Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 CrAccepted-Finance | ₹5.4 Cr | L1 | Accepted-Finance FIRST LOWEST BIDDER |
| 2 | L2₹5.5 Cr+₹10.2 L (1.89%)Accepted-Finance A TO SUBASH CHOWK MAIN ROAD MALKANGIRI | MALKANGIRI | MALKANGIRI | ODISHA | 764045 | ₹5.5 Cr+₹10.2 L (1.89%) | L2 | Accepted-Finance SECOND LOWEST BIDDER |
| 3 | L3₹5.6 Cr+₹17.5 L (3.25%)Rejected-Finance | ₹5.6 Cr+₹17.5 L (3.25%) | L3 | Rejected-Finance THIRD LOWEST BIDDER |
| 4 | L4₹6.7 Cr+₹1.3 Cr (24.4%)Rejected-Finance | ₹6.7 Cr+₹1.3 Cr (24.4%) | L4 | Rejected-Finance FORTH LOWEST BIDDER |
| 5 | L4₹6.7 Cr+₹1.3 Cr (24.4%)Rejected-Finance | ₹6.7 Cr+₹1.3 Cr (24.4%) | L4 | Rejected-Finance FORTH LOWEST BIDDER |
Tender Value
₹6.7 Cr
EMD Value
₹6.7 L
Closing Date
25 May 2026, 5:00 pmClosed
CHIEF CONSTRUCTION ENGINEER
Chief Construction Engineer Jeypore R and B circle Jeypore
Development of Tourism Infrastructure at Malikeswar Temple in Malkangiri District.
2026_EICCL_129143_1
C.C.E.J.C (RANDB)-04/2026-27
National Competitive Bid
Civil Works - Buildings
Percentage
330 days
Malkangiri
3 documents required · 3 mandatory
₹10,000
₹6.7 L
Yes
17 Sept 2026
11 May 2026
26 May 2026
11 May 2026
25 May 2026
11 May 2026
11 May 2026 - 25 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation of foundation in laterite rock or any hard rock(other than granite or disintigrated rock) removed by chiselling including dressing and levelling the bed not exceeding 1.5m in depth and depositing the soil within initial lead of 50m and as per specification approved by the Department. | 311.92 | cum | 2,006.93 | ₹6,26,001.61 |
| 2 | Earthwork in Excavation in hard soil for site leveling, foundation, pits, trenches and other civil works upto and including 1.5metre lift and stacking the soil upto a lead of 100 metre and including dewatering, removing slush, shoring and strutting (as required), complete as per specification and as directed by the Engineer-In-Charge. | 1,752.42 | cum | 276.9 | ₹4,85,245.1 |
| 3 | Providing & applying of pre constructional anti-termite treatment by drilling 12mm dia holes at distance of 30cm @ junction of wall & floor about 300mm apart deep enough to reach the soil below & chemical emulsion (IMIDACHLOPRIED 30.5SC mixed with 47.5ltr water) pumped these holes to soak the soil @ 1 ltr solution of each hole as per manufactures specification & the holes should be pluged the filling materials including cost of all materials, labour,conveyance, T&P , all taxes and hire charges of machinaries as per direction of Engineer-in-charge.(make-premise-BAYER,Paxton-FMC,ozie-KALYANI) | 1,429.55 | sqm | 104.5 | ₹1,49,387.98 |
| 4 | Filling in foundation trenches and plinth, with excavated earth including laying the earth in layers not exceeding 23.5 cm thick ramming & watering with all leads & lifts including cost of all labour, T & P completed as directed by the Engineer-in-Charge. | 7,827.5 | cum | 153.8 | ₹12,03,869.5 |
| 5 | Supplying & filling of foundation with course sand well watered and rammed including cost, cost of all labour, carriage, royalty complete in all respect. (As Per A/R Page No-1, Item No-2) | 704.83 | cum | 763.6 | ₹5,38,208.19 |
| 6 | Providing and laying plain cement concrete 1:4:8 (1 cement: 4 sand: 8 stone agregate 40mm nominal size) as levelling course in foundation and plinth etc. including tempering, curring ,shuttering etc.complete all depth and height. | 172.5 | cum | 5,700.5 | ₹9,83,336.25 |
| 7 | Cement Concrete (1:3:6) using 40mm size hard granite C.B. metal approved quality from approved quarry including cost, carriage, royalty, cost of all labour. etc complete and as directed by E.I.C. | 141.07 | cum | 6,098.7 | ₹8,60,343.61 |
| 8 | Cement Concrete (1:2:4) using 12mm size hard granite C.B. chips approved quality from approved quarry including cost, carriage, royalty, cost of all labour. etc complete and as directed by E.I.C. | 167.3 | cum | 6,982.7 | ₹11,68,205.71 |
| 9 | R.C.C. M-20 grade with 20mm and down grade C.B. chips of approved quality from approved quarry including hoisting, laying hire charges of concrete mixture, vibrator, watering, curing and cost of all materials and labour, centering shuttering etc complete but excluding cost of reinforcement.
A)FOOTING | 176.69 | cum | 6,611.66 | ₹11,68,214.21 |
| 10 | B)COLOUMN
GROUND FLOOR | 18.56 | cum | 15,874.57 | ₹2,94,632.02 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 4.43 MB
Tendernotice_1.pdf
PDF • 3.16 MB
BOQ_590699.xls
BOQ • 0.48 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .