| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹24.0 LAccepted-Finance | 1 | Accepted-Finance L1 Bidder | |
| 2 | 2₹24.4 L+₹41,117.50 (1.72%)Rejected-Finance | 2 | Rejected-Finance Second Lowest Bidder | |
| 3 | 3₹24.6 L+₹63,426.25 (2.65%)Rejected-Finance | 3 | Rejected-Finance Third Lowest Bidder |
Tender Value
Refer Docs
EMD Value
₹48,000
Closing Date
5 Jan 2021, 10:20 amClosed
AQMG HQ 8 SECT RR
HQ 8 SECT RR PIN-934708 C/o 56 APO
Constr of First Floor of AGS Krusan with Five Classrooms and furniture
2020_ARMY_407648_1
15/AG/113
Limited
Construction Works
Works
60 days
47 RR Bn
2 documents required · 2 mandatory
₹0
₹48,000
Yes
5 Jan 2021
29 Dec 2020
5 Jan 2021
29 Dec 2020
5 Jan 2021
29 Dec 2020
29 Dec 2020 - 5 Jan 2021
Amount
Brick work with FPS bricks of class design 75 in 1:16 mix including extra and all carriages comllete. Wall = 1 x 368'-6" x 0'-9" x 9'-0"=2487.37Cft Pillers = 14 x 14" x 14" x 9'-0"=169.54 Total = 2656.92 Cft Deductions Doors = 05 x 4'-0" x 0'-9" x 8'-0"=120.00 Cft Windows = 1 x 20 x 5'-0" x 0'-9"-6"=412.50 Total = 532.50 Cft NetBrik Work Qty =2656.91-532.50=2124.41 Cft = 60.00 Cum
Providing and fixing of door / window / vent frames, rough chowkats of Popular / KD wood. Door = 05 x 25'-0" x 3" x 5" = 13.02 Cft Windows = 20 x 39'-0" x3" 5" = 81.24 Total = 94.26 Cft = 2.66 Cum
Centering & Shuttering incl. Strutting, propping etc. & removal of form work for: (a) Sill / Lintels, beams etc. 2 x 368'-6" x 0'-12" = 737.00 Sft 1 x 122'-3" x 1'-0" =122.25 1 x 132'-0" x 1'-0" = 132.00 Total = 991.25 Sft =92.00 Sqm
(b) Suspended floors etc. Slabs = 1 x 2975.00 Sft = 2975.00 Sft 276.00 Sqm
Reinforced cement concrete work in beams, suspended floors, roofs, landings, columns, balconies etc. Uto floor v levels in 1:1.5:3 mix excl cost of centering and shuttering using 20 mm graded stone agg. Lintel band = 1 x 368'-6" x 0' -9" x 0'=9" = 207.28 Cft Beam = 1 x 132'-0" x 1'-0" x 1'-0" = 132.00 Slab = 1 x 112'-3" x 26'-6" x 0'-5" = 1219.59 Total 1558.87 Cft = 44 cum
Providing and fixing Popular / KD wood members CGI roof base structure asvertical posts, MS bottom plate, tie beams, king posts, rafters, purlins, struts, clets Total = 706 Cft = 20 Cum
Providing / fixing 26 gauges CGI colour coated laminated sheets of class IIIrd with G.I. Nuts, bolts, limp set washers etc. Over the truss as roof. Complete Plinth area of structure = 225.70 SM X 1.50 (due to site constraint's) = 338.55 SM
Supply / providing aesthetic superior quality Plastic Chairs and table (2ft x 4 ft) for facility members
Fabrication / providing of steel structural base membered wood impregnated table and chairs members for the students in desketed from (3 ft x 5 ft)
M/S ADDEM ENGINEERING
M/S SHEIKH NADEEM AKBAR
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .