Tender Value
Refer Docs
Closing Date
5 Oct 2023, 11:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
anjali kumari
POWER GRID CORPORATION OF INDIA LIMITED, CF-17, ACTION AREA-1C, NEW TOWN, RAJARHAT, KOLKATA-700156
EMPANELMENT OF AGENCIES FOR DIVERSION WORK OF TRANSMISSION LINE UNDER ER-II.
ER2/NT/W-MISC/DOM/E00/23/07711/1000011215/I-4021/5001000740
Empanelment
Services
Works
ER-II region
5 Oct 2023
4 Sept 2023
5 Oct 2023
4 Sept 2023
29 Oct 2023
4 Sept 2023
Name of the Company M/s
2 Other Income(Except non-incurring income)
4 Net Profit After Tax (PAT)
5 Share Capital
Reserves & Surplus
Miscellaneous Exp not written off
7 Net Fixed Assets
Non current Assets
8 Net Current Assets 0.00 0.00 0.00 0.00 0.00
9 Capital Employed(7+8) 0.00 0.00 0.00 0.00 0.00
10 Current Assets
12 Current Liabilities & Provisions
13 Long Term Loan Funds
14 Repayment of Loans
15 Depreciation
16 Interest Paid
17 PAT + Depreciation + Interest 0.00 0.00 0.00 0.00 0.00
Profitability Ratios (%)
18 Net Profit to Total Income (4/3) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
19 Net Profit to Capital Employed (4/9) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
20 Net Profit to Net Worth (4/6) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Liquidity Ratios (Times)
21 Current Ratio (10/12) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
22 Debt to Equity Ratio (13/6) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Other Ratios (%)
23 Debtor to Sales Ratio #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
24 Inventory to Sales Ratio #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Other Ratios (Times)
25 Debt Service Coverage Ratio [17/(14+16)] #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
26 Interest Coverage Ratio [17/16] #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
27 Debtor Turnover Ratio (Sales/Av Receivables) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Other Ratios (Days)
28 Debtor Velocity (365/Debtor Turnover Ratio) #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Debtor Turnover Ratio Sales / Av Receivables
Debtor Velocity 365 / Debtor Trunover Ratio
Net Cash flow from Operating Activities (A)
(As per the Cash Flow Statement forming part of the
Audited Accounts)
Lon Term Loans - banks repaid (B) 0.00 0.00 0.00 0.00 0.00
Dividend and Dividend Tax paid (C) 0.00 0.00 0.00 0.00
Cash Flow from Operations net of Repayment of loans & 0.00 0.00 0.00 0.00 0.00
Dividend (A)-(B)-(C)
Cash Flow from Operations net of Repayment of loans &
Dividend (In Crores)
REQUEST FOR EMPANELMENT [RfE (2023)] OF AGENCIES FOR DIVERSION WORK OF TRANSMISSION LINE UNDER ER-II
This Price_schedule sheet is enclosed as per the requirements of SRM Portal attachment bidding and not for the purpose of agencies submitting their applications for empanelments for the aforesaid subject.
Sl. No. Item Description Unit Qty
a Check survey KM.
2 Excavation of Various types of Soil.
c Dry Fissured Soil CuM
a Wet Fissured Soil CuM
b Hard Rock CuM
3 Concreting( including all associated work related to foundation work
a Concrete nominal mix 1:1.5:3 ( M20) CuM
b Lean Concrete nominal mix 1:3:6 (M10) CuM
c Supply of Re-inforcement Steel MT
d Installation of Stub including Bolts & Nuts MT
4 Erection of various types of Towers, Tower parts and its body/ extensions (complete) including Bolts & Nuts, Step bolts, Hangers, D-Schacles etc including tack welding & application of zink rich primer and two coats of enamel paints.
a Normal Towers MT
b Multi Circuit Towers MT
c River Crossing Tower MT
d For HTLS reconductering Towers MT
5 Installation of Earthing of Towers
a Pipe type earthing Nos
b River Crossing Earthing MT
c Counterpoise Earthing(120 Meter length) Nos
d Counterpoise Earthing(180 Meter length) Nos
e Counterpoise Earthing(280 Meter length) Nos
6 Installation of Tower Accessories
a Danger Plate Nos
b Number Plate Nos
c Phase Plate ( Set of Three) Set
d Circuit Plate ( Set of Two) Set
e Anti Climbing Device Set
f Bird Guard(Set of three) set
g Bird Buard(for V string) set
h Pole Plate(set of two) set
7 Installation of Insulator Strings complete with Arching horns, necessary Hardwares & Stringing of conductor including fixing of conductor accessories, Installing & Stringing of Earthwire / OPGW including fixing of eaartwire/OPGW accssories.
a 132 KV AC Double Circuit Single conductor KM.
b 132 KV AC Single Circuit Single conductor KM.
c 220 KV AC Double Circuit Single conductor KM.
d 220 KV AC Single Circuit Single conductor KM.
e 400 KV AC Single Circuit double conductor KM.
f 400 KV AC Double Circuit double conductor KM.
g 400 KV AC Double Circuit Tripple conductor KM.
h 400 KV AC Double Circuit Quard conductor KM.
i 765 KV AC Double Circuit Hexagonal conductor KM.
j Bipole 800 KV with hexagonal with metalic return conductor KM.
8 De-Stringing of Insulator Strings, Conductor, Earthwire with all conductor & earhwire Hardwares, providing necessary back stays and transporting back to POWERGRID store
a 132 KV AC Double Circuit Single conductor KM.
b 132 KV AC Single Circuit Single conductor KM.
c 220 KV AC Double Circuit Single conductor KM.
d 220 KV AC Single Circuit Single conductor KM.
e 400 KV AC Single Circuit double conductor KM.
f 400 KV AC Double Circuit double conductor KM.
g 400 KV AC Double Circuit Tripple conductor KM.
h 400 KV AC Double Circuit Quard conductor KM.
i 765 KV AC Double Circuit Hexagonal conductor KM.
j Bipole 800 KV with hexagonal with metalic return conductor KM.
9 Installation of following atems for Aviation Requirement
a Span Markers Nos.
b Obstruction Lights (to be provideed as per IS 5613)
i 1 medium intensity + 2 Low intensity set
ii 1 medium intensity + 4 Low intensity set
10 Dismantling of various types of Towers, Tower parts and its body/ extensions (complete) including Bolts & Nuts, Step bolts, Hangers, D-Schacles, Danger plate, Number Plate, Phase Plate, ACD etc including de- welding of Bolts & Nuts and transporting back to POWERGRID Store (within 100 Km). MT
11 Loading, Unloading & Transportation of new Tower parts, conductor,H/W etc.from POWERGRID store to site . Also loading, Unloading & Transportation of old Tower parts, conductor,H/W etc.from site to POWERGRID store (within 100 Km)
a Tower parts, nut bolts,accessories MT
b Conductor, Insulator, H/W (TATA 709 Truck or Equivalent) Per Trip
12 Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-in charge.
1:3:6 or richer mix Cum
13 Demolishing R.C.C work manually/by mechanical means including stacking steel bars and disposal of un-servicable material within 50 meters lead as per direction of Engineer-in charge. Cum,
15 Tower Foundation protection work
a RRM including excavation (1:5 cement morter) Cum,
b Stone bound in GI wire netting including excavation Cum,
c Revetment of pack6" & above stone/ boulder in heavily coated GI 4mm dia performed wire mesh size 100 Cum,
d M 15 (1:2:4) concrete for top seal cover of revetment Cum,
e Plum Concrete Cum,
f Back filling & gap leveling Cum,
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html
01 Instruction to Bidders Sec-1 to 5.doc
doc • 0.48 MB
02_Annex-I (Sec-2_Clause-1 2).doc
doc • 0.20 MB
03_KMP Decla_(Sec-2_Clause-6 9).docx
docx • 0.05 MB
04_RfE (2020)_Sec-6_Appli Form.doc
doc • 0.22 MB
05_Attach-1_Integrity Pact.doc
doc • 3.83 MB
06_Attach-2_Power of Attorney.doc
doc • 0.14 MB
07_Attach-3_QR.doc
doc • 0.20 MB
08_Attach-4_Cover Page.doc
doc • 0.16 MB
09_Attach-4_Sec-I (Comp Profile).doc
doc • 0.19 MB
10_Attach-4_Sec-II (Fin Details).doc
doc • 0.17 MB
11_Attach-4_Sec-II-(Bank Certi).docx
docx • 0.07 MB
12_Attach-4_Sec-II-Fin Detail.xlsx
xlsx • 0.02 MB
13_Check List.docx
docx • 0.08 MB
Price Schedule.xlsx
xlsx • 0.01 MB
Scope of work.docx
docx • 0.05 MB
Thumbs.db
db • 0.01 MB
01-SECTION-1 Empanelment of Erection Agencies R1.pdf
pdf • 0.85 MB
02-Section-II -Rev-6 March-2018.pdf
pdf • 0.74 MB
03_1-SECTION - 3 - Rev-6 March-2018 with Mod upto Oct-2018 .pdf
pdf • 0.99 MB
03_3_ TS_VOL-II_,Sec-III _2nd Part_ Annex B -C-D-E.pdf
pdf • 0.48 MB
04_1-Section 4-Rev-6 March-2018 withMod june 19.pdf
pdf • 0.82 MB
Scope of work.pdf
pdf • 0.26 MB
TS for transmission line.pdf
pdf • 1.44 MB
04_2_APP-I_Precommissioning final.pdf
pdf • 1.25 MB
04_3_APP-II_SFQP Transmission Line, Revision 06.pdf
pdf • 2.80 MB
04_5_Annex-I_ SAT.pdf
pdf • 0.33 MB
04_6_AM formats.pdf
pdf • 0.56 MB
10_1_2_Appendix B-C-D OPGW Inst..pdf
pdf • 1.75 MB
corrigendum-CPPP.pdf
pdf • 0.65 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .