Finance |
| 4 | L4₹27.0 LAdmitted-Finance | -32.00% | ₹27.0 L | L4 | Admitted-Finance |
| 5 | L5₹27.5 LAdmitted-Finance | -30.71% | ₹27.5 L | L5 | Admitted-Finance |
Tender Value
₹39.7 L
EMD Value
₹79,440
Closing Date
16 May 2026, 4:00 pmClosed
Er. Mohd Qasim
Executive Engineer PWD R and B Division Billawar
Please refer in BOQ
2026_PWDJK_309733_7
e-NIT No 14 of 2026-27 dated 11-05-2026
Open Tender
Civil Works
270 days
Billawar
Please refer Tender documents
2 documents required · 2 mandatory
₹600
Executive Engineer PWD R and B Division Billawar
₹79,440
23 May 2026
11 May 2026
16 May 2026
11 May 2026
16 May 2026
11 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation by mechanical means (Hydraulic excavator) in trenches for foundation, drains, pipes etc. (not exceeding 1.5m in width) and for shafts, wells, cesspits and the like not exceeding 10sqm on Plan, including dressing of sides and ramming of bottoms lift upto 1.5m, including getting out the excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 mtr. All kinds of soil. | 88.28 | Cum | 256.85 | ₹22,674.72 | 53.9 |
| 2 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil. | 198.24 | cum | 187.3 | ₹37,130.35 | 35.06 |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. | 70.62 | Cum | 218.4 | ₹15,423.41 | 12.04 |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:A)1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) | 11.6 | Cum | 4,826.5 | ₹55,987.4 | - |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:A)1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) with 20% boulder. | 76.01 | Cum | 4,774.46 | ₹3,62,906.7 | - |
| 6 | Providing and laying in position reinforced cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:A) 1:1½:3 (1 cement :1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) | 22.48 | CUM | 7,788.4 | ₹1,75,083.23 | - |
| 7 | Reinforced cement concrete work in walls (any thickness) including attached pilasters,buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts upto floor five level including curing but excluding cost of centering shuttering,finishing and reinforcement. A) 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 6.84 | Cum | 9,395.7 | ₹64,266.59 | - |
| 8 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°,landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering,finishing and reinforcement with A) 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 38.85 | Cum | 9,821.85 | ₹3,81,578.87 | - |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level A) Cold twisted bars. | 8,521.4 | kg | 123.2 | ₹10,49,836.48 | - |
| 10Centering and shuttering including strutting, propping etc. and removal of form work for: | ||||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.54 MB
BOQ_1002514.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid