| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹33.4 LAccepted-AOC | ₹33.4 L | L-1 | Accepted-AOC Accepted as L-1 |
| 2 | L-2₹36.9 L+₹3.5 L (10.3%)Rejected-Finance CAMP WARD NO 17 GHAROULA MOHALLA NEW BUS STAND SHAHDOL DIST SHAHDOL MP PIN 484001 | SHAHDOL | MADHYA PRADESH | 484001 | ₹36.9 L+₹3.5 L (10.3%) | L-2 | Rejected-Finance Rejected as L-2 |
| Sl No | Description | Qty | Unit | VIKASH KUMAR VISHWAKARMA L1 | M/S D K SINGH L2 |
|---|---|---|---|---|---|
| 1.00PARTICULAR | |||||
| 1.01 | (A) Labour cost
Cutting in soft stonel by Chisel & Hammer | 116.23 | cubic mtr | 5,31,752.25 ₹6,27,467.66 Lowest | 5,81,150 ₹6,85,757 |
| 1.02 | Cleaning/ removal of debris/stone from galleries and stacking within 50m distance | 116.23 | cubic mtr | 52,594.08 ₹62,061.01 | 46,492 ₹54,860.56 Lowest |
| 1.03 | RCC (1:2:4) in wall/roof ceiling of air crossing/ stopping (any thickness) in u/g (Excluding centring, shuttering, reinforcement cutting, bending, placing in position and binding etc all complete as well as cost of RCC materials) | 94.33 | cubic mtr | 3,85,526.71 ₹4,54,921.52 | 3,77,320 ₹4,45,237.6 Lowest |
| 1.04 | Cement concrete/PCC (1:2:4) in foundation /plinth / flooring/wall (any thickness) in u/g (Excluding centring, shuttering and cost of CC materials) | 44.26 | cubic mtr | 1,47,253.02 ₹1,73,758.56 Lowest | 1,77,040 ₹2,08,907.2 |
| 1.05 | Centring, shuttering, finishing and reinforcement including cutting, bending, placing in position and binding and strutting, propping etc complete. | 856.41 | sq. mtr | 6,71,425.44 ₹7,92,282.02 Lowest | 7,70,769 ₹9,09,507.42 |
| 1.06 | 06mm Thick cement plaster/cement punning (1:4) to RCC/PCC work in u/g including curing etc complete(exclusive cost of material) | 579.71 | sq. mtr | 1,65,217.35 ₹1,94,956.47 Lowest | 2,02,898.5 ₹2,39,420.23 |
| 1.07 | White washing in u/g with white lime to give an even shade on old work/new work | 362.6 | sq. mtr | 4,713.8 ₹5,562.28 Lowest | 5,439 ₹6,418.02 |
| 1.08 | Loading of all kind of building materials in to tubs at incline/Pit mouth on surface with lead of 50m.
Cement | 929 | Bag | 7,432 ₹8,769.76 Lowest | 8,361 ₹9,865.98 |
| 1.09 | Sand | 70.6 | cubic mtr | 17,014.6 ₹20,077.23 Lowest | 21,180 ₹24,992.4 |
Tender Value
₹40.3 L
EMD Value
₹50,400
Closing Date
8 Jun 2026, 5:00 pmClosed
STAFF OFFICER MINING
OFFICE OF THE STAFF OFFICER MINING
Construction of steps, side wall and drains in MD1 Incline at Bangwar UG Mine of Sohagpur Area.
2026_SECL_360357_1
SECL/SGP/SO(M)/2026-27/NIT-734 dated 27-05-202
Open Tender
Civil Works - Others
Item Rate
365 days
BANGWAR UG MINE
as per NIT
7 documents required · 7 mandatory
₹50,400
25 Aug 2026
27 May 2026
10 Jun 2026
27 May 2026
8 Jun 2026
28 May 2026
27 May 2026 - 4 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1PARTICULAR | |||||
| 1.01 | (A) Labour cost
Cutting in soft stonel by Chisel & Hammer | - | cubic mtr | 5,510.07 | - |
| 1.02 | Cleaning/ removal of debris/stone from galleries and stacking within 50m distance | - | cubic mtr | 545.17 | - |
| 1.03 | RCC (1:2:4) in wall/roof ceiling of air crossing/ stopping (any thickness) in u/g (Excluding centring, shuttering, reinforcement cutting, bending, placing in position and binding etc all complete as well as cost of RCC materials) | 1 | cubic mtr | 4,925.15 | ₹4,920.22 |
| 1.04 | Cement concrete/PCC (1:2:4) in foundation /plinth / flooring/wall (any thickness) in u/g (Excluding centring, shuttering and cost of CC materials) | 1 | cubic mtr | 4,008.8 | ₹4,004.79 |
| 1.05 | Centring, shuttering, finishing and reinforcement including cutting, bending, placing in position and binding and strutting, propping etc complete. | 1 | sq. mtr | 945.21 | ₹944.26 |
| 1.06 | 06mm Thick cement plaster/cement punning (1:4) to RCC/PCC work in u/g including curing etc complete(exclusive cost of material) | - | sq. mtr | 343.79 | - |
| 1.07 | White washing in u/g with white lime to give an even shade on old work/new work | - | sq. mtr | 15.86 | - |
| 1.08 | Loading of all kind of building materials in to tubs at incline/Pit mouth on surface with lead of 50m.
Cement | - | Bag | 9.69 | - |
| 1.09 | Sand | 1 | cubic mtr | 290.84 | ₹290.55 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.75 MB
Tendernotice_2.pdf
PDF • 1.48 MB
BOQ_373225.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .