| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 LAccepted-AOC | L1 | Accepted-AOC Bidder is L1 and has quoted lowest item rates overall | |
| 2 | L2₹17.3 L+₹1.3 L (8.25%)Rejected-Finance | L2 | Rejected-Finance Bidder is Quoted Higher Rate |
Tender Value
₹17.5 L
EMD Value
₹21,900
Closing Date
5 Jun 2024, 5:00 pmClosed
Staff Officer (Civil), Pench Area
Staff Officer (Civil), AGM Office, Pench Area, P.O. Parasia, Dist. Chhindwara (M.P.) 480441
Renovating of existing structure to provide firefighting system for enhancing the safety of stakeholders at Barkuhi Hospital under Pench Area.
2024_WCL_308690_1
pe3350-civ-s-e010-2024-25
Open Tender
Civil Works - Others
Item Rate
90 days
BARKUHI HOSPITAL
As Per NIT
3 documents required · 3 mandatory
₹21,900
6 Aug 2024
21 May 2024
7 Jun 2024
21 May 2024
5 Jun 2024
21 May 2024
21 May 2024 - 28 May 2024
Amount
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (All complete as per the direction of Engineer-In-Charge) of Main Fire Alarm Control Panel 14 Zone.
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (all complete as per the direction of Engineer- In-Charge) Fire Smoke Detector Sensitivity: 0.98-2.4%FT,Temperature rang: 0 'C-65'C.
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (all complete as per the direction of Engineer- In-Charge) Manual Call Point.
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (all complete as per the direction of Engineer- In-Charge) Fire Hooter.
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (all complete as per the direction of Engineer- In-Charge) 2x1.5sq mm Cable With all accessories cutting.
(FIRE ALARM SYSTEM & SMOKE DETECTION) Supplying, installation and commissioning (all complete as per the direction of Engineer- In-Charge) Fire flashing light.
(FIRE SPRINKLER SYSTEM) Supplying,Installing,Testing and Commissioning of Fire Safety pendent Sprinkler T-ZSTX80-68 'C etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Supply and installation of 2" inch pipe G I "B" class etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Supplying,Installing,Testing and Commissioning of Fire Butterfly Valve of capacity 80 NB etc. all complete as per the direction of Engineer-In-Charge. .
(FIRE SPRINKLER SYSTEM) Supplying,Installing,Testing and Commissioning of Fire Butterfly Valve of capacity 100 NB etc. all complete as per the direction of Engineer-In-Charge. .
(FIRE SPRINKLER SYSTEM) Supplying,Installing,Testing and Commissioning of Non retrunValve of capacity 80 NB etc. all complete as per the direction of Engineer-In-Charge. .
(FIRE SPRINKLER SYSTEM) Supplying,Installing,Testing and Commissioning of Non return valve of capacity 100 NB etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Suppling,Installing,Testing and Commissioning of GI Pipe 1/1.5 inch. G I "B" class etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM)Suppling,Installing,Testing and Commissioning of Tie rods 8 mm Support etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Suppling,Installing,Testing and Commissioning of Chilli Clamp As per requirment etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Suppling,Installing,Testing and Commissioning of 1 inch Ms Socket. etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Supplying and installation of Anchor fastener bolt As per requirement etc. all complete as per the direction of Engineer-In-Charge.
(FIRE SPRINKLER SYSTEM) Supplying and installation of Nut washer As per requirement etc. all complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supply, Installation, Testing & Commissioning of GI pipe as Per Is 1239 'B' Class with fittings GI pipe as Per IS 1239 'B' Class etc. complete as per the direction of Engineer-In-Charge. 4" inch GI pipe
(FIRE HYDRANT SYSTEM) Supply, Installation, Testing & Commissioning of GI pipe as Per Is 1239 'B' Class with fittings GI pipe as Per IS 1239 'B' Class etc. complete as per the direction of Engineer-In-Charge. 3" inch GI pipe
(FIRE HYDRANT SYSTEM) Supply, Installation,Testing & Commissioning of Hydrant Vavle 63mm dia SS Type Coupling etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supply,Installation,Testing & Commissioning of Wall mounting swinging Hose Reel Drum as per IS 884 with 19mm dia,30 meter etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supply,Installation,Testing & Commissioning of RRL Hose pipe conforning to is: 636 & 30 mtr etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supply,Installation,Testing & Commissioning of 63 mm dia Nozel branch short fittied with 25mm dia. IS:903 etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Providing fixing, testing commissioning of weather. proof standard fire hose cabinet wall mounting type having single opening with necessary. locking arrangement by allan key suitable for housing 1 nos. pipe .1 no branch pipe & nozzles BIG Sige Single Door. etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supply,Installation,Testing & Commissioning of 2 Way Fire Brigade Header(Inlet) of 100 mm dia SS 'B' class etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supplying,Installing,Testing and Commissioning of Non return valve 100NB etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 3" inch Elbow etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 4" inch Elbow etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 3"/2, 2.5"/3 MS Reducer etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 3"inch MS Flange etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 4"inch MS Flange etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Suppling,Installing,Testing and Commissioning of 1/2", 3/8",1" MS socket etc. complete as per the direction of Engineer-In-Charge.
(FIRE HYDRANT SYSTEM) Supplying and use of Teflon Tape as per the requirement etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installation,Testing & Commissioning of 5 HP 3Phase Fire Moter pump 2880 rpm etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installation,Testing & Commissioning of 5 HP 3 Phase Fire Moter Starter Panel etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installation,Testing & Commissioning of Fire Moter cable (4 Core x 4 Sq mm.) etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Fire Butterfly Valve 100NB etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Non return valve 100NB etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Flanged Food Valve 100 NB etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Ball valve 1"inch etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Pressure Guage of100mm dia,0 to 300 PSI (0-21 kg/sqcm) range,pad cock valve and elbow etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply,Installing,Testing and Commissioning of Pressure Switch,0-300 PSI etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Rating & Suitable Drilling with Accessories & above ground pipe protection painting red oxide & painting etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supply, Installing,Testing and Commissioning of Air Release Valve etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supplying of 2.5" inch Paint Brush etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supplying and installation of 1"x9" M.S. Nipple etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Ensuring Rubber Packing 160 pcd, 4", 3" etc. complete as per the direction of Engineer-In-Charge.
(FIRE PUMP ROOM SYSTEM) Supplying and installation of Nut Bolt 5/8, 4",2.5",2", as per the requirement etc. complete as per the direction of Engineer-In-Charge.
(CIVIL WORK & MAINTNANCE CHARGE) Civil work for Fire Safety System Installation a which includes all the associated activities such as plaster, painting, repairing of false celling etc to match the condition of site i.e., before installation of Fire safety system and after Fire safety system condition of site, etc. complete as per the direction of Engineer-In-Charge.
(CIVIL WORK & MAINTNANCE CHARGE) Maintnance work for the period of three years (a) Maintnance service will be provide for 1 year (without equipment), (b) Maintnance will be done along with service charge in the second year (without equipment), (c ) Maintnance will be done along with service charge in the third year (without equipment)
(CIVIL WORK & MAINTNANCE CHARGE) Electricity work for motor installation, panel connection, casing and other allied activities etc. complete as per the direction of Engineer-In-Charge.
(CIVIL WORK & MAINTNANCE CHARGE) Transportation charge at site which includes loading and unloading of all the equipments at site etc. all complete as per the direction of Engineer-In-Charge.
(CIVIL WORK & MAINTNANCE CHARGE) Fire plan designing & Approval charges in coherance with the prevailing norms i.e, IS 2190 & National Building Code 2016 Part IV, MP Town & Country Planning Act 1973, Factories Act, Petroleum Act, CEA Regulation and other safety standards
(CIVIL WORK & MAINTNANCE CHARGE) Fire Engineer fees & Documentation charge for attainment of NOC, empanelment of concerned Fire Consultant etc. all complete.
Total impact of GST for the purpose of CTC
PEARL SHINE COMPLETE SOLUTIONS
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .