Executive Engineer-8
EE-8, Room No. CB-201B, 2 floor, CCC Building JDA
Construction of RUB at JP-SWM Railway Line between Haldi Ghati and Diggi/Malpura Road in Sanganer, Zone-08, JDA, Jaipur.
2026_JDAJP_589861_1
JDA/EE-8/11/2026-27
Open Tender
Civil Works
Percentage
270 days
Haldi Ghati and Diggi/Malpura Road in Sanganer
As per tender documents
3 documents required · 3 mandatory
₹5,000
Secretary, JDA
₹33.8 L
Yes
Manthan Hall Main Building, JDA Campus, Jaipur
18 Aug 2026
18 Aug 2026
25 Sept 2026
18 Aug 2026
18 Sept 2026
18 Aug 2026
1 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing, laying and compacting design mix plain/ reinforced cement concrete of specified grade in foundation/ levelling course/ pile cap using batching plant, transit mixer and concrete pump and vibrator including cost of form work, complete as per drawing and technical specifications as per clause 1100, 1500,1700,2100 of MoRT&H specification including all material, labour, machinery, and maintenance of diversion.
PCC grade M -20 | 707.78 | cum | 5,170 | ₹36,59,222.6 |
| 2 | Providing, laying and compacting design mix plain/ reinforced cement concrete of specified grade in foundation/ levelling course/ pile cap using batching plant, transit mixer and concrete pump and vibrator including cost of form work, complete as per drawing and technical specifications as per clause 1100, 1500,1700,2100 of MoRT&H specification including all material, labour, machinery, and maintenance of diversion.
RCC Grade M -20 | 368.88 | cum | 5,220 | ₹19,25,553.6 |
| 3 | Providing, laying and compacting design mix plain/ reinforced cement concrete of specified grade in foundation/ levelling course/ pile cap using batching plant, transit mixer and concrete pump and vibrator including cost of form work, complete as per drawing and technical specifications as per clause 1100, 1500,1700,2100 of MoRT&H specification including all material, labour, machinery, and maintenance of diversion.
RCC Grade M -25 | 822.14 | cum | 5,620 | ₹46,20,426.8 |
| 4 | Providing, laying and compacting design mix plain/ reinforced cement concrete of specified grade in foundation/ levelling course/ pile cap using batching plant, transit mixer and concrete pump and vibrator including cost of form work, complete as per drawing and technical specifications as per clause 1100, 1500,1700,2100 of MoRT&H specification including all material, labour, machinery, and maintenance of diversion.
RCC Grade M -35 | 2 | cum | 5,720 | ₹11,440 |
| 5 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Depth upto 1.5 m | 23,909.79 | cum | 229.5 | ₹54,87,296.35 |
| 6 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 1.5 m and upto 3.0 m over item no 4.10.1.1 | 7,601.03 | cum | 16.1 | ₹1,22,376.58 |
| 7 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 3.0 m and upto 4.5 m over item no 4.10.1.1 | 7,601.03 | cum | 36.7 | ₹2,78,957.8 |
| 8 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 4.5 m and upto 6.0 m over item no 4.10.1.1 | 2,937.78 | cum | 64.3 | ₹1,88,899.25 |
| 9 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 6.0 m and upto 7.5 m over item no 4.10.1.1 | 606.15 | cum | 98.7 | ₹59,827.01 |
| 10 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 7.5 m and upto 9.0 m over item no 4.10.1.1 | 323.28 | cum | 137.5 | ₹44,451 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 15.91 MB
BOQ_1047487.xls
BOQ • 0.38 MB
Tender011.pdf
Tender Documents • 15.89 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].