Tender Value
₹86.8 L
EMD Value
₹1.7 L
Closing Date
12 Oct 2026, 6:00 pmDue today
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
EE, PWD Dn I Pratapgarh
EE, PWD Dn I Pratapgarh
2) Rate Contract for Heliped Construction, Ground Leveling Work, Road Repair and Various Miscellaneous Works while VIP Visits under PWD Division I Pratapgarh
2026_CEPWD_602691_2
EE, PWD Dn I, Pratapgarh NIT No 09/2026-27
Open Tender
Civil Works
Percentage
Pratapgarh
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
EE, PWD Dn I Pratapgarh by eGRAS Challan
₹1.7 L
Yes
1 Oct 2026
1 Oct 2026
13 Oct 2026
1 Oct 2026
12 Oct 2026
1 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRTH Specification Clause 201. By Mechanical Means In area of non-thorny jungle | 40 | Hect. | 10,374 | ₹4,14,960 |
| - | Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil, benching for 300mm width, laying fresh Material in layers not exceeding 250mm and compacting with plate compactor or power rammers to restore the original alignment, levels and slopes. (MoRTH specification : Clause 3002) Mechanical Means | 3,500 | Cum | 93 | ₹3,25,500 |
| - | Making up loss of Material/irregularities on shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment. (Maintenance of Earthen shoulder with filling fresh soil) with average depth of 150mm. (MoRTH specification : Clause 3003) | 9,500 | Sqm | 18 | ₹1,71,000 |
| - | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3 | 2,500 | Cum | 25 | ₹62,500 |
| - | Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site with a lift upto 1.5 m and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections as per MoRTH Specification Clause 301.3.5 | 1,500 | Cum | 36 | ₹54,000 |
| - | Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal with a lift upto 1.5 m and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross- sections as per MoRTH Specification Clause 301.3.5. Mechanical Means | 1,000 | Cum | 188 | ₹1,88,000 |
| - | Construction of embankment with approved materials deposited at site obtained from roadway cutting and excavation from drain and foundation or other structures graded and compacted to meet requirement of Tables 300-1 and 300-2 as per MoRTH Specification Clause 305.3 | 2,500 | Cum | 33 | ₹82,500 |
| - | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead upto 50 m as per MoRTH Specification Clause 305.3 | 4,000 | Cum | 44 | ₹1,76,000 |
| - | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300-2 with lead upto 50 m as per MoRTH Specification Clause 305.3 | 1,000 | Cum | 45 | ₹45,000 |
| - | Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete.[MoRTH specification : Clause 401]. By mechanical means with a lead of 1 Km. For All Rajasthan except Bikaner, Churu, Hanumangarh and Sri Ganganagar. For Grading-II Material | 275 | Cum | 751 | ₹2,06,525 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.02 MB
Tendernotice_2.pdf
PDF • 29.79 MB
BOQ_1068347.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .