| 1 | L1Accepted-AOC 03 GOVIND PURAM EIDGHAH ROAD BIJNOR BIJNOR UTTAR PRADESH 246701 | BIJNOR | UTTAR PRADESH | 246701 | L1 | Accepted-AOC L1 |
| 2 | Not Admitted-Fee/PreQual/Technical JABALPUR | JABALPUR | MADHYA PRADESH | 482001 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | Deep Enterprises |
|---|---|---|---|---|
| 1.01 | Polyhouse –Technical Specifications
1. Size & Shape
• Size: 40 feet × 60 feet
• Type: Arch-shaped polyhouse
• Center Height: 15 feet
• Side Height: 11 feet
2. Base / Foundation (Description)
1. Ground Preparation
• The land must be excavated, filled with at least 45 cm murrum, and leveled properly.
2. Pole Foundation
• Galvanized Iron (GI) pipes must be fixed in the ground using cement concrete.
• Hole size for each pole: 0.45 m × 0.45 m × 0.50 m deep.
• Distance between two poles should not be more than 3 meters.
3. Side Brick Wall
• A small brick wall of 20 cm height and 20 cm width should be built around the entire structure.
4. Center Path
• In the middle of the polyhouse, a path of interlocking pavement blocks should be made.
• Path size: 17.88 m × 1.50 m.
5. Plant Beds
• Beds should be built on both sides of the path.
• Beds should be made using brickwork and plastered.
• Beds should be placed at 90° (right angle) to the path.
• Each bed:
• Inner width: 1 meter
• Side wall height: 20 cm
• Distance between two beds: 35 cm (including sidewalls).
• The gap between two bed walls should be filled with M-20 cement concrete, and plaster should be done on all brickwork.
3. Structure (Simple Description)
1. Material
• Entire structure should be made from Galvanized Iron (GI) steel, hot-dip galvanized.
• Structure must follow IS 875 standard and withstand 120 km/h wind speed.
2. Poles and Pipes
• Main column GI pipes: 1.5 inch x 1.5 inch square pipes
• Arch base GI pipes: 1.5 inch x 1.5 inch square pipes
• Purlins: 1.5 inch x 1.5 inch square pipes
• Remaining structure pipes: 2 inch x 2 inch square pipes
• All GI pipes should be fixed into cement concrete in the ground.
3. Door
• 2 Aluminium frame doors with 6mm polycarbonate sheet. One door should be at front and the other at the back
4. Distance Between Columns
• Maximum 3 meters.
4. Cladding (Covering Materials)
1. Poly Film
• 200-micron UV-stabilized film
• More than 80% light transmission
• From a major/reputed brand
2. Insect Net
• 40-mesh insect net on both long sides
• Net height: from 1 meter above ground up to 2.5 meters
• Poly film in net area should be foldable to allow airflow.
3. Shade Net
• Shade-net curtains should be fixed inside the polyhouse to cover plant beds when needed.
5. Overhead Irrigation / Fogger System
• Hanging foggers with lateral pipes, supporting wire, and MS support frame.
• Fogger parts must be from a major/reputed brand.
• 1 HP pump should be provided.
• 1000-liter water tank for fogger supply. | 3 | Per unit rate required from bidder | 12,66,300 ₹12,66,300 Lowest |
| 1.02 | Drip Irrigation System -
The project requires the setup of two independent systems:
• Site 1: Installation for 500 beds.
• Site 2: Installation for 100 beds.
• Scope of Work and Materials Required
Your quote must cover all labor, materials, and installation for the following requirements:
1. Bed Irrigation Setup (for all 600 beds):
• Bed Dimensions: 10 meters (length) x 0.15 meters (width) x 1.20 meters (height).
• Drip Lines: Four parallel drip line per bed, which may extend in length to consecutive beds. Emitter (dripper) spacing of drip lines should be 6 inch
• Fittings: All necessary 16mm pipes, O-rings, take-ups, and 16mm valves connecting to the main line.
2. Underground Main Supply Line:
• Pipe: 75mm diameter, 4-gauge PVC pipe.
• Installation: Pipe must be installed 1 meter below ground level.
• Total Length: Approximately 550 meters of underground piping across both sites
• Water Source Setup: Supply and installation of a 5000-liter water tank.
• Pumping: Supply and installation of a 5 HP motor.
• Filtration & Fertigation: Installation of a Screen Filter, a Sand Filter, and a Venturi injector system for fertilizer application.
4. Site 2 Specific Equipment (for 100 beds location):
• Water Source Setup: Supply and installation of a 1000-liter water tank.
• Pumping: Supply and installation of a 3 HP motor.
• Filtration & Fertigation: Installation of a Screen Filter, a Sand Filter, and a Venturi injector system for fertilizer application.
• Valves to be provided as per requirement for sectorwise irrigation | 600 | Pe bed rate required from bidder | 3,99,000 ₹3,99,000 Lowest |
Tender Value
Refer Docs
EMD Value
₹63,000
Closing Date
11 Feb 2026, 4:00 pmClosed
DFO
CCF office, social forestry circle indore
Poly house construction and drip irrigation system construction work (including material)
2026_MPFD_478595_1
172
Open Tender
Miscellaneous Works
Item Wise
30 days
CCF office, social forestry circle indore
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
₹63,000
CCF office, social forestry circle indore
20 Feb 2026
29 Jan 2026
13 Feb 2026
29 Jan 2026
11 Feb 2026
29 Jan 2026
5 Feb 2026
Polyhouse –Technical Specifications 1. Size & Shape • Size: 40 feet × 60 feet • Type: Arch-shaped polyhouse • Center Height: 15 feet • Side Height: 11 feet 2. Base / Foundation (Description) 1. Ground Preparation • The land must be excavated, filled with at least 45 cm murrum, and leveled properly. 2. Pole Foundation • Galvanized Iron (GI) pipes must be fixed in the ground using cement concrete. • Hole size for each pole: 0.45 m × 0.45 m × 0.50 m deep. • Distance between two poles should not be more than 3 meters. 3. Side Brick Wall • A small brick wall of 20 cm height and 20 cm width should be built around the entire structure. 4. Center Path • In the middle of the polyhouse, a path of interlocking pavement blocks should be made. • Path size: 17.88 m × 1.50 m. 5. Plant Beds • Beds should be built on both sides of the path. • Beds should be made using brickwork and plastered. • Beds should be placed at 90° (right angle) to the path. • Each bed: • Inner width: 1 meter • Side wall height: 20 cm • Distance between two beds: 35 cm (including sidewalls). • The gap between two bed walls should be filled with M-20 cement concrete, and plaster should be done on all brickwork. 3. Structure (Simple Description) 1. Material • Entire structure should be made from Galvanized Iron (GI) steel, hot-dip galvanized. • Structure must follow IS 875 standard and withstand 120 km/h wind speed. 2. Poles and Pipes • Main column GI pipes: 1.5 inch x 1.5 inch square pipes • Arch base GI pipes: 1.5 inch x 1.5 inch square pipes • Purlins: 1.5 inch x 1.5 inch square pipes • Remaining structure pipes: 2 inch x 2 inch square pipes • All GI pipes should be fixed into cement concrete in the ground. 3. Door • 2 Aluminium frame doors with 6mm polycarbonate sheet. One door should be at front and the other at the back 4. Distance Between Columns • Maximum 3 meters. 4. Cladding (Covering Materials) 1. Poly Film • 200-micron UV-stabilized film • More than 80% light transmission • From a major/reputed brand 2. Insect Net • 40-mesh insect net on both long sides • Net height: from 1 meter above ground up to 2.5 meters • Poly film in net area should be foldable to allow airflow. 3. Shade Net • Shade-net curtains should be fixed inside the polyhouse to cover plant beds when needed. 5. Overhead Irrigation / Fogger System • Hanging foggers with lateral pipes, supporting wire, and MS support frame. • Fogger parts must be from a major/reputed brand. • 1 HP pump should be provided. • 1000-liter water tank for fogger supply.
Drip Irrigation System - The project requires the setup of two independent systems: • Site 1: Installation for 500 beds. • Site 2: Installation for 100 beds. • Scope of Work and Materials Required Your quote must cover all labor, materials, and installation for the following requirements: 1. Bed Irrigation Setup (for all 600 beds): • Bed Dimensions: 10 meters (length) x 0.15 meters (width) x 1.20 meters (height). • Drip Lines: Four parallel drip line per bed, which may extend in length to consecutive beds. Emitter (dripper) spacing of drip lines should be 6 inch • Fittings: All necessary 16mm pipes, O-rings, take-ups, and 16mm valves connecting to the main line. 2. Underground Main Supply Line: • Pipe: 75mm diameter, 4-gauge PVC pipe. • Installation: Pipe must be installed 1 meter below ground level. • Total Length: Approximately 550 meters of underground piping across both sites • Water Source Setup: Supply and installation of a 5000-liter water tank. • Pumping: Supply and installation of a 5 HP motor. • Filtration & Fertigation: Installation of a Screen Filter, a Sand Filter, and a Venturi injector system for fertilizer application. 4. Site 2 Specific Equipment (for 100 beds location): • Water Source Setup: Supply and installation of a 1000-liter water tank. • Pumping: Supply and installation of a 3 HP motor. • Filtration & Fertigation: Installation of a Screen Filter, a Sand Filter, and a Venturi injector system for fertilizer application. • Valves to be provided as per requirement for sectorwise irrigation
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
td.pdf
Tender Documents • 2.70 MB
BOQ_562513.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .