| Sl No | Description | Qty | Unit | gowthaman L2 | elangovan L1 |
|---|---|---|---|---|---|
| 1.00Arcot Block | |||||
| 2.00Strengthening of the road from K.velur Road to Karivedu ADC Km 0/0 - 0/700 (R-156) VPR in Arcot Block Ranipet District | |||||
| 3.00Clearing the scrub jungles including cutting the scrubs and removing away from site etc complete] | |||||
| 4.00 | KM 0/0-0/610 | 439.2 | /sqm | 8 ₹3,513.6 | 5 ₹2,196 Lowest |
| 5.00Picking 5 Cm to 10 cm of existing wornout BT / WBM Surface sectioning in all labour charges etc complete | |||||
| 6.00 | KM 0/0-0/610 | 762.5 | /sqm | 25 ₹19,062.5 | 20 ₹15,250 Lowest |
| 7.00Earthwork excavation in all classes of soils and subsoils including shoring and strutting with initial lead and lift etc complte, as per MOST specification asper SS20 A. | |||||
| 8.00 | KM 0/0-0/610 | 109.8 | /Cum | 130 ₹14,274 | 120 ₹13,176 Lowest |
| 9.00collection and supply of carted earth from approved quarry including cost and conveyance of all materials to site inclunding charges for spreading and compaction with power roller etc complete for shoulders | |||||
| 10.00 | KM 0/0-0/610 | 109.8 | /Cum | 136 ₹14,932.8 | 130 ₹14,274 Lowest |
Tender Value
₹18.7 L
EMD Value
₹19,000
Closing Date
24 Sept 2025, 3:00 pmClosed
Block Development Officer
Block Development Officer Arcot Block Ranipet District
Strengthening of Road From K. Velur Road to Karivedu ADC KM 0/0 - 0 / 700 (R -156 ) VPR in Arcot Block Ranipet District
2025_RDTN_602261_1
A1/3265/2025
Open Tender
Civil Works
Item Wise
240 days
Block Development Officer
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹19,000
11 Oct 2025
10 Sept 2025
24 Sept 2025
10 Sept 2025
24 Sept 2025
10 Sept 2025
Amount
Arcot Block
Strengthening of the road from K.velur Road to Karivedu ADC Km 0/0 - 0/700 (R-156) VPR in Arcot Block Ranipet District
Clearing the scrub jungles including cutting the scrubs and removing away from site etc complete]
Picking 5 Cm to 10 cm of existing wornout BT / WBM Surface sectioning in all labour charges etc complete
Earthwork excavation in all classes of soils and subsoils including shoring and strutting with initial lead and lift etc complte, as per MOST specification asper SS20 A.
collection and supply of carted earth from approved quarry including cost and conveyance of all materials to site inclunding charges for spreading and compaction with power roller etc complete for shoulders
Providing & Laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 125mm thick specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in sub base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges rentals for machinery, fuel and all other incidental charges etc, completed as per clause of MORTH Rev-5.
Applying Prime coat over WMM surface using 7 kgs of bitumen emulsion (SS1) per 10 sqm for preparatory to another bituminous construction over it including cost of bitumen emulsion including conveyance of bitumen emulsion to actual workspot handling charges including labour charges for brushing , cleaning and preparing the surface for laying the required quantity of bitumen emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges as per Clause 502 of MORTH Rev-5.
Applying Tack coat over WMM surface using 2.50 kgs of bitumen emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of bitumen emulsion including conveyance of bitumen emulsion to actual workspot handling charges including labour charges for brushing , cleaning and preparing the surface for laying the required quantity of bitumen emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges as per Clause 502 of MORTH Rev-5
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Provision for Hectometer stone
GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package}
gowthaman (BID ID -1458163)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .