| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 LAccepted-Finance NOCHIPALAYAM AUTHUR PO KARUR 2 | L1 | Accepted-Finance 1st lowest bidder | |
| 2 | L2₹3.0 L+₹53,415.44 (21.4%)Accepted-Finance | L2 | Accepted-Finance Other than the lowest bidder | |
| 3 | Not Admitted-Fee/PreQual/Technical/Finance | - | Not Admitted-Fee/PreQual/Technical/Finance Others-Additional Security Deposit copy not uploaded | |
| 4 | Not Admitted-Fee/PreQual/Technical/Finance | - | Not Admitted-Fee/PreQual/Technical/Finance Others-WRD Registration certificate copy not uploaded | |
| 5 | Not Admitted-Fee/PreQual/Technical/Finance | - | Not Admitted-Fee/PreQual/Technical/Finance Others-Additional Security Deposit copy not uploaded |
Tender Value
₹3.6 L
EMD Value
₹3,600
Closing Date
11 Nov 2026, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
The Executive Engineer, WRD
O/o the Executive Engineer, WRD, Mettur Dam Division, Mettur Dam-1
Special repairs to the canal reach from mile 0/2 to 0/3 in the Distributory at mile 19-2-300 of Mettur West Bank Canal.
2026_WRD_716694_1
NIT NO.04/DB/MDD/2026-27
Open Tender
Civil Works
Lump-sum
90 days
Distributory at mile 19-2-300 of Mettur WBC
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹3,600
20 Nov 2026
22 Oct 2026
12 Nov 2026
22 Oct 2026
11 Nov 2026
22 Oct 2026
90 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing the scrub jungle including removal of roots and disposing off etc., complete complying with standard specification and as directed by the departmental officers. | 400 | m2 | 6.36 | ₹2,544 |
| 2 | Earthwork excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc., complete complying with standard specification and as directed by the departmental officers. | 12 | m3 | 131.89 | ₹1,582.68 |
| 3 | Plain Cement Concrete 1 : 4 : 8 (One Cement, four sand and Eight metal) using 40 mm jelly for foundation and basement including dewatering if found necessary and laid in layers of not more than 15cm tk etc.,complete complying with standard specification and as directed by the departmental officers | 7 | m3 | 5,582.3 | ₹39,076.1 |
| 4 | Reinforced Cement Concrete 1:2:4 (One Cement, Two M.sand and Four hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for retaining walls excluding cost of reinforcement grill and fabricating charges, centering and shuttering including laying, curing & finishing etc., complete complying with standard specification and as directed by the departmental officers | 10 | m3 | 8,600.3 | ₹86,003 |
| 5 | Supplying and erecting steel centering for sides and soffits including supports and strutting upto 3.0m height for Plain surfaces such as reinforced cement slabs using MS sheets of size 90 X 60 cms and "B.G.10" gauge, stiffened with M.S angles of size 25 X 25 X 3 mm by boarding laid over silver oak (country wood) joists of size 10 X 6.5 cms (spaced at about 90 cms centre to centre) and supported by casurina props of size 10 to 13 cms dia (spaced at 75 cm centre to centre at suitable intervels) etc., complete complying with standard specifications and as directed as directed by the departmental officers. | 55 | m2 | 1,089.1 | ₹59,900.5 |
| 6 | Supplying, fabricating and placing in position of RTS steel rods for all R.C.C works as per the design given including cost of steel and binding including cost of steel and binding wire etc., complete complying with standard specification. (The contractor will have to make his own arrangements for the supply of MS Plain Rod/RTS Rod and binding wire) for the work to work site as per GOMS. No. 303/PW(R1/Dept/Dt. 26.05.1998 & got tested before use on the work. | 3.2 | qtl | 9,190.25 | ₹29,408.8 |
| 7 | Earth work excavating and depositing on bank with a lead of 6 km in hard stiff clay,stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders including watering and consolidating etc. complete complying with standard specification and as directed by the departmental officers. | 410 | m3 | 202.6 | ₹83,066 |
| 8 | GST 18% | 25 | Nos | 5 | ₹125 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
finance_860926.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.41 MB
BOQ_860926.xls
BOQ • 0.37 MB
Condition8.pdf
Tender Documents • 0.70 MB
8C192300.pdf
PDF • 0.13 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .