Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC L1 CONTRACTOR |
| 2 | L2₹1.2 Cr+₹7.2 L (6.45%)Rejected-Finance | ₹1.2 Cr+₹7.2 L (6.45%) | L2 | Rejected-Finance L2 CONTRACTOR |
| 3 | A AJMEER KHAN Rejected-Technical | - | - | Rejected-Technical Technically not qualified |
Tender Value
Refer Docs
EMD Value
₹1.1 L
Closing Date
12 Jul 2024, 3:00 pmClosed
ADDITIONAL COLLECTOR (D) MADURAI
0/0 ADDITIONAL COLLECTOR (D) DRDA MADURAI
Madurai District_Strengthening of 2 nos of Roads in Melur Block under MGSMT (2024-25) Package no 26
2024_RDTN_460620_3
DIRR/2074/TENDER/2024/Mel24
Open Tender
Civil Works
Item Rate
180 days
Melur
Refer Tender document
4 documents required · 4 mandatory
₹0
₹1.1 L
7 Aug 2024
5 Jul 2024
12 Jul 2024
5 Jul 2024
12 Jul 2024
9 Jul 2024
Amount
Clearingthe Scrub jungle including all labour charges for burrying and burning etc.,
Picking exiting BT Surface including all materials and labour charges etc complete
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20B
Providing and Laying US gravel to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.therefor and all incidental charges etc., complete for TOP LAYER
Providing and laying tack coat over the Pream coat surface using 2.50 Kg of bituminous emulsion for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MoRT&H specification.
Bituminous concrete of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for etc complete
Supply and fixing of KM stone SI No.44 A
Supply and fixing of HM stone SI No.44 A
Provision for Side marking
Provision for Sign board Charges etc Complete
Provision for Name board Charges etc Complete
Clearingthe Scrub jungle including all labour charges for burrying and burning etc.,
Picking exiting BT Surface including all materials and labour charges etc complete
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Providing and Laying US gravel to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.therefor and all incidental charges etc., complete for TOP LAYER
Providing and laying tack coat over the Pream coat surface using 2.50 Kg of bituminous emulsion for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MoRT&H specification.
Bituminous concrete of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for etc complete
Supply and fixing of KM stone SI No.44 A
Supply and fixing of HM stone SI No.44 A
RET. WALL @ ch.520 mtr
Earthwork excavation in all clauses of soil except hard which recurring blastering with initial lead and lift including shorring struttion Baling out water etc., complete for Foundation.
supplying and filling in foundation and basement with filling sand in layers not more than 15cm. Thick well rammed and watered and compacted complying specification.
Cement concrete in cm 1:4:8 mix using 40 mm ISS HGB including cost and conveyance of material at site and all labour charges including curring etc., compelled.
Centering and Shuttering charges including all labour charges etc., complete.
Cement concrete in cm 1:3:6 mix using 40 mm ISS HGB including cost and conveyance of material at site and all labour charges including curring etc., compelled.
Providing Wheep holes using 63mm dia PVC Pipes inlcuding all labour charges etc., complete
Provision for Side marking
Provision for Sign board Charges etc Complete
Provision for Name board Charges etc Complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M A BAHADURKHAN (BID ID -1078948)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .