Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹75,000
Closing Date
5 Nov 2022, 3:00 pmClosed
SUBHAMCHAKRABORTY
Retail Ops. Northern Region, Bharat Petroleum Corporation Limited
CIVIL WORK AT RAILWAY SIDING FOR INSTALLATION OF APPROACH TO WFM AT JOBNER INSTALLATION
7109
1000394601
Limited Tender
Works
Retail Ops. Northern Region
₹75,000
10 Nov 2022
21 Oct 2022
5 Nov 2022
21 Oct 2022
5 Nov 2022
21 Oct 2022
22 Oct 2022 - 31 Oct 2022
CIVIL AND STRUCTURAL WORKS.
1. The method of measurement shall be as per latest revision of IS:1200 unless otherwise
2. Providing and operating necessary measuring and testing devices and materials including all
consumable are included in the scope of work. No separate measurement or payment for testing
the work shall be made and rates quoted for various items shall be deemed to include the cost
of such tests, which are required to ensure specific quality.
3. All materials shall be of standard quality, manufactured by renowned concerns conforming
to Indian Standard or equivalent and shall have IS mark as far as possible unless otherwise
approved by the Site-in-charge, prior to procurement and use. The Contractor shall furnish
manufacturer's certificates for the materials supplied by him when asked for. Further to that he
shall get the materials tested from an approved lab if
asked for by the Site-in-charge. The cost for all the tests and test certificate shall be borne by
the contractor. Any materials procured or brought to site and not conforming to specifications
and satisfaction of Site-in-charge shall be rejected
4. Wherever referred to in this tender document, only the latest revision which shall be in force
till the completion of work, of specifications, Codes of Practice and other publications of
Bureau of Indian Standards shall be applicable.
5. Wherever the contractor executes civil and structural works involving building, equipment
foundations, supporting structures, pipe racks etc., the following works are deemed to have
been included in the quoted rates for various works.
a) Marking of centre lines of foundations.
b) Marking of top levels of foundations, floors etc. and establishment of reference lines, bench
marks on various floors, platforms etc.
c) Preparation of "As built" scheme of structural foundations, equipment foundations etc.
6. The schedule of rates, specifications and drawings shall be read
in conjunction with each other and in case of conflict amongst
them, clarification shall be obtained from the Site-in Charge,
whose decision shall be final and binding.
SPECIFICATION FOR MATERIALS
Water used for cement concrete, mortar, plaster, grout, curing or washing of coarse aggregate
shall be clear and free from excess amounts of oil, acids, alkalis, organic matters or other
harmful substances in such amounts that may impair the strength or durability of the structure.
Potable water shall generally be considered satisfactory for preparation of mortar, concrete mix
and curing of brickwork, plaster, concrete etc.
The Site-in-charge may require the Contractor to get the water tested from an approved
laboratory at latter's expense and in case the water contains excess of acid, alkali or salt etc.,
the Site-in-charge may refuse to permit its use.
Coarse and fine aggregates for concrete shall conform in all respects to IS:383.
Aggregates shall be obtained from a source known to produce these satisfactorily. These shall
be chemically inert, hard, strong, dense, durable, clean and free from excess amounts of alkalis,
vegetable matter and other deleterious substances. Flaky and elongated pieces shall not be used.
Coarse aggregate is aggregate most of which is retained on 4.75 mm IS sieve. It shall have a
specific gravity not less than 2.6.
Fine aggregate is aggregate most of which passes through 4.75 mm IS sieve but not more than
ten percent (10 %) pass through 150 micron IS sieve.
The Site-in-charge may require the Contractor to carry out tests at the
Contractor 's expense, in accordance with IS : 516 (Methods of test for
strength of concrete )and IS:2386 (Methods of test for aggregates for
3.0 SAND FOR FILLING
Sand for filling shall be medium coarse hard, strong free from any organic and deleterious
materials. Any sand (Fine/Coarse) proposed, shall be used only after it is approved by the Site-
The cement used shall be ordinary Portland cement conforming to IS:269 or Portland
Pozzolana Cement Conforming to IS : 1489 (Part-I, 1991) or Portland Slag Cement
Conforming to IS:455 unless otherwise specified.
RECEIPT AND STORAGE OF CEMENT BAGS
It must be ensured that the cement being received at site is as fresh as possible by checking the
batch no. with the supplier's test certificate which should accompany the cement. Generally
cement more than 120 days old shall not be used. Before receiving cement it should be ensured
that a proper cement godown is constructed by the contractor.
The godown shall be weather tight, and of proper ventilated structure. Wooden battens or ball
is shall be laid on the floor so that a gap of atleast 15 cm is available between the floor and
cement bags. The cement bags may be stacked upside down at least once in 60 days to avoid
slump formation. While receiving cement following precautions must be taken.
Bags should not be wet /partially or fully set. The cement shall be stored as per IS :4082-1977.
Relevant excerpts of IS:4082 are as given below. At least 60 cm space should be kept between
walls and stacks. Cement bags should be stacked close so as to avoid air circulation to the
extent possible. Maximum 10 bags shall be stacked in one stack. Cement of different types and
brands shall be kept in separate stacks to ensure usage on first in first out basis. For extra safety
in monsoon, polythene sheet shall be used to cover the bags.
All reinforcement and structural steel shall conform to the following:
5.1 REINFORCEMENT STEEL
- IS : 1139 Hot rolled deformed bars
- IS : 1786 Cold twisted bars
- IS : 432 Mild Steel round bars (Grade - I)
- IS : 1566 Hard drawn steel wire fabric.
5.2 STRUCTURAL STEEL
- IS : 226/2062 Hot rolled sections and plates
- IS : 1079 Cold formed light gauge sections
- IS : 432 Mild Steel round bars (Grade - I)
- IS : 4923 Hollow sections (rectangular or square)
5.3 OTHER BARS AND SECTIONS:
Any other type of reinforcement bars and structural sections specified on the drawings shall
conform to respective Indian Standard Codes.
The reinforcement and structural steel shall be stored in such a way as to avoid and prevent
deterioration and corrosion.
SPECIFICATION FOR EARTHWORK
1.0 CLASSIFICATION OF SOIL
1.1 SOFT/LOOSE SOIL
Generally any soil which yields to the ordinary application of pick and shovel or to phawra or
other ordinary digging implement; such as sand, silt, loam, clay, peat etc.
1.2 HARD/DENSE SOIL
Generally any soil which requires the close application of pick, or jumper or scarifier to loosen
such as stiff clay, gravel and cobble stone.
1.3 SOFT/DISINTEGRATED ROCK
Rock or boulder may be quarried or split with crowbar. This will also include laterite & hard
1.4 HARD ROCK (REQUIRING BLASTING)
Any rock or boulder for the excavation of which blasting is required.
1.5 HARD ROCK (REQUIRING CONTROLLED BLASTING)
Due to any reason, if general blasting is prohibited, then for excavating these rocks, controlled
blasting as approved by the Site-in-charge shall be used.
1.6 HARD ROCK (BLASTING PROHIBITED)
Hard rock requiring blasting as described under 1.4 but where blasting is prohibited for any
reason and excavation has to be carried out by chiselling, wedging or any other agreed method.
2.0 BACKFILLING MATERIAL
Backfilling material shall be as approved by the Site-in-charge. Back filling of excavations in
trenches, foundations and elsewhere shall consist of one of the following materials as the Site-
in-charge may direct in each location.
(ii) Selected earth from heaps or brought from borrow areas.
(iii) Stone/gravel
(v) Lean concrete
The material shall be free from rubbish, roots, hard lumps and any
other organic material.
3.0 EARTHWORK IN EXCAVATION
Excavation shall be carried out in any material encountered on the site to the lines, levels and
contours shown on the detailed drawings and the Contractor shall remove all excavated
materials to soil heaps on site or transport for use in filling the site or stack for reuse as directed.
Excavated material shall not be deposited within 1.5M from the top edge of the excavation.
The sides of the excavation may be cut sloping or shored and strutted to hold the face of earth
as per site requirements and as directed by the BPCL's Site-in-charge. The Contractor shall
remove all vegetation, shrubs etc. encountered during excavation. Foundation pits/trenches
shall not be excavated to the full depth unless construction is imminent. The last 15 cm depth
of the excavation shall not be removed until concreting work is imminent. The full depth may
at the discretion of the Site-in-charge be excavated and the bed covered with a seventy five
(75) mm (minimum) thick (or as indicated on the drawing) layer of lean concrete 1:5:10 mix
(1 Cement: 5 Coarse Sand: 10 Crushed Stone Aggregates) or as specified in schedule or rates.
The Contractor shall provide suitable drainage arrangement to prevent surface water from any
source entering the foundation pits at his own cost.
Where excavation is made in excess of the depth required, the Contractor shall at his own
expense, fill upto required level with lean concrete 1:5:10 mix or as decided by Site-in-charge.
Lowering of water table by well-point pumping shall be paid separately. The Contractor shall
make necessary arrangements for lighting, fencing and other suitable measures for protection
against risk of accidents due to open excavation at his own expense. Where the excavation is
to be carried out below the foundation level of an adjacent structure, the precaution to be taken
such as under pinning, shoring and strutting etc. shall be determined by the Site-in-charge. No
excavation shall be done unless such precautionary measures are carried out. The payment for
such precautionary measures shall, however, be made separately unless the rate for such
measures are specifically included in the rates for items of excavation. Loose or soft bed ground
encountered in excavation at the required depth shall be excavated to a firm bed and difference
made up to the required level with lean concrete 1:5:10 mix or as decided by the Sitein-
charge. Any obstacle encountered during excavation shall be reported immediately to the Site-
in-charge and shall be dealt with as instructed by him. Removal of buried pipes or cables shall
be done with prior permission of BPCL's Site-in-charge and the Contractor shall provide
all measures to protect the same. Cost of such protective measures are deemed to be included
in the rates for various items of excavation. The Contractor shall not undertake any concreting
in foundation until the excavation pit/trench is approved by the Site-in-charge.
3.1 The specification for earthwork shall also apply to excavation in rock in general. The
excavation in rock shall be done such that extra excavation beyond the required width and
depths as shown in drawing is not made. If any extra excavation particularly in depth is made
by the Contractor during the excavation operation, the Contractor shall make up such extra
excavations with concrete 1:5:10 mix to the required levels and shaped at no extra cost to the
3.2 In case of hardrock requiring blasting, the provisions mentioned below
shall be strictly followed.
4.0 MEASUREMENT
Payment for earth work in excavation shall be made on cubic meter (m3) basis on the
measurement of volume of pit/trench of excavation as per IS:1200 . The rate shall include cost
of all the operations of blasting, making all arrangements for dewatering, removal and disposal
of surplus earth.
The contractor shall intimate BPCL's Site-in-charge as soon as different soil classifications are
met with. Joint levels shall be taken as to the levels of different soil classifications and volumes
shall be worked out on the basis of levels only. Where levels of different strata cannot be clearly
marked and defined, the contractor shall stack soils separately for measurement purpose and
then dispose it off as directed. If soil of any classification other than that specified in the SOR
is met with during the excavation, the decision of the Site-in-charge as to the classification of
the soil, levels of the strata and their location shall be binding on the contractor.
In the above case, the total quantity of excavation shall be computed from the measurement of
pit/trench excavated. The hard rock and soft rock shall be measured separately from the
relevant stacks and each shall be reduced by 50% for voids, and paid under the relevant items.
The balance, i.e. the total quantity of excavation minus the reduced (for voids) quantity of
excavation for rocks shall be paid as soft/hard soil as per the direction of the BPCL's Site-in-
charge. However the maximum payment shall be limited to the volume of the excavated
pit/trench asapproved.
SHORING AND STRUTTING
The shoring and strutting of the sides to withhold the face of excavation pits/trenches shall be
done as approved by the Site-incharge. Payment for shoring/strutting shall be made on square
meter basis as separate items.
GENERAL PROCEDURE/INSTRUCTIONS
FOR EARTH FILLING IN
DEPOTS/INSTALLATION
1.0 The procedure for earth filling can be divided into following:
1. Quantity of earth filling.
2. Evaluation of earth.
3. Filling procedure.
4. Compaction Test procedure.
5. Measurement of earth filling.
1.1 Quantity of earth filling
To arrive at the quantity of earth to be filled at a particular site, the HFL of the area is transferred
from some permanent bench mark (Railway, Culvert, Bridge etc.) to site and the area
earmarked for filling is divided into no. of grids of 10, 15, 20, 25M spacing depending on
the size of the plot. The reduced levels of various grid points are taken with the help of dumpy
level and are plotted on the land development drawing. Depending on the finished ground level
of the area, the quantity of earth is calculated. The procedure for using dumpy level is as follows
Dumpy level is an instrument with which difference of levels of any 2 points can be found out.
It is very commonly used in surveying for finding the levels and for plotting the contours. From
any known level e.g. permanent benchmark level of any point can be found out. With the help
of dumpy level a horizontal plane (Line of collimation) is formed which is tangent to mean sea
level and by taking height of different points to this line of collimation, level of each point can
For taking level of any point w.r.t. the known Bench Mark (BM), with dumpy level, first take
the height of B.M. reading, you get the level of line of collimation and by reducing the height
of particular point from B.M's reading you get the level of that particular point.
There are two methods of recording the measurements.
(a) Collimation System (H.I.): In this method the level of collimation is found out and then
for each point the reading is reduced and level is found out e.g.
Stn. Chainage Reading Collim- Reduced
Back Inter Fore HI
Sight Sight Sight
To check, if the difference of sum of back sight and fore sight-reading is equal to difference of
1st & last B.M. reading, It is OK
b) Rise & Fall Method:
In this method rise and fall of each point is added or subtracted from B.M. reading to get the
level of particular point e.g.
Stn. Chainage Reading Rise Fall Reduced
Back Inter Fore
Sight Sight Sight
To check the calculation and reading - close the reading on some known B.M. The difference
of back sight and fore sight reading, rise and fall readings and first and last B.M. reading should
be same. If they are not same then adjust the difference in all the readings.
For checking Dumpy Level and correcting the line of collimation, Dumpy level is kept at mid
location of 2 staff locations and, say reading on both the staff is taken as a & b. Then the dumpy
level is shifted in same line towards one staff and then say the reading on both the staff is taken
as a' and b'. If the difference of a, b and a, 'b' is same, the D.L. is OK. If it is different then
adjust diaphragm screw and check by repeating the process.
1.2 Evaluation of Earth
Before finally selecting the particular soil for filling from a quarry, the properties of earth are
tested to ensure its suitability.
(a) Procedure for Testing Soils
For selecting earth for earth filling following tests are conducted to check the suitability of
earth for filling purpose as per IS:2720 (Part-V)
(b) Liquid Limit (LL)
It is the minimum amount of water required to be added to a soil that will just make it to flow
like liquid when jarred slightly:
Wt. of wet soil - Wt. of dry soil
Wt. of dry soil
Most clay soils have LL around 50 - 90%. If sand or silt is added to
clay, its LL is lowered.
(c) Plastic Limit (PL)
It is the moisture content at which a thread of soil can be rolled without
breaking until it is only 3 mm in diameter, when it just begin to
crumble under pressure exerted by hand.
Sands, gravel and peat do not possess plasticity and their PL is zero.
Average PL of clay is 45 while that of silts is
Plasticity Index (PI) = LL - PL
Liquidity Index (LI) = Natural moisture content - PL
(d) Acceptability Criterion
(i) LI & PI should be less than 30 for good soil.
(ii) It should also be checked that the organic impurity level of
selected earth is not more than 2 - 3%.
(iii) Soil having laboratory maximum dry density of less than
gm/cc shall not be used.
(e) Testing Frequency
One test for every 3000 m² of earth filled is required to be carried out.
1.3 FILLING PROCEDURE
Depending upon the depth of earth filling in an area, the numbers of layers are decided. At few
selected points, a reference (constructed of 16mm dia reinforcing bar grouted in cement
concrete) flag with depth of earth filling layers marked on it is installed. Filling is carried out
with approved material in layers, not exceeding 30 cms of loose thickness; watering and rolling
Compaction to 90-95% of maximum dry density can be achieved by any of the following
(I) Using Road Rollers upto capacity of 10MT.
(ii) Using hand rollers.
(iii) Using sheep's foot Roller (can compress upto 35 kg/cm sq.)
(iv) Using Rammer (weighing 3.3 - 4.0 kg).
As per practical experience, Sheep’s foot roller is best suited for earth compaction, while
rammer is best suited for sand. When areas are large, road roller could also be used effectively
in combination with sheep's foot roller. It should be noted that water flooding should always
be avoided while compacting the earth.
1.4 COMPACTION TEST PROCEDURE
The compaction test procedure is as follows:
(a) Laboratory Test
First a test is conducted in laboratory to find density/moisture relation by proctor compaction
test. For this test, cylindrical metal mould of 4" dia x 4 1/2" ht. is used in which soil is filled in
3 equal layers with 24 blows of 2.5 kg. hammer from a height of 30 cm. By changing the
percentage of moisture, we get different dry densities, which can be plotted in the form of
curve. From this curve, relation between maximum dry density and moisture content can be
(b) Procedure of Calculation Dry Density of Soil Samples
The internal volume (Vc) of the core-cutter in ml. shall be calculated from its dimensions which
shall be measured to the nearest 0.25 mm. The core cutter shall be weighed to the nearest gram.
(Wc) A small area approximately 30 cm square of the soil layer to be tested shall be exposed
and levelled. The steel dolly shall be placed on top of the cutter and the latter shall be rammed
down into the soil layer until only about 14 mm of the dolly protrudes above the surface, care
being taken not to rock the cutter. The cutter shall then be dug out of the surrounding soil, care
being taken to allow some soil to project from the lower end of the cutter. The ends of the soil
core shall then be trimmed flat to the ends of the cutter by means of the straight edge. The
cutter containing the soil core shall be weighed to the nearest gram (Ws)
The soil core shall be removed from the cutter and a representative sample shall be placed in
an air-tight container and its moisture content (W) determined as per IS:2720 (Part-II) -
Note: It is necessary to make a number of repeat determinations and average out results, since
the dry density of the soil varies appreciably from point to point. The number of determinations
should be such that an additional one should not alter the average significantly.
The bulk density (Db), that is, the weight of the wet soil per cubic metre shall be calculated
from the following formula:
Ws = weight of soil and core-cutter in g,
Wc = weight of core-cutter in g, and
Vc = volume of core-cutter in ml.
The dry density Dd, that is, the weight of the dry soil per cubic metre
shall be calculated from the following formula:
Db = bulk density, and
w = moisture content of the soil (percent)
Dry density thus calculated should be 90-95% of max. dry density
determined by lab. test.
1.5 MEASUREMENT OF EARTH FILLING
Earth filling should be calculated meticulously to avoid any complications at the latter date.
The various methods of area calculations are as follows:
(1) Average Ordinate Rule
(2) Trapezoidal Rule.
(3) Simpson's Rule.
We shall compare only Trapezoidal rule and Simpson's rule as Average
Ordinate rule is not accurate.
Trapezoidal Rule: The rule is based on the assumption that the figures are trapezoids.
Simpson's rule: It assumes that the short lengths of boundary between
the ordinates are parabolic arcs.
Area of the figure = L [ (Ol + On) + 4 (O2 + O4 + .........On-1) + 2 (O3 +
This rule is applicable only when the number of divisions of the area is even and total number
of ordinates is odd. If there is an odd number of divisions (resulting in even number of
ordinates), the area of the last division must be calculated separately and added to equation.
The results obtained by the use of Simpson's rule are more accurate than trapezoidal rule.
Earth Volume Calculation: This can also be done by using
(i) Prismoidal formula or Simpson's rule for Volume
(ii) Trapezoidal formula.
Prismoidal formula
Here also it is necessary to have an odd number of cross sections. If there are even number of
sections, the end strip must be treated separately, and volume between the remaining section
be calculated by Prismoidal formula.
Trapezoidal Formula
For Volume Calculation, we should use only Simpson's rule (Prismoidal formula) as this is
more accurate than Trapezoidal formula. Sample Calculations of area and volume are enclosed
in Annexure-I for reference.
SPECIFICATION FOR EARTH WORK IN FILLING
1.0 MATERIAL FOR EARTHWORK
1.1 Only Material considered suitable by the Site-in-Charge shall be employed for the
construction and that considered unsuitable shall be disposed off, as directed at his own cost
and no claim for compensation will be entertained.
1.2 The CONTRACTOR shall give the samples of Earth he proposes to use for filling along
with the following characteristics of the samples to Site-in-Charge, prior to collection and use,
for approval. The tests for following characteristics shall be done in a laboratory/test house as
approved by Site-in-Charge.
(i) Mechanical analysis for grain size distribution as per IS:2720 part IV.
(ii) Liquid limit as per IS:2720 Part V.
(iii) Plastic limit as per IS:2720 Part V.
(iv) Moisture density relationship as per IS:2720 Part-VII.
1.3 The material (soil) used for filling shall be free from boulders lumps, tree roots, rubbish or
any organic deleterious matter.
1.4 Material (soil) having plasticity index less than 20 shall be used for filling purpose.
1.5 Soil having laboratory maximum dry density of less than 1.5 gms/cc shall not be used.
1.6 Care shall be taken to see that unsuitable waste material is disposed off in such a manner
that there is no likelihood of its getting mixed with
the material proposed to be used for filling.
2.0 CUTTING TREES
2.1 All trees having girth between 30 cms and 120 cms and which are not marked for
preservation, shall be cut down and their roots dug up to a depth of 1 metre from the existing
2.2 All holes or hollows produced by digging up roots shall be carefully filled with approved
material (soil) including all leads and lifts, rammed and compacted to obtain 90% of maximum
laboratory dry density of soil and levelled as directed.
2.3 All uprooted trees shall be stacked or disposed off as directed by Sitein- Charge.
Cutting of trees above 30 cms girth shall be paid per number. The rate quoted shall include
cutting, uprooting, removing the trees within plant boundary as directed, including filling holes
or hollows produced by removal of roots etc. as per specifications.
3.0 CLEARING AND STRIPPING
3.1 The areas including depressions, where filling or cutting is to be carried out shall be cleared
and stripped completely of bushes, roots, vegetation, plantation trees, shrubs, trees upto 30 cms
girth, organic and other objectionable materials. All these shall be completely uprooted and
virgin soil exposed and not merely scrapped at the surface. The roots of trees of girth upto
cms shall be removed to a minimum depth of 1 M below existing ground level and holes,
hollows filled up with selected approved available earth within all leads and lifts, and
compacted to obtain 90% of laboratory dry density of soil and levelled as directed by Site-in-
Charge. All soft patches must be worked out to remove soft soil and selected approved Earth
Must be filled back and the areas (areas coming under filling) compacted to obtain 90% of
maximum laboratory dry density of soil, as per IS:2720 Part-VII. The depth of stripping shall
be generally 50 to 150 mm, as decided by Sitein-Charge.
3.2 Material obtained from clearing shall be stacked or disposed off as directed by Site-in-
No separate payment shall be made for clearing, stripping and disposal of Materials obtained
from clearing. This shall be considered as part of Cutting Work in areas of cutting and Filling
work in areas of Filling and the rates quoted under the respective items.
4.0 EARTHWORK IN FILLING
4.1 After clearing, stripping and consolidation of areas, spot levels at intervals and pattern as
decided by Site-in-Charge shall be taken jointly and filling shall commence only after the levels
are signed by the CONTRACTOR as a token of his acceptance. Approved fill Material shall
be spread in uniform layers not exceeding 30 cms. in loose depth. The Contractor has to make
his own approach and access roads from the borrow area to the demarcated filling areas. BPCL
does not guarantee any passage way or right of way for the Contractor's work other than
available at site. No claim shall also be admissible to the CONTRACTOR on account of his
having to take longer leads or routes for earth movement, than envisaged by him, either due to
any road cuttings, non-availability of routes, or any other grounds whatsoever. In case total
filling required in any area consists of earth both from borrow areas and available approved
excavated material from within plant area, then joint levels, shall be taken before commencing
filling with earth from borrow area. However, earth from Borrow areas required for filling can
be used only after the available earth from excavation within demarcated area has been utilised
and clearance to this effect obtained from the Site-in- Charge.
4.2 All clods, Lumps, etc. shall be broken before compaction.
4.3 Successive layers of filling shall not be placed until the layer below has been thoroughly
compacted to satisfy the requirements laid down in this specification.
4.4 Prior to Rolling, the moisture content of Material shall be brought to within plus or minus
2% of the Optimum Moisture Content as described in IS:2720 Part VII. The moisture Content
shall preferably be on the wet side for potentially expansive soil.
4.5 After adjusting the Moisture Content as described the layers shall be thoroughly compacted
by either sheep foot roller or power driven roller or vibratory roller as approved by Site-in-
Charge till the specified maximum laboratory dry density is obtained.
4.6 Each layer shall be tested in field for density and accepted by Site-in- Charge subject to
achieving the required density before laying the next layer. A minimum of one test per 500 M2
for each layer shall be conducted.
4.7 If the layer fails to meet the required density, it shall be reworked or the material shall be
replaced and method of construction altered as directed by Site-in-Charge to obtain the required
4.8 The filling shall be finished in conformity with the alignment, levels, cross-section and
dimensions as shown in the drawing. Earthen embankment shall be filled 300 mm more on
both sides, where height is more than 1M, and this extra filling shall be dressed, after
compaction, in conformity with alignment, level, cross-section and dimension as shown in the
drawing to achieve proper compaction in the slope. No extra payment shall be made in this
4.9 Extra Material shall be removed and disposed off as directed by the Site-in-Charge.
4.10 Tolerances
General site grading including cutting and filling in depressions shall- be carried out to within
up down tolerance of ± 5 cms of final lines grades and slopes.
Payment for filling shall be made on Cubic Metre of Volume calculated on the basis of cross
section plotted from the levels of ground, where filling is to be carried out and the levels
reached after filling is duly consolidated, volume being calculated by Prismoidal formula. In
case of simultaneous cut and fill operation, wherever specified, payment shall be made on the
basis of one composite rate for cutting and filling, all other details about measurement etc.
remaining same as above. No extra payment shall be made towards testing charges.
SPECIFICATION FOR PLAIN AND
REINFORCED CEMENT CONCRETE
1.0 Construction of plain and reinforced concrete works shall be in accordance with IS:456 and
other relevant codes mentioned therein.
2.0 GRADES OF CONCRETE
Unless otherwise specified, the grades of concrete shall generally be as per table given below.
GRADE COMPRESSIVE
OF 15 CM CUBE AT
28 DAYS (N/SQ. MM)
The compressive strength is defined as the strength of material below which not more than 5%
of test results are expected to fall.
3.0 TYPE OF CONCRETE MIX
The concrete shall be either nominal mix or design mix as defined in IS:456. Unless otherwise
specified, all lean concrete shall be nominal mix and all structural concrete shall be design mix.
3.1 NOMINAL MIX
This concrete shall be made by adopting proportions of materials as specified in table given
GRADE TOTAL QUANTITY PROPORTION OF FINE QUANTITY OF
OF DRY AGGREGATES AGGREGATE TO COARSE WATER PER50
BY MASS PER 50 KG AGGREGATE (BY WEIGHT) OCEMENT
OF CEMENT(KG)(MAX) LITERS
M 5 800 Generally 1:2 but
subject to an upper
limit of 1:1.5 and
lower limit of 1:2.5
3.2 DESIGN MIX CONCRETE
The mix shall be designed to produce the grade of concrete having the required workability
and characteristic strength not less than appropriate values given in para 2 above.
3.3 PROPORTIONING
Proportioning shall mean the process of determining the proportions of the various ingredients
to be used to produce concrete of the required strength, workability, durability and other
properties. BPCL's Site-in-charge shall verify the strength of the concrete mix, before giving
his sanction for its use. However, this does not absolve the Contractor from his responsibility
as regards achieving the prescribed strength of the mix. If during the execution of the work,
cube tests show lower strengths than required, the Site-in-Charge shall order fresh trial mixes
to be made by contractor. No claim to alter the rates of concrete work shall be entertained due
to some changes in mix variations. Preliminary mix designs shall be established well ahead of
the start of work.
3.4 MAXIMUM DENSITY
Suitable proportions of sand and different sizes of coarse aggregates for each grade of concrete
shall be selected to give the maximum density as nearly as practicable. This shall be determined
by mathematical means, laboratory test, field trials and suitable changes in aggregate gradation.
3.5 WATER CEMENT RATIO
Once a mix, including its water-cement ratio, has been determined and specified for use by the
Site-in-charge, the water-cement ratio shall be maintained. The Contractor shall determine the
water content of the aggregates frequently as the work progresses, and the amount of mixing
water shall be adjusted so as to maintain the specified watercement ratio.
3.6 CONSISTENCY
The concrete shall have consistency such that it shall be workable in the required position and
when properly vibrated it flows around reinforcing steel all embedded fixtures etc.
3.7 WORKABILITY
The concrete mix proportion chosen should be such that the concrete is of adequate workability
for the placing condition and can be properly compacted with the means available. The
suggested ranges of values of workability of concrete measured in accordance with IS :
are indicated below.
PLACING CONDITIONS DEGREE OF VALUES OF
Concreting of shallow Very low 20-10 seconds, vee-bee
sections with vibration time or 0.75 - 0.80
compacting factor
Concreting of lightly Low 10-5 seconds , vee-bee time
reinforced section with or
vibration 0.80 -0.85 , compacting
Concreting of lightly Medium 5-2 seconds , vee-bee time
reinforced sections without or
vibration , or heavily 0.85-0.92 ,compacting
reinforced sections with or
vibration 25-75 mm, slump for
Concreting of heavily High Above 0.92, compacting
reinforced sections without or
vibration 75-125 mm, slump for
*For smaller aggregate the values will be lower.
In proportioning concrete , the quality of both cement and aggregate should be determined by
weight. Where the weight of cement is determined on the basis of weight of cement per bag, a
reasonable number of bags should be weighed periodically to check the net weight. Water
should be either measured by volume in calibrated tanks or weighed. Any solid admixtures that
may be added, may be measured by weight; liquid and paste admixtures by volume or by
weight. Batching plant, where used, shall conform to IS : 4925. All measuring equipment shall
be maintained in a clean serviceable condition, and their accuracy periodically checked.
4.1 Except where it can be shown to the satisfaction of the Site-in-charge that supply of
properly graded aggregate of uniform quality can be maintained over the period of work, the
grading of aggregate should be controlled by obtaining the coarse aggregate in different sizes
and blending them in the right proportions when required, different sizes being stacked in
separate stock piles. The grading of coarse and fine aggregate shall be checked frequently, the
frequency for a given job being determined by the Site-in-charge to ensure that the specified
grading is maintained.
4.2 Under special circumstances, change from weigh batching to volume batching may be
permitted by BPCL's Site-in-charge on specific request from the Contractor.
4.3 The amount of the added water shall be adjusted to compensate for any observed variations
in the moisture contents in both fine and coarse aggregates. For the determination of moisture
content in the aggregates, IS : 2386 (Part-III) may be referred to. To allow for the variation in
weight of aggregates due to variation in their moisture content, suitable adjustments in the
weights of aggregate shall also be made. In the absence of exact data, only in the case of
nominal mixes, the amount of surface water may be estimated from the values given in
SURFACE WATER CARRIED BY AGGREGATE
AGGREGATE APPROXIMATE QUANTITY OF SURFACE
Litres/M3 Percentage by weight
Moderately Wet Sand 80
Moist gravel or crushed rock 20-40 1.25 -
Very wet Sand 120
5.0 CONCRETE MIXING.
The concrete mixing shall be carried out in an approved type of mechanical mixer. The mixing
shall be continued until there is a uniform distribution of material and the mass is uniform in
colour and consistency. If there is segregation, after unloading from the mixer, the concrete
shall be remixed.
Mixers shall comply with IS:1791 and shall be maintained in satisfactory operating condition
. Mixer drum shall be kept free of hardened concrete and blades shall be replaced when worn
down more than ten percent (10%) of their depth. Should any mixer at any time produce
unsatisfactory results , leak mortar or cause waste of materials , its use shall be promptly
5.2 MIXING TIME
Mixing time shall be as indicated in the following table. Excessive mixing requiring additions
of water shall not be permitted. Time shall start when all solid materials are poured in the
revolving mixer drum, provided that all or the mixing water shall be introduced before
onefourth of the mixing time has elapsed. The Site-in-charge may, however, direct a change in
the mixing time, if he considers such a change necessary.
CAPACITY MINIMUM MIXING TIME
2 Cu.M or less 1-1/2 Minutes.
3 Cu.M 2-1/2 Minutes.
5 Cu.M 3 Minutes
All records and charts for the batching and mixing operations shall be prepared as specified
and as per the instructions of the Site-in-charge.
5.3 HAND MIXING
Normally hand mixing of concrete shall not be permitted. However this may be allowed by the
Site-in-charge in special cases (such as far away isolated places). Ten percent (10%) extra
cement shall have to be added to the normal mix when mixed by hand .It shall be carried out
on a water tight platform and care shall be taken to ensure that mixing is continued until the
mass is uniform in colour and consistency. No extra payment shall be made to the Contractor
for mixing by hand or for using extra cement due to hand mixing.
Admixtures shall be used in concrete only with the approval of the Site-in-charge.
5.5 TRANSPORTATION
All concrete shall be conveyed from the mixer to the place of final deposit as rapidly as possible
in suitable buckets, dumpers, containers or conveyors which shall be mortar leak tight. Care
shall be taken to prevent the segregation or loss of the ingredients and maintaining the required
5.6 PLACING AND COMPACTION
Before placing concrete all soil surfaces upon which or against which concrete is to be placed
shall be well compacted and free from standing water, mud or debris. Soft or yielding soil shall
be removed and replaced with lean concrete or with selected soils and compacted to the density
as directed by Site-in-charge. The surface of absorbing soil (against which concrete is to be
placed) shall be moistened thoroughly so that moisture is not drawn from the freshly placed
concrete. Concrete shall not be placed until the framework, the placement of reinforcing steel,
embedded parts etc. have been inspected and approved by the Site-in-charge. Any accumulated
water on the surface of the bedding layer shall be removed by suitable means before start of
placement. No concrete shall be placed on a water-covered surface. Concrete shall be
discharged by vertical drop only and the drop height shall not exceed 1.5 M. Concrete shall be
deposited as near as practicable in its final position to avoid rehandling. Concrete shall be
placed in successive horizontal layers.
All struts, stays and braces (serving temporarily to hold the forms in correct shape and
alignment pending the placing of concrete at their locations) shall be removed when the
concrete placing has reached an elevations rendering their service unnecessary. These shall
not be buried in the concrete. Concrete shall be thoroughly compacted with vibrators and fully
worked around the reinforcement, embedded fixtures and into corners of form work before
setting commences. In no case this shall be subsequently disturbed. Methods of placing shall
be such as to preclude segregation. Care shall be taken to avoid displacement of reinforcement
or movement of formwork. Unless otherwise approved, concrete shall be placed in single
operation to the full thickness of slabs, beams and similar members. Concrete shall be placed
continuously until completion of the part of the work between construction joints or as directed
by the Site-in-charge. The method of placing and compaction employed in any particular
section of the work shall be to the entire satisfaction of the Site-incharge. During hot weather
(atmospheric temperature above 40 oc) or cold weather (atmospheric temperature below 5 oc),
the concreting shall be done as per the procedure set out in IS:7861. Concrete that has been left
standing and become stiffened shall not be deposited in the work.
5.7 ITEMS EMBEDDED IN CONCRETE
Concreting shall not be started unless the electrical conduits, pipes, fixture etc., wherever
required, are laid by the concerned agency. The Contractor shall afford all the facilities and
maintain co-ordination of work with other agencies engaged in electrical and such other work
as directed by the Site-in-charge. Before concreting, the Contractor shall provide, fabricate and
lay in proper position all metal inserts, anchor bolts, pipes etc. (which are required to be
embedded in concrete members) as per relevant drawings and directions of Site-in-charge.
6.0 REQUIREMENT OF CONCRETE EXPOSED TO
SULPHATE ATTACK
Concentration of Type of Min.
Sulphates Cement Cement
In soil In Water
Less than Less than OPC 280
0.2 to 0.5 300 to OPC or 330
0.5 to 1.0 1200 to Super 330
7.0 CONSTRUCTION JOINTS
7.1 Construction joints shall be provided in position as shown or described on the drawings or
as directed by the Site-in-charge. Such joints shall be kept to the minimum. These shall be
straight and at right angles to the direction of main reinforcement.
7.2 In a column, the joint shall be formed about 100 mm to 150 mm below the lowest soffit of
the beams framing into it. Concrete in a beam and slab shall be placed throughout without a
joint but if the provision of a joint is unavoidable, the joint shall be vertical and located within
1/3 to 1/4 of the span. This is to be done to ensure that joint is located at the point of minimum
7.3 When stopping the concrete on a vertical plane in slabs and beams, an approved stop board
shall be placed with necessary slots for reinforcement bars. The construction joints shall be
keyed by providing a triangular or trapezoidal fillet nailed on the stop board. When concrete is
stopped on a horizontal plane, the surface shall be roughened and cleaned after the initial set .
7.4 When the work has to be resumed on a surface, which has hardened, such surface shall be
roughened to expose the tips of the coarse aggregate by hacking it. It shall then be swept clean
and thoroughly wetted. For vertical joints neat cement slurry shall be applied on the surface
before it is dry. For horizontal joints the surface shall be covered with a layer of mortar about
10 to 15 mm thick composed of cement and sand in the same ratio as the cement and sand in
concrete mix. This layer of cement slurry or mortar shall be freshly mixed and applied
immediately before placing the concrete.
7.5 Where the concrete has not fully hardened, all laitance shall be removed by scrubbing the
wet surface with wire or bristle brushes, care being taken to avoid dislodgement of particles of
aggregate. The surface shall be thoroughly wetted and all free water removed. The surface shall
be coated with neat cement slurry. On this surface, a layer of concrete not exceeding 150 mm
in thickness shall first be placed and shall be well rammed against old work, particular attention
being paid to corners and close spots , work thereafter shall proceed in normal
8.0 SEPARATION JOINT
Separation joint shall be obtained by using an approved alkathene sheet stuck on the surface
against which concrete shall be placed.
9.0 EXPANSION JOINT
Expansion joints in structures shall be formed in positions and to the shapes shown in relevant
drawings. Joints shall be filled with material as stipulated in drawings/schedule of rates/Tender
10.0 PROTECTION OF FRESHLY LAID CONCRETE
Newly placed concrete shall be protected by approved means from rain, sun and wind. Concrete
placed below the ground level shall be protected from falling earth during and after placing.
Surface shall be kept free from contact with such ground or with water draining from such
ground during placing of concrete for a period of atleast 3 days. The ground water around
newly poured concrete shall be kept to an approved level by pumping or other means.
Curing of concrete shall be in accordance with IS : 456. Concrete shall be cured by keeping it
continuously wet for the specified period of time to ensure complete hydration and hardening.
Curing shall be started after 8 hours of placement of concrete and in hot weather after 4 hours.
Curing shall be assured by use of an ample water supply in pipes, with all necessary appliances
such as hose, sprinklers etc. A layer of sacking, canvass, hessian, or other approved material
that will hold moisture for long periods and prevent loss of moisture from the concrete shall be
used as covering. Type of covering which would stain, disfigure, or damage the concrete during
and after the curing period shall not be used. The Contractor shall have all equipment and
materials required for curing on hand and ready for use before concrete is placed. For curing
the concrete in pavements, floors, flat roofs or other level surfaces the ponding method of
curing is preferred after the expiry of first 24 hours during which (i.e. first 24 hours) the
concrete shall be cured by use of wet sacking, canvass, hessian etc. The minimum water depth
of 25 mm for ponding shall be maintained. The ponded areas shall be kept continuously filled
with water and leaks, if any , shall be promptly repaired.
12.0 DAMP PROOF COURSE - (DPC)
The 40 mm thick Damp Proof Course shall consist of plain cement concrete of nominal mix
1:2:4 by volume (1 Cement : 2 Coarse Sand : 4 Crushed Stone Aggregates ) with 10 mm and
down size graded aggregate, unless otherwise specified. The Damp Proof Course shall be laid
at plinth level of brick walls, flush with the floor surface and shall not be carried across
doorways. Before laying, the top surface of wall should be thoroughly cleaned and watered.
The D.P.C shall be laid in layers of 20 mm thickness retaining the edges by necessary formwork
and shall be well tamped and trowelled to smooth finish. The layer shall be cured by keeping
the surface wet for 40 hours and after it has dried, two coats of hot bitumen of grade 85/25
conforming to IS:73 shall be applied over it at the rate to 1.7 Kg/M2. Over this, the second
layer 20 mm thick concrete shall be laid and cured as described in case of the first layer and
two coats of hot bitumen at the rate of 1.7 Kg/M2 shall be applied again in a similar manner.
Over this, dry sharp sand shall be sprinkled evenly.
13.0 FINISHING OF CONCRETE
On striking the formwork, all surface defects such as bulges, ridges and honey-combing etc.
observed shall be brought to the notice of the Sitein- charge. The Site-in-charge may, at his
discretion allow rectification by necessary chipping and packing or grouting with concrete or
cement mortar. However, if honeycombing or sagging are of such extent as being undesirable,
the Site-in-charge may reject the work totally and his decision shall be binding. No extra
payment shall be made for rectifying these defects, demolishing and reconstructing the
structure. All burrs and uneven faces shall be rubbed smooth with the help of carborandum
13.1 REPAIR AND REPLACEMENT OF UNSATISFACTORY
Repairs shall be made as soon as possible after the forms are removed and before the concrete
becomes too hard. Stone pockets, segregation patches and damaged areas shall be chipped out
and the edges undercut slightly to form a key. All loose material shall be washed out before
patching. A good bond between the patch and parent concrete shall be obtained by sprinkling
dry cement on the wet surface or by throwing mortar with force on to the wetted concrete, or
by brush in a coat of thick cement grout of about 1:1 (1 Cement:1 Sand) just before applying
the patching material. Before this has dried, the remainder of the patch shall be filled with
mortar or concrete, depending on the extent of the repair. Cement concrete/mortar used in
repair of exposed surfaces shall be made with cement from the same source as that used in
concrete and blended with sufficient amount of white Portland cement to produce the same
colour as in the adjoining concrete. The proportions of ingredients shall be same as those used
in parent concrete. The mortar shall be as dry as possible and well compacted into the cavity.
All filling shall be tightly bonded to the concrete and shall be sound, free from shrinkage cracks
after the filling has been cured and dried. For larger repairs to hardened concrete, necessary
formwork bearing tightly at the edges of the cavity shall be provided. Concrete shall be chipped
out to a depth of at least 100 mm. Mortar shall be scrubbed into all surfaces with a wire brush
before placing the concrete. Damaged reinforcement shall be adequately spliced with new steel
so as to maintain the original strength. Additional reinforcement, ifrequired in the patch, shall
be provided as per the instructions of Sitein-charge.
13.2 CURING OF PATCHED WORK
Immediately after patching is completed, the patched area shall be covered with an approved
non-staining water saturated material, which shall be kept wet and protected against sun and
wind for a period of 12 hours. Thereafter, the patched area shall be kept continuously wet by a
fine spray or sprinkling for not less than 10 days.
13.3 The use of an epoxy for bonding fresh concrete used for repairs shall be permitted at the
discretion of the Site-in-charge. Epoxy shall be applied in strict accordance with the
instructions of the manufacturer.
14.0 CEMENT WASH
If instructed by the Site-in-charge, the Contractor shall provide one coat of cement wash over
the concrete surfaces of foundation, pipe racks, columns, walls etc. which are not plastered.
Forms for concrete shall be of plywood or steel as directed by the Sitein-charge and shall give
smooth and even surface after removal thereof. If it is desired by the Site-in-charge, the
Contractor shall prepare, before commencement of actual work, design and drawings
forframework and get them approved by the Site-in-charge.
15.1 FORM REQUIREMENT
The formwork shall be true, rigid and adequately braced both horizontally as well as
diagonally. The forms shall have smooth and even surface and be sufficiently strong to carry
without deformation the dead weight of the green concrete, working load, wind load and also
the side pressure exerted by the green concrete. As far as practicable, clamps shall be used to
hold the forms together. Where use of nails is unavoidable minimum number of nails shall be
used and these shall be left projecting so that they can be easily withdrawn. Form joints shall
not permit any leakage. The formwork shall be strong enough to withstand the effect of
vibrations practically without any deflection, bulging, distortion or loosening of its
components. Forms for beams and slabs (span more than 6.0 m) shall have camber of 1 in
so as to offset the deflection and assume correct shape and line after deposition of concrete.
For cantilevers, the camber at free end shall be 1/100th of the projected length.
15.2 INSPECTION OF FORMS
Before concrete is placed, all forms shall be carefully inspected to ensure that they are properly
placed, sufficiently rigid and tight, thoroughly cleaned, properly treated and free from foreign
material. The complete formwork shall be inspected and approved by the Sitein- charge before
the reinforcement bars are placed in position. When forms appear to be unsatisfactory in any
way, either before or during the placing of concrete, the work shall be stopped until the defects
have been corrected as per the instructions of the Site-in-charge.
15.3 TREATMENT OF FORMS
The surfaces of forms that would come in contact with concrete shall be well treated with
approved non-staining release agents such as soft soap, oil, emulsions etc. Care shall be taken
that such release agents are kept out of contact with the reinforcement.
15.4 REUSE OF FORMS
Before reuse, all forms shall be thoroughly scrapped, cleaned, examined and when necessary
repaired and retreated before resetting. Formwork shall not be reused, if declared unfit or un-
serviceable by the Site-in-charge.
15.5 REMOVAL OF FORMS/ STRIPPING TIME
In the determination of time for removal of forms, consideration shall be given to the location
and character of the structures, the weather and other conditions including the setting and
curing of the concrete and material used in the mix. Forms and their supports shall not be
removed without the approval of the Site-in-charge. Methods of form removal likely to cause
overstressing or damage to the concrete shall not be adopted. Supports shall be removed in
such a manner as to permit the concrete to uniformly and gradually take the stresses due to its
own weight. In normal circumstances and where ordinary Portland cement is used, forms may
generally be removed after expiry of following periods and as per IS:456,
(1) Walls , columns and vertical faces 24 to 48 hrs as may of all structural members be decided
by the Site-in-charge.
(2) Slabs (props left under) 3 days.
(3) Beam Soffits (props left under) 7 days
(4) Removal of props under slabs :
Spanning up to 4.5 M 7 days.
Spanning over 4.5 M 14 days.
(5) Removal of props under beams and
Spanning upto 6 M 14 days
Spanning over 6 M and upto 9M 21 days
Over 9 M 28 days
15.6 STAGING/SCAFFOLDING
Staging/Scaffolding shall be properly planned and designed by the Contractor. The Contractor
shall get it reviewed by Site-in-charge before commencement of work.
16.0 REINFORCEMENT
Reinforcement shall be cut, bent to shape and dimensions as shown in the bar bending
schedules/drawings. In normal course the bar bending schedule shall be supplied to the
Contractor, however, in case, bar bending schedule is not provided , the Contractor shall
develop the same at no extra cost to the Owner and get it reviewed by the Site-incharge. The
Contractor shall check the bar-bending schedule (issued by the Owner) prior to fabrication and
satisfy himself about the correctness of the same.
16.1 STRAIGHTENING, CUTTING AND BENDING
Procedure for cutting and bending shall be as given in IS:2502.
16.2 PLACING AND FIXING
All reinforcement shall be cleaned of mill scale, loose rust, oil, grease or any other harmful
material before placing them in position. All reinforcement shall be fixed in correct position
and shall be properly supported to ensure that displacement will not occur when concrete is
placed. The reinforcement bars shall be tied at every intersections by two strands of 16 SWG
black soft annealed binding wire.
16.3 OVERLAPPING
Only bars of full length shall be used as shown in the drawings. But where this can not be done,
overlapping of bars shall be done as directed by the Site-in-charge. Where practicable, the
overlapping bars shall not touch each other, but these shall be kept apart by 25 mm or
times the maximum size of the coarse aggregate whichever is greater. But where this is not
possible, the overlapping bars shall be tied with two strands of 16 SWG black soft annealed
binding wire. The overlaps shall be staggered for different bars and located at points along the
span where neither shear nor bending moment is maximum.
16.4 WELDED JOINTS
Welding of reinforcing bars shall not be permitted without the written permission of the Site-
in-charge. Where welding is permitted, it shall be in accordance with the recommendations of
IS:2751 and IS:9417. Welded joints shall be located at suitable staggered positions. Tests shall
be made to prove that the joints are of the full strength of the bars.
16.5 SUBSTITUTION
When specified diameter of reinforcement bars is not available, the Contractor shall use other
diameter of reinforcement bars on written approval of the Site-in-charge.
Cover to reinforcement shall be as indicated on the drawings and in their absence as per IS:456
or directed by the Site-in-charge.
17.0 PRECAST CONCRETE
17.1 Specifications contained in clauses above regarding concrete, formwork and
reinforcement shall apply in addition to the clauses given as under. The Contractor shall get
the precasting bed approved by the Site-in-charge prior to the start of the work.
17.2 Necessary lifting hooks of 12mm diameter MS rounds shall be provided for handling as
indicated in the drawing or as directed.
17.3 Unless otherwise specified, the exposed surfaces of precast members shall be finished
smooth with 1:3 (1 Cement: 3 Sand) cement mortar. Surface used, as walkways shall be given
a non-skid finish
18.1 PLAIN AND REINFORCED CONCRETE
Payment for plain and reinforced cement concrete (cast in-situ) shall be made on cubic meter
basis of the volume of the actual finished work done or as per approved construction drawings,
whichever is less and shall be inclusive of providing pockets, openings, recesses of all sizes,
chamfers, fillets construction joints, cement wash, curing etc. The rates shall be deemed to
include complete cost of taking and testing concrete cubes and carrying out other tests as per
specifications and as directed by Site-in-charge. The rate shall however be exclusive of
reinforcement, metal inserts,pipe sleeves, and formwork. Where the strength of concrete mix
(nominal or design) as indicated by tests, lies in between the strengths of any two grades and it
is accepted by the Owner/Site-in-charge, such concrete shall be classified as a grade belonging
to the lower of the two grades between which it lies. The concrete giving lower strength than
specified may be accepted at reduced rates after satisfying the safety of the structure by
checking it with devices such as impact hammer, load test etc. or rejected entirely at the
discretion of the Site-in-charge. The rejected concrete shall be dismantled at no extra cost to
the owner and no payment shall be made for the concrete so rejected and the formwork and
reinforcement used for the same . In case the concrete of lower strength can be improved by
carrying out some strengthening measures entirely at the discretion of the Site-in-charge, then
the said measures shall be carried out by Contractor at his own cost. If the Contractor is able to
make up the strength to the required grade by such improvement measures ,payment shall be
made for the grade achieved. However, if the strength of concrete is not made up to the strength
of required grade , then no payment whatsoever shall be made for any improvement measures
undertaken by the Contractor and payment shall be made only for the lower strength if accepted
by the Site-in-charge. Deductions for openings, pockets etc. shall be as specified in relevant
Indian Standard Codes.
Unless otherwise specified, payment for formwork shall be on square meter basis of the actual
area in contact with the concrete cast. The rates shall be inclusive of keeping the formwork for
the full period as specified in the above clauses and removing the same after the period
is over. No extra payment shall be made for providing scaffolding/staging.
Superior quality formwork for exposed/architectural concrete work shall be measured and paid
separately under the relevant item in the schedule of rates.
18.3 REINFORCEMENT
Payment for reinforcement bars shall be on the basis of weight in metric tons. The weight shall
be derived from the sizes and corresponding unit weights given in handbook of Bureau of
Indian Standards. Binding wire shall not be weighed nor otherwise measured. Measurements
for weight shall not include cutting allowance etc. Rate quoted for reinforcement should
include cost of supplying, decoiling, straightening, cleaning, cutting, bending, placing, binding,
welding if required and providing necessary cover blocks of concrete
18.4 PRE-CAST CONCRETE
Payment for precast concrete members shall be made on cubic metre basis of the volume of the
finished member. The rate quoted shall include cost of formwork, preparation of casting yard,
finishing as specified, curing, handling, fixing in position, breaking masonry and/or concrete
surfaces and making good the same etc. Reinforcement shall be paid separately under relevant
items. Lifting hooks shall be paid on the same basis as reinforcement . Metal inserts shall be
paid as per relevant clauses of Specification
18.5 DAMP PROOF COURSE (D.P.C)
Payment shall be made on square meter basis of the area laid inclusiveof formwork, curing,
providing and applying bitumen, supplying and spreading sand over bitumen etc.
SPECIFICATION FOR
1.0 CLASSIFICATION OF BRICK WORK
Bricks shall conform to IS:1077. Locally available best quality bricks with a minimum
compressive strength of 50 to 75 Kg/cm² conforming to the specification shall be used for
construction. The brickwork shall be classified as 50A class or 50-B class or 35 A class
(Locally available bricks) according to the classification of bricks used and the method of
laying. The sampling and testing of bricks shall be done in accordance with the procedure laid
down in IS :5454 and IS:3495 respectively.
2.0 CEMENT MORTAR
Cement Mortar shall be prepared by mixing cement, sand and water in specified proportions.
The mortar shall be used as soon as possible after mixing and before it has begun to set and in
any case within thirty (30) minutes after the water is added to the dry mixtures. Mortar unused
for more than 30 minutes shall be rejected and removed from the site of work.
2.1 PROPORTIONING
The unit of measurement for cement shall be a bag of cement weighing 50 kgs and this shall
be taken as 0.035 cubic meter (M3). Sand in specified proportion shall be measured on the
basis of its dry volume. In case of damp sand its quantity shall be increased suitably to allow
The mixing of mortar shall be done in mechanical mixer operated manually or by power. The
Site-in-charge may, however, relax this conditions at his discretion, taking into account the
nature and location of work, practicability of the use of these machines etc., particularly
keeping in view the utilization of mortar turned out in one operation of the mixer before its set
initially or where items involving small quantities are to be done or if, in his opinion, the use
of mixer is not feasible.
A) Mixing in Mechanical Mixer
Cement and sand in specified proportion shall be mixed dry thoroughly in a mixer. Water shall
then be added gradually and wet mixing continued for at least one minute. Care shall be
taken not to add more water than that which shall bring the mortar to the consistency of a stiff
paste. Only the quantity of mortar which can be used within 30 (thirty) minutes of its mixing
shall be prepared at a time. Mixer shall be cleaned with water each time before suspending
The measured quantity of sand shall be levelled on clean masonry platform and cement bags
emptied on top. The cement and sand shall be thoroughly mixed dry till the mixture is of a
uniform color. The quantity of dry mix, which can be used within 30 minutes, shall then be
mixed with just sufficient quantity of water to bring the mortar to the consistency of a stiff
3.0 PROCEDURE OF CONSTRUCTION
3.1 SOAKING OF BRICKS
Bricks shall be thoroughly soaked in clean water before use for at least two hours and until air
bubbles cease to come out. The soaked bricks shall be kept on wooden planks or bricks platform
to avoid earth being smeared on them. At the time of placing the bricks, they should be
Brickwork (one or more brick thickness) shall be laid in English Bond unless otherwise
specified. Half or cut bricks shall not be used except when needed to complete the bond. The
walls shall be taken up truly plumb; if battered, the batter is to be truly maintained. All courses
shall be laid truly horizontal and all vertical joints shall be truly vertical. The level and
verticality of the brickwork in walls shall be checked up at every one-metre interval.Brick shall
be laid with frogs upward. While laying, bricks shall be thoroughly bedded and flushed in
mortar and tapped into position with a wooden mallet and the superfluous mortar removed.
The walls of all structures shall be carried up regularly in all cases leaving no part one-meter
lower than another. If this cannot be adhered to, the brick work shall be raked back according
to bond (and not left toothed) at and angle not more than 45o but raking back should not start
within 60 centimetres of a corner. The brickwork shall not be raised more than 14 courses per
day. All iron fixtures, pipes, conduits, holdfasts of doors and windows etc. which are required
to be built in walls, shall be embedded in cement mortar or in cement concrete as specified, in
their correct position as the work proceeds.
Joints shall be restricted to 6 mm in 50 A class brick work and 10 mm in 50 B class and 35 A
class brick work. After the work the faces of the brickwork shall be cleaned (the very day, the
brick work is laid) with wire brush and all mortar droppings removed.
Green work shall be protected from rain by suitable covering. Masonry work as it progresses
shall be kept thoroughly well watered on all faces for al least 10 days after completion. The top
of masonry work shall be left flooded at the close of the day by forming fillet of mortar 40 mm
high round the edges of top course and filled with water.
4.0 SCAFFOLDING/STAGING
Staging/Scaffolding shall be properly planned and designed by the Contractor. The Contractor
shall get it reviewed by Site-in-charge before commencement of work.
5.0 HALF BRICK MASONRY
5.1 Brickwork shall be of half brick thickness and reinforced with 40 x 3 mm thick MS flats as
The work shall be done exactly in a similar manner as brickwork of one or more brick thickness
except that all courses shall be laid with stretchers. Before laying, the reinforcement bars shall
be straightened and thoroughly cleaned. Half the mortar thickness for the bedding joint shall
be laid first and then MS rounds embedded (one on each face of the brick work) maintaining a
side cover of 12 mm mortar. Subsequently the other half of the mortar thickness shall be laid
covering the reinforcement fully. The reinforcement bars shall be carried at least 150 mm into
the adjoining walls. At the junction of two walls, the brick shall, at each alternate course, be
carried into each of the respective walls so as to thoroughly unite the work. The brickwork shall
not be raised more than 14 courses per day. All required fixtures shall be embedded in cement
mortar or concrete as specified in their correct position as the work proceeds.
6.1 Payment for brick masonry work (of one or more brick thickness) shall be made on cubic
metre basis on the volume of actual work done.
6.2 Payment for half brick masonry work shall be made on square meter (M2) basis on the area
of actual work done and shall include cost of supplying and fixing reinforcement in position.
6.3 The rate of brick masonry work shall be inclusive of all labour, material, sampling and
testing, scaffolding/staging, soaking of bricks raking of joints, curing, providing recesses and
openings, embedding fixtures etc.
SPECIFICATION FOR
1.0 RANDOM RUBBLE MASONRY
Stone shall be of approved quality and type. It shall be hard, sound, uniform in colour and free
from decay and weathering. Unless otherwise approved, stones from one single quarry shall be
used for any one work. The length of the stone shall not exceed three times the height and the
breadth on base shall not be greater than 3/4 th the thickness of wall and not less than 15 cms.
The height of stone may beup to 30 cms.
Stone shall be hammer-dressed on the face, the sides and the beds. The "bushing" (projection)
on the face shall not project more than 40 mm on an exposed face and 10 mm on the face to be
All stones shall be wetted before use. The wall shall be carried up truly plumb or to specified
batter. Every stone shall be carefully fitted to the adjacent stones so as to form neat and close
joints. Stones may be laid at random without being brought upto any level courses except at
plinth, window sills and roof level. The bond shall be obtained by fitting in closely the adjacent
stones and by using bond stones. Face stones shall extend and bond well into the backing.
These shall be arranged to break joints as much as possible and to avoid long vertical
lines of joints. Hearting (interior filling) of the wall face shall consist of rubble stones with
thickness not less than 100 mm in any direction, carefully laid, hammered down with a wooden
mallet into position and solidly bedded in mortar. Chips and spawls of stones shall be used
wherever necessary to avoid thick mortar beds or joints and at the same time ensuring that no
hollow spaces are left anywhere in the masonry.The masonry in a structure shall be carried
regularly. Where the masonry of one part has to be delayed, the work shall be raked back at
an angle not steeper than 45 degree.
Bond or through stone running right through the thickness of wall shall be provided in the walls
having thickness upto 600 mm. If the walls are thicker than 600mm, two or more bond stones
overlapping each other by at least 150 mm shall be provided in a line from face to back.
Atleast one bond stone or a set of bond stones shall be provided for every 0.5 sq.m. of wall
Stones shall be so laid that all joints are fully packed with mortar. Facejoints shall be 20 mm
thick. The joints shall be struck flush and finished at the time of laying when plastering and
pointing is not required. If walls are to be plastered or pointed, joints shall be raked to a depth
of 20 mm (minimum) during the progress of work when the mortar is still green. For the faces
of walls that are not to be plastered, stone surfaces shall be cleared of mortar splashing to give
uniform appearance.
Payment for stone masonry work shall be made on cubic metre (M3) basis on the volume of
actual work done and the rates shall be inclusive of all labour, material, scaffolding/staging,
wetting out of stones, raking out joints, curing, providing recesses and openings, embedding
2.0 COURSED RUBBLE MASONRY
Stones shall be as specified in 1.1.
Face stones shall be hammer dressed and to be squared on all sides and joints so as to give
them approximately rectangular block shape. The bed joint shall be rough chisel dressed, true
and square for at least 60mm back from the face and the side joints for at least 40 mm, such
that no portion of the dressed surface is more than 6 mm from a straight edge placed on it. The
remaining portion of stones shall not project beyond the surface of the bed and side joints. The
"Bushing" on the face shall not project more than 40 mm on exposed face and 10 mm on
the face to be plastered.
All stones shall be wetted before use. The walls shall be carried up truly plumb or to specified
batter. All courses shall be laid truly horizontal and all vertical joints shall be truly vertical.
The stones shall be laid in horizontal courses and each course shall be of equal height. The
height of each course shall not be less than 150 mm and not more than 300 mm. Face stones
shall be laid as alternate headers and stretchers. Stones shall break joint atleast half the height
of the course. No face stone shall be less in breadth than its height and at least one third of the
stones shall tail into the work for length not less than twice their height. The hearting of interior
filling of the wall shall consist of flatbedded stones carefully laid on their proper beds or joints
of mortar and at the same time ensuring that no hollow spaces are left anywhere in the masonry.
Chips not more than 10% of quantity of stone masonry may be used where necessary to fill
interstices between adjacent stones to avoid thick beds or joints of mortar. The masonry in
structure shall be carried up regularly, but where breaks are unavoidable, the joint shall be
raked back at an angle not exceeding 45 degree.
Same as for random rubble masonry except that a bond stone or a set of bond stones shall be
inserted 1.5 to 1.8 m apart, in every course.
All bed joints shall be horizontal and all side joints vertical. All joints shall be full of mortar.
Face joints shall not be more than 10 mm thick. When plastering or pointing is not required to
be done, the joints shall be struck flush and finished at the time of laying. Otherwise the joints
shall be raked to a minimum depth of 20 mm during the progress of work when the mortar is
still green. The joint shall be either flush or struck. Raised or cut-pointing, shall be done with
cement mortar 1:3 using wooden mould/template of minimum 12 mm depth for uniformity.
SPECIFICATION FOR
PLASTERING AND POINTING
1. CEMENT PLASTERING
1.1 PREPARATION OF SURFACE
The surface to be plastered shall be thoroughly cleaned so that it is free from dust, dirt, oil,
salts, etc. On cement concrete surfaces, the surface shall be cleaned with wire brush and
scarified by lines with trowel. The surface in both cases shall be washed properly and kept wet
for 4 hours before plastering is commenced.
The mortar of specified mix shall be used.
1.3 APPLICATION OF PLASTER
Plaster shall be started from top and gradually worked down towards floor. It shall not, at any
place be thinner than specified. To ensure even thickness, plaster of about 15cm x 15cm shall
be first applied horizontally and vertically at not more than 2 metre interval over the entire
surface to serve as gauges. The surfaces of these gauged areas shall be truly in the plane of
finished plaster surface. The mortar shall then be laid on the wall or other surfaces between the
gauges and finished even. All corners shall be rounded to a radius of 25 mm unless otherwise
specified. The Contractor shall not be paid for any extra thickness of plaster done than as
specified. The plastering thicknesss hall generally be as under unless otherwise specified.
For internal wall - 12 mm thick in CM 1:4 External wall - 15 or 19 mm thick in CM 1:4 in two
coats For underside of roof - 6 mm thick in CM 1:3
Curing shall start 24 hours after the plaster is laid. It shall be kept were for 7 days. During this
period it shall be suitably protected from all damages at the Contractor's expenses by such
means as approved by the Site-incharge.
1.5 Any cracks which appear in the surface and all portions which sound hollow when tapped,
or are found to be soft or otherwise defective, shall be cut out in rectangular shape and redone
as directed by the Sitein- charge.
1.6 Wherever specified, standard water proofing compound as approved by the Site-in-charge
shall be added to the mortar at the rate of 3% or as specified by the manufacturer by weight of
Cement for which the rate shall be specified separately in the schedule of rates.
Payment for plastering shall be made on square metre basis, irrespective of particular thickness
of plaster. For openings of area less than 0.5 metre square no deduction and no payment shall
be made for jambs, sills, soffits etc. For opening of area between 0.5 sqm and 3.0 sqm. each
deduction shall be made at 50% of the opening area and no payment made for jambs, soffits
etc. For openings of area above 3 sqm.each , deduction shall be made for full area of opening
but Jambs, Soffits and Sills, shall be measured. All measurements shall be separately made for
each face. The rate of plastering shall include the cost of providing drip moulds/bands,
scaffolding, swing etc. needed for the work with labour and material all complete.
2.0 SAND FACE PLASTER
2.1 PREPARATION OF SURFACE
The surface to be plastered shall be thoroughly cleaned so that it is free from dust, dirt, oil, salts
etc. On cement concrete surfaces, the surface shall be cleaned with wire brush and scarified by
lines with trowel. The surface in both cases shall be washed properly and kept wet for 4 hours
before plastering is commenced.
2.2 Sand face plaster shall consist of two layers. The first layer generally 7mm average thick
cement plaster with cement mortar of 1:4 mix (1 cement : 4 sand) shall be rough finished. Over
this a second layer of average 13 mm thick of cement sand plaster in the proportion of 1:2 mix
shall be applied. The second layer of plaster shall be laid only after first layer has sufficiently
dried.The surface of sand plaster shall be finished rough with sponge or as directed by the Site-
The plaster shall be thoroughly cured for 7 days as directed by Site-incharge.
2.4 Any cracks which appear in the surface and all portions which sound hollow when tapped,
or are found to be soft or otherwise defective, shall be cut out in rectangular shape and redone
as directed by the Sitein- charge.
Payment for plastering shall be made on square metre basis, for the particular thickness of
plaster. Deduction shall not be made for Jambs, Sills and soffits measured for opening of area
less than 0.5 sqm. each. For opening of area between 0.5 sqm. and 3.0sqm. each, deduction
shall be made at 50% of the opening area and no payment made for jambs, soffits, sills etc. For
openings of area above 3 sqm. each, deduction shall be made for full area of opening but jambs,
soffits and sills shall be measured. All measurements shall be separately made for each face.
The rate shall include the cost of providing drip moulds/bands, scaffolding and swing etc.,
needed for the work with labour and material all complete.
3.0 ROUGH CAST CONCRETE FACING/AGGREGATE
3.1 The surface shall be prepared as for cement plaster and then 2 cm backing coat of cement
mortar 1:3 (1 cement:3 sand) shall be applied. Subsequently a top coat, 13mm average thick of
cement and stone chips mixture in proportion 1:3 (1 cement : 3 stone chips10mm size and
below) shall be applied by throwing the mixture on top with trowel to produce uniform rough
Payment shall be made on square metre basis. The rate shall include the cost of scaffolding,
swing etc. With labour and material all complete.
4.1 TYPE OF POINTING
Pointing shall be of the type specified such as "Flush", "ruled" and "Raised and cut" etc.
4.2 PREPARATION OF SURFACE
The Joints shall be brushed clean of dust with wire brush and wetted thoroughly for 6 hours
before pointing is commenced.
Mortar of specified mix shall be used conforming to the schedule of rates.
4.4 APPLICATION & FINISHING
The mortar shall be pressed into raked out joints with pointing trowel and finished either flush,
sunk or raised according to type of pointing specified in the drawings or as directed. The
superfluous mortar shall be cut off from the edges of the lines and the surface of masonry shall
be cleaned of all mortar finish to be free of slack spots, cut faces and other blemishes. Finished
work of pointing shall be to exact size and shape stipulated and edges shall be straight, neat
The pointing shall be kept wet for 7 days. During this period it shall be suitably protected from
Payment shall be made on basis of area of brick wall pointed with deductions for voids as per
clause 1.7. The rate shall include cost of all material and labour involved in all the operations
including the cost of scaffolding etc. Required for work.
4.7 POINTING ON RANDOM RUBBLE STONE MASONRY
In recessed pointing, the mortar shall be simply struck off with a trowel and the work left
showing the natural irregularities in line and surface of the stones themselves. Other
specification shall remain as above for pointing. In case of raised pointing, it shall project from
the well facing with its edges cut parallel so as to have a uniformly raised band about 6mm
raised and width 10mm or more as directed showing the natural irregularities in line and surface
of stones themselves. Other specifications shall remain same as per above specifications of
Payment shall be made on square metre basis of the surfaced pointed with deductions for voids
as per clause 1.7. The rate shall include cost of all materials and labour involved in all the
operations including the cost of scaffolding etc. required for the work.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
7109.pdf
pdf • 0.02 MB
BUDGETDOC_7109.pdf
pdf • 0.43 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .