Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.7 CrAccepted-Finance PANCHGACHHIA PO BARAIPALI PS AINTHAPALI DIST SAMBALPUR PIN 768006 | SAMBALPUR | SAMBALPUR | ODISHA | 768006 | ₹7.7 Cr | L1 | Accepted-Finance First Lowest |
| 2 | L2₹7.6 Cr−₹11.5 L (1.49%)Accepted-Finance | ₹7.6 Cr−₹11.5 L (1.49%) | L2 | Accepted-Finance Second Lowest |
| 3 | L3₹7.7 CrSame as L1Accepted-Finance NOT AVAILABLE | NEW DELHI | DELHI | 110001 | ₹7.7 CrSame as L1 | L3 | Accepted-Finance Third Lowest |
| 4 | L3₹7.3 Cr−₹42.8 L (5.55%)Rejected-Finance AT PO PRATAPPUR PS BALIAPAL DIST BALASORE PIN 756083 | BALASORE | BALASORE | ODISHA | 756083 | ₹7.3 Cr−₹42.8 L (5.55%) | L3 | Rejected-Finance Third Lowest |
| 5 | L3₹77.1 Cr+₹69.4 Cr (900.0%)Rejected-Finance AT GOPALPUR PO TIKILIPARA PS HEMGIR DIST SUNDARGARH PIN 770076 | HEMGIR | SUNDARGARH | ODISHA | 770076 | ₹77.1 Cr+₹69.4 Cr (900.0%) | L3 | Rejected-Finance Third Lowest |
Tender Value
₹8.6 Cr
EMD Value
₹8.6 L
Closing Date
30 Jun 2025, 5:00 pmClosed
CCE Rayagada R and B Circle
CCE Rayagada R and B Circle Rayagada
Building works
2025_EICCL_114483_2
CCE R and B RGDA- 01/2025-26
National Competitive Bid
Civil Works - Buildings
Percentage
330 days
Paralakhemundi
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹8.6 L
Yes
7 May 2026
16 Jun 2025
1 Jul 2025
16 Jun 2025
30 Jun 2025
16 Jun 2025
16 Jun 2025 - 23 Jun 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation in all types of soil (Hard soi,ordinary soil,stony earth) for site leveling, foundation, pits, trenches and other civil works upto and including 1.5metre depth and stacking the soil upto a lead of 100 metre and including dewatering, removing slush, shoring and strutting (as required), complete as per specification and as directed by the Engineer-In-Charge.
S+3 & S+2 | - | One Cum | 304.92 | - |
| 2 | Filling at all depth with available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 15cm in depth: consolidating each deposited layer by ramming and watering complete (lead upto 100m) as directed by the Engineer-In-charge.
S+3 & S+2 | - | One Cum | 169.4 | - |
| 3 | Supplying of filling sand in foundation and over areas including watering, ramming, consolidating and dressing, labours, tools, taxes etc., all complete as per the specification and direction of Engineer-In-Charge.
S+3 & S+2 | - | One Cum | 699.8 | - |
| 4 | Supplying, diluting and preparing chemical emulsion like imidacloprid 30.5% SC or other chemicals approved by central insecticides board of as directed by the manufactured and spraying the mixture uniformly by sprayers as pre- constructional Anti-termite treatment confirming to IS 6313 (part-ll) and creating a chemical barrier under and around the column pits, wall trenches basement excavation joints, surrounding the pipes and conduits etc. at the rate of 7.5 liters per sqm on vertical surface and 5.0 liters per sqm on horizontal surfaces, 50% of the emulsion to be filled in the holes made in trenches at 150mm center ( or as directed by the manufactured ) including the cost of all materials cost of all labour, conveyance loading unloading , T&P. etc. all complete as per the direction of engineer-in-charge.
S+3 & S+2 | - | One Sqm | 104.54 | - |
| 5 | Cement concrete of prop.(1:4:8) in foundation up to lowest bed level using hard black granite crusher broken metal of size 40 mm size down graded of approved quality from approved quarry as per approved design including hoisting,lowering,laying compacting concrete in layers not exceeding 6” thick, watering, curing for three weeks shuttering the exposed surfaces, finished smooth, providing grooves of beads where necessary including cost, conveyance, royalty, & taxes of all materials, with labour, T&P required for the work etc., complete in all respects including dewatering if required as per direction of Engineer-in-Charge.
S+3 & S+2 | - | One Cum | 5,306.64 | - |
| 6 | Fly ash Brick masonry using bricks of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. Per. Sqr. Cm. in cement mortar of mix (1:6) with ordinary Portland slag cement(PSC) and screened & washed sand for mortar after immersing the bricks for 6 (Six) hours in water before use in Foundation & Plinth including splays cutting, circular moulding, corbelling, chamfering and similar such type of works, watering and curing etc. including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour, scaffolding, sundries, T&P required for the works etc. complete in all respect as directed by the Engineer-in-Charge.
S+3 & S+2 | - | One Cum | 5,661.91 | - |
| 7 | Fly ash Brick masonry using bricks of size 25 cm. x 12 cm. x 8 cm. having crushing strength not less than 75 kg. Per. Sqr. Cm. in cement mortar of mix( 1:6) with ordinary Portland slag cement(PSC) and screened & washed sand for mortar after immersing the bricks for 6 (Six) hours in water before use in Super stracture including splays cutting, circular moulding, corbelling, chamfering and similar such type of works, watering and curing etc. including cost, conveyance, loading, unloading, royalties and taxes of all materials, cost of all labour, scaffolding, sundries, T&P required for the works etc. complete in all respect as directed by the Engineer-in-Charge.
S+3
Stilt Floor | - | One Cum | 5,700.24 | - |
| 8 | First Floor | - | One Cum | 6,078.63 | - |
| 9 | Second Floor | - | One Cum | 6,513.77 | - |
| 10 | Third Floor | - | One Cum | 7,014.18 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.09 MB
BOQ_543200.xls
BOQ • 2.38 MB
DTCN_E_type_dhh.pdf
Tender Documents • 1.07 MB
Tenderdocument.pdf
Tender Documents • 1.07 MB
BOQ.xls
BOQ • 2.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .