| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹49.1 LAccepted-AOC NO 5 2 3 CV NAIDU SALAI THIRUVALLUR TAMILNADU 602001 | THIRUVALLUR | TAMIL NADU | 602001 | ₹49.1 L | L1 | Accepted-AOC L1 |
| 2 | L2₹50.0 LRejected-AOC NO 164 HARERAM NAGAR RAJAJIIPURAM TVLR 602 001 | TIRUVALLUR | TIRUVALLUR | TAMIL NADU | 602001 | ₹50.0 L | L2 | Rejected-AOC L2 |
| 3 | Rejected-Technical NO 134 BETHANAYAKKANPETTAI UTHUKOTTAI TALUK ATHIVAKKAM TIRUVALLUR 601102 | ATHIVAKKAM | TIRUVALLUR | TAMIL NADU | 601102 | - | - | Rejected-Technical Disqualified |
| 4 | Rejected-Technical | - | - | Rejected-Technical Disqualifed |
| 5 | Rejected-Technical | - | - | Rejected-Technical Disqualified |
| Sl No | Description | Qty | Unit | M/S.J M Constructions L2 | KUMARAN ENGINEERING ENTERPRISES L1 |
|---|---|---|---|---|---|
| 1.001. MODERNIZATION OF GOVERNMENT ADW PG COLLEGE BOYS HOSTEL PONNERI @ PONNERI PANCHAYAT IN THIRUVALLUR DISTRICT UNDER CSR | |||||
| 2.00 | Brickwork in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site mixing, palcing, curing and all labour charges etc. completed. | 3.27 | CUM | 6,500 ₹21,255 Lowest | 6,513 ₹21,297.51 |
| 3.00 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work. | 42.5 | SQ.M | 310 ₹13,175 Lowest | 310 ₹13,175 Lowest |
| 4.00 | Plastering in CM 1:5 mix, 12mm thickness including cost and conveyance of all materials to work site from approved quarry sources and labour charges etc. completed. | 36.9 | SQ.M | 288 ₹10,627.2 Lowest | 290 ₹10,701 |
| 5.00 | Supply and Fixing of mosquito net including all cost of labour charges As per Market Rate | 45.64 | SQ.M | 1,500 ₹68,460 Lowest | 1,510 ₹68,916.4 |
| 6.00 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer | 1,729.39 | SQ.M | 150 ₹2,59,408.5 Lowest | 151 ₹2,61,137.89 |
| 7.00 | Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358 | 2,238.02 | SQ.M | 268 ₹5,99,789.36 Lowest | 280 ₹6,26,645.6 |
| 8.00 | Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) | 306.11 | SQ.M | 159 ₹48,671.49 Lowest | 160 ₹48,977.6 |
| 9.00 | Floor finish and dadooing walls in cement mortar with
Mosaic Tiles / Glazed Tiles / Clay Tiles / Cuddapah Slabs | 157.77 | SQ.M | 66 ₹10,412.82 Lowest | 69 ₹10,886.13 |
| 10.00 | Dadooing walls with following best approved quality, white / colour glazed tiles of following sizes set in Cement Mortar 1:2 (One Cement and Two crushed stone M.Sand) 10mm thick and pointing the joints with white cement mixed with colouring pigments at the rate of 0.40 Kg. / sq.m. neatly in all floors, curing, etc., complying with standard specification and as directed by the departmental officers. | 135.63 | SQ.M | 1,435 ₹1,94,629.05 Lowest | 1,435 ₹1,94,629.05 Lowest |
Tender Value
₹50 L
EMD Value
₹50,000
Closing Date
26 Feb 2026, 3:00 pmClosed
Project Director/Joint Director
DRDA Tiruvallur
Modernization of Government ADW PG College Boys Hostel Ponneri at Ponneri Town Panchayat in Tiruvallur District Pac.02
2026_RDTN_659130_1
2955/2025/A2 dt.16.02.2026
Open Tender
Civil Works
Item Rate
120 days
Ponneri
As per eligible criteria
5 documents required · 5 mandatory
₹0
₹50,000
Yes
8 May 2026
17 Feb 2026
26 Feb 2026
17 Feb 2026
26 Feb 2026
18 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 1. MODERNIZATION OF GOVERNMENT ADW PG COLLEGE BOYS HOSTEL PONNERI @ PONNERI PANCHAYAT IN THIRUVALLUR DISTRICT UNDER CSR | - | - | - | - |
| 2 | Brickwork in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site mixing, palcing, curing and all labour charges etc. completed. | 3.27 | CUM | 6,513.37 | ₹21,298.72 |
| 3 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work. | 42.5 | SQ.M | 308.85 | ₹13,126.13 |
| 4 | Plastering in CM 1:5 mix, 12mm thickness including cost and conveyance of all materials to work site from approved quarry sources and labour charges etc. completed. | 36.9 | SQ.M | 288.73 | ₹10,654.14 |
| 5 | Supply and Fixing of mosquito net including all cost of labour charges As per Market Rate | 45.64 | SQ.M | 1,500 | ₹68,460 |
| 6 | Distempering the old walls and ceiling one coat with best oil bound distemper of approved quality including preparation of surfaces (the colour and quality should be got approved by the Executive Engineer before use) the rate includes cost of brushes, high scaffolding charges, neat finishing, cost of brushes etc., complete complying with standard specification and as directed by the Departmental Officer | 1,729.39 | SQ.M | 150.42 | ₹2,60,134.84 |
| 7 | Re Painting the walls with Two coats with first class quality Plastic Emulsion paint of approved colour over a priming coat including thorough scraping, clean removal of dirt. The rate includes cost of brushes, sand paper, plaster of parries, putty wherever required and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) S I No 358 | 2,238.02 | SQ.M | 267.42 | ₹5,98,491.31 |
| 8 | Painting the old iron works two coats with syntactic enamel paint of approved quality and colour including ordinary scraping using brushes and neat finishing etc., complete complying with standard specification and as directed by the Departmental Officer (the colour and quality should be got approved by the Executive Engineer before use) | 306.11 | SQ.M | 159.23 | ₹48,741.9 |
| 9 | Floor finish and dadooing walls in cement mortar with
Mosaic Tiles / Glazed Tiles / Clay Tiles / Cuddapah Slabs | 157.77 | SQ.M | 65.56 | ₹10,343.4 |
| 10 | Dadooing walls with following best approved quality, white / colour glazed tiles of following sizes set in Cement Mortar 1:2 (One Cement and Two crushed stone M.Sand) 10mm thick and pointing the joints with white cement mixed with colouring pigments at the rate of 0.40 Kg. / sq.m. neatly in all floors, curing, etc., complying with standard specification and as directed by the departmental officers. | 135.63 | SQ.M | 1,434.25 | ₹1,94,527.33 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.41 MB
TechBidADWMJR02.pdf
Tender Documents • 0.75 MB
PriceBidADWMJR02.pdf
Additional Documents • 0.28 MB
BOQ_790783.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].