| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹82.2 LAccepted-Finance | L1 | Accepted-Finance QUALIFIED | |
| 2 | L2₹85.9 L+₹3.7 L (4.49%)Accepted-Finance | L2 | Accepted-Finance QUALIFIED | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹82 L
EMD Value
₹82,000
Closing Date
22 Jun 2024, 11:00 amClosed
SE, EDC-II, BULANDSHAHR.
SE, EDC-II, BULANDSHAHR.
INCREASING CAPACITY OF TRANSFORMER AND OTHER WORK IN BUSINESS PLAN UNDER EDD-IV, SYANA.
2024_PVVNL_928888_1
93/EDC-II/BSR/2023-24
Open Tender
Electrical Works
Lump-sum
30 days
BULANDSHAHR
INCREASING CAPACITY OF TRANSFORMER AND OTHER WORK IN BUSINESS PLAN UNDER EDD-IV, SYANA.
2 documents required · 2 mandatory
₹3,540
SE, EDC-II, BULANDSHAHR
₹82,000
27 Jun 2024
14 Jun 2024
22 Jun 2024
14 Jun 2024
22 Jun 2024
14 Jun 2024
Amount
Carriage of fallowings from ESC BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, required ccompletion of work, distance about to 0 to 70 Km. approx.
STP Pole 13 Mtr Long
PCC Pole 11 Mtr Long
Pcc Pole 8.5 Mtr Long
Carriage of ACSR Weasal/Dog Conductor, AB Cable, LT XLPE Cable, G.I. Wire, 11 KV XLPE Cable, 33 KV Disc Insulator with fitting & 11 KV Disc insulator with fitting, 33 Pin Insulator with pin & 11 KV pin insulator with pin, 33 KV V-Type X-arm & 11 KV V-Type Cross Arm, M.S. Channel-Angle, Earthing Rod, Stay Set Complete & Etc as per RESPO Norms.
25 KVA Transformer
63 KVA Transformer
100 KVA Transformer
250 KVA Transformer
10 KVA Single Phase TF
The following meterial Erection & Fixing as per RESPO manual. It including the cost of labour, T&P, Carrier etc. required for proper completion of work.
Single support on PCC pole 8.5 Mtr. Long with all accessories.
Single support on STP Pole 13/PCC 11 Mtr Long with all accessories
Making of D/P for T/F on PCC pole 8.5 Mtr. Long.
Grouting concreting & Plinthing of STP/Pcc Pole as per RESPO norms.
Fixing erection & grouting of Stay set complete with binding & Nozzling of Stay wire.
Earthing of supports with the help of Earthing rod & GI wire/Earth wire.
Laying stringing & sagging of Dog conductor in 3 phase
Laying stringing & sagging of Rabbit conductor in 3 phase
Laying stringing & sagging of Weasal conductor in 3 phase
Laying stringing & sagging of 11 KV 3x120 sq mm XLPE Cable
Laying stringing & sagging of LT XLPE Cable 3.5x240 sq mm
Laying stringing & sagging of AB Cable (3X50 + 1X35+1X16) sq.mm
Laying stringing & sagging of AB Cable (3X95 + 1X70+1X16) sq.mm
Laying stringing & sagging of AB Cable (3X120+1X95+1X16) sq. mm
Installation of 25 KVA Transformer
Installation of 63 KVA Transformer
Installation of 100 KVA Transformer
Installation of 250 KVA Transformer
Installation of 10 KVA Single Phase TF
Making of Plinth of 250 KVA Transformer.
Earthing of 250 KVA T/F water level
Fencing of 250 KVA T/F
Laying stringing & sagging of G.I. Wire 3.15 mm 10 SWG
Laying stringing & sagging of G.I. Wire 4 mm 6 SWG
Fixing of Gurding M.S. Angle 65x65x6mm)/1.6 meter
Installation of Distribution Box
Grouting of Pole
Providing & Fixing of the following material by the Contractor as per UPPCL/RESPO Rules.
Gurding M.S. Angle 65x65x6mm)/1.6 meter
Distribution Box
MS Channel (Dropper) 100x50x2028
MS Angle 75x75x6x2028 mm
M.S. Top Channel (125x65x2240 mm)
MS T-off Channel 125x65x1300 mm
F-Clamp
11 KV Cross Arm Holding Clamp
33 KV Cross arm Holding clamp
Danger Board with Clamp
Stone Pad
Clamps for D.B. (40x6 mm)
Clamps for 10 KVA T/F (75x8 mm)
Clamp for D/P
Nut & Bolt
DEAD END CLAMPS WITH I-HOOK (INSULATED)
LT PIERCING CONNECTOR
SUSPENSION CLAMPS WITH I-HOOK (INSULATED)
Clamp for Gurding MS Angle
Earthing Rod
The fallowings matarial dismantalling & Carriage from site to ESC BSR including loading and unloading chagres at both ends, required ccompletion of work, distance about to 0 to 70 Km. approx.
ACSR Weasal/Rabbit Conductor (Scrap) -
G.I. Wire (Scrap) -
XLPE/AB Cable (Scarap / Old And Damaged)
ST POLE 11 MTR LONG (Iron scrap)
1. Nut, Bolt, Clamps and others necessary items should be provided by contractor. 2. T and P should be and other necessary machinery should be provided by contractor. 3. All the MS Items must be Galvanized. All work will be done as per UPPCL/RESPO Rules and these work will be inspected by TPIA or any departmental authority.
Vivek Electricals
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .