Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Not Admitted-Fee/PreQual/Technical 1 49 MELEGOUNDANPALAYAM METTUPALAYAM KINATHUKADAVU 642110 | COIMBATORE | TAMIL NADU | 642110 | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
Tender Value
₹68.8 L
EMD Value
₹69,000
Closing Date
13 Feb 2020, 3:00 pmClosed
The Project Director DRDA Kancheepuram
O/o The Project Director DRDA Kancheepuram
Rejuvenation of 5 Nos. of Ponds in Lathur Block of former Kancheepuram District and present Chengalpattu District under SFC - PU and DP Grant 2019-20 having Pkg No.25/2019-20
2020_RDTN_157381_1
DIPR/646/Tenders/2020, dt.30.01.2020
Open Tender
Civil Works
Item Rate
180 days
Lathur Block
Please refer Tender documents.
9 documents required · 9 mandatory
₹0
₹69,000
O/o The Project Director DRDA Kancheepuram
21 Feb 2020
7 Feb 2020
13 Feb 2020
7 Feb 2020
13 Feb 2020
7 Feb 2020
10 Feb 2020
Amount
PART I: Rejuvenation of Katchan Kuttai in Kalkulam Panchayat Estimate Amount : Rs.21.63 Lakh
Clearing the Scrub jungle with uprooting and disposing of the same as directed by the Engineer in charge of the Works and as per technical specification
Earthwork in all soils except hard rock requiring blasting and conveying with a lead of 0 to 100 M by deploying earth moving machineries and tippers for formation of bund in layers of suitable thickness, depending upon type of compaction equipment deploy
Sectioning during forming bund when earth moving machineries, lorries and roller are used for consolidation
Construction of Revetment
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Rough stone dry packing for rivetment work complying with standard specifiction including all cost and charges etc complete
Pointing the RR masonry with CM 1:3 mix - 20mm thick including cost and conveyance etc., complete.,
Construction of Baby Pond Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Construction of Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Construction of Inlet
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Cement Concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
PART II : Rejuvenation of Madavilagam, Eswaran koil kulam in Kalkulam Panchayat Estimate Amount : Rs.23.46 Lakh
Clearing the Scrub jungle with uprooting and disposing of the same as directed by the Engineer in charge of the Works and as per technical specification
Earthwork in all soils except hard rock requiring blasting and conveying with a lead of 0 to 100 M by deploying earth moving machineries and tippers for formation of bund in layers of suitable thickness, depending upon type of compaction equipment deploy
Sectioning during forming bund when earth moving machineries, lorries and roller are used for consolidation
Construction of Revetment
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Rough stone dry packing for rivetment work complying with standard specifiction including all cost and charges etc complete
Pointing the RR masonry with CM 1:3 mix - 20mm thick including cost and conveyance etc., complete.,
Construction of Bathing Ghat
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Construction of Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Construction of Inlet
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Cement Concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
PART III: Rejuvenation of Pachambakkam Village Kulam in Pachambakkam Panchayat Estimate Amount : Rs.7.80 Lakh
Clearing the Scrub jungle with uprooting and disposing of the same as directed by the Engineer in charge of the Works and as per technical specification
Earthwork in all soils except hard rock requiring blasting and conveying with a lead of 0 to 100 M by deploying earth moving machineries and tippers for formation of bund in layers of suitable thickness, depending upon type of compaction equipment deploy
Sectioning during forming bund when earth moving machineries, lorries and roller are used for consolidation
Construction of Revetment
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Rough stone dry packing for rivetment work complying with standard specifiction including all cost and charges etc complete
Pointing the RR masonry with CM 1:3 mix - 20mm thick including cost and conveyance etc., complete.,
Construction of Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
PART IV: Rejuvenation of Nelvoy Village Kulam in Nelvoy Panchayat Estimate Amount : Rs.7.58 Lakh
Clearing the Scrub jungle with uprooting and disposing of the same as directed by the Engineer in charge of the Works and as per technical specification
Earthwork in all soils except hard rock requiring blasting and conveying with a lead of 0 to 100 M by deploying earth moving machineries and tippers for formation of bund in layers of suitable thickness, depending upon type of compaction equipment deploy
Sectioning during forming bund when earth moving machineries, lorries and roller are used for consolidation
Construction of Revetment
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Rough stone dry packing for rivetment work complying with standard specifiction including all cost and charges etc complete
Pointing the RR masonry with CM 1:3 mix - 20mm thick including cost and conveyance etc., complete.,
Construction of Baby Pond Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
PART V : Rejuvenation of Pinagandai gangaiyamman koil Kulam in Periyavelikkadu Panchayat Estimate Amount : Rs.8.32 Lakh
Clearing the Scrub jungle with uprooting and disposing of the same as directed by the Engineer in charge of the Works and as per technical specification
Earthwork in all soils except hard rock requiring blasting and conveying with a lead of 0 to 100 M by deploying earth moving machineries and tippers for formation of bund in layers of suitable thickness, depending upon type of compaction equipment deploy
Sectioning during forming bund when earth moving machineries, lorries and roller are used for consolidation
Construction of Revetment
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
Rough stone dry packing for rivetment work complying with standard specifiction including all cost and charges etc complete
Pointing the RR masonry with CM 1:3 mix - 20mm thick including cost and conveyance etc., complete.,
Construction of Baby Pond Retaining wall
Earthwork excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc., complete as per SS 20 B for foundation
Filling of Sand including all cost and conveyance and labour chages etc complete
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Centering with shuttering for all cc works including all other labout charges etc complete
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost and conveyanceof all materials to work site and all labour charges etc.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .