| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.6 CrAccepted-AOC B 126 SWARAN JAYANTI VISTAR SANIGAWAN KANPUR | ₹12.6 Cr Quoted ₹13.6 Cr | L1 | Accepted-AOC Low Rate |
| 2 | L2₹13.8 Cr+₹19.8 L (1.46%)Rejected-Finance | ₹13.8 Cr+₹19.8 L (1.46%) | L2 | Rejected-Finance High Rate |
| 3 | Rejected-Technical 00 KHRAUTI RAMPUR BASTI BASTI UTTAR PRADESH 272124 | BASTI | UTTAR PRADESH | 272124 | - | - | Rejected-Technical Non Responsive |
Tender Value
₹14.0 Cr
EMD Value
₹28.0 L
Closing Date
22 Mar 2025, 12:00 pmClosed
SE Kanpur Circle, PWD, 16/22 Civil Lines Kanpur
SE Kanpur Circle, PWD, 16/22 Civil Lines Kanpur
WIDENING AND STRENGTHENING OF CHS KM-14 TO RAMAIPUR KAINDHA ROAD KM-7 TO PIPAURI-GAMBHIRPUR -DAKSHIN-MANNIPURWA-KAINDHA-DEVINPURWA TO ITARA ROAD (INCLUDING 5 YEARS MAINTENANCE COST).
2025_CEKNP_1017979_1
1940C/131C-KV/2024-25 Dt. 07.03.2025
Open Tender
Civil Works - Roads
Item Rate
365 days
Kanpur Nagar
Please refer tender documents
2 documents required · 2 mandatory
₹7,714
₹28.0 L
Yes
SE Kanpur Circle, PWD, 16/22 Civil Lines Kanpur
17 Dec 2025
17 Mar 2025
22 Mar 2025
17 Mar 2025
22 Mar 2025
17 Mar 2025
18 Mar 2025
Amount
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m.
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2.
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. (For Compaction only)
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete asper MORT&H specficatin clause no.401.
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. As per clause no. 406
Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. As per clause no. 502
Providing and applying tack coat with bitumen VG-10 using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.asper MORT&H specficatin clause no.503. (Rate Including Bitumin VG-10)
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP-120 TPH using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Rate Including Bitumin VG-30) (Grading-II)
Providing and laying bituminous concrete with higher capacity batch type hot mix plant 120 TPH using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects Grading-II.(Rate Including Bitumin VG-30)
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing as per specification clause no. 602.
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.asper MORT&H specficatin clause no.2100.
Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications.(Grade M20) asper MORT&H specficatin clause no.1500,1700 &2200.
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications.asper MORT&H specficatin clause no.1600.
Brick Masonry Work in Cement Mortar 1:3 in sub strructure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.asper MORT&H specficatin clause no.1300.
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications asper MORT&H specficatin clause no.1300 &2200.
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications asper MORT&H specficatin clause no.1300 & 2200
Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets. as per technical specification no. 2900 (1000 mm dia)
Laying Reinforced cement concrete pipe NP3 / prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets . (600 mm dia)
Lettering and painting of culvert and parapet etc. complete.
Markings of centre line, Road edge lines on both side of Road with hot applied thermoplastic road marking paint material conforming to MORT&H clause 803.4.2 and marking complete as per clause 803 of MORT&H specifications 2004 (up to date revision)
Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing
Supply fixing of delineators( Road way indicators hazard marker, object marker)80 to 100 cm high above fixing bed level, painted block and white in 15 cm wide strips fitted with 80X100mm rectangular or 75 mm dia circular reflectorized panel at top ,buried or pressed into the ground and conforming to IRC 79 and the drawing.
Maintenance of bituminous surface road and / or gravel road and / or WBM road including filling of pot holes and patch repair etc., restoration of rain cuts and dressing of side slopes / berms, making up of berms / shoulders, maintenance of drains, maintenance of guard rail and parapets, maintenance of road signs, speed breakers, standing tree adjacent to road wherever required, maintenance of 200m (hectometre stone) and kilometre stones, cutting of branches of trees, shrubs and trimming of grass and weeds etc., white washing of parapets including CD works, painting of guard stones and Re-Fidding of displaced guard stones etc. as per Direction of E/I for the period of Five Year from the actual completion of work. (Excluding G.S.T.) (as per performance Index Annexure-1) mentioned in GO No. 17/2024/sa-113/23-1- 2024-23-1099/113/2023 dated 16.01.2024 & Enc Letter no. 3689/C- OPRMC/MUL-2023-24 dated 17.02.2024) (I) Maintenance of First Year (@0% of Total Work Amount of 1 to 23)
Maintenance of bituminous surface road and / or gravel road and / or WBM road including filling of pot holes and patch repair etc., restoration of rain cuts and dressing of side slopes / berms, making up of berms / shoulders, maintenance of drains, maintenance of guard rail and parapets, maintenance of road signs, speed breakers, standing tree adjacent to road wherever required, maintenance of 200m (hectometre stone) and kilometre stones, cutting of branches of trees, shrubs and trimming of grass and weeds etc., white washing of parapets including CD works, painting of guard stones and Re-Fidding of displaced guard stones etc. as per Direction of E/I for the period of Five Year from the actual completion of work. (Excluding G.S.T.) (as per performance Index Annexure-1) mentioned in GO No. 17/2024/sa-113/23-1- 2024-23-1099/113/2023 dated 16.01.2024 & Enc Letter no. 3689/C- OPRMC/MUL-2023-24 dated 17.02.2024) (II) Maintenance of Second Year (@0.25% of Total Work Amount of 1 to 23)
Maintenance of bituminous surface road and / or gravel road and / or WBM road including filling of pot holes and patch repair etc., restoration of rain cuts and dressing of side slopes / berms, making up of berms / shoulders, maintenance of drains, maintenance of guard rail and parapets, maintenance of road signs, speed breakers, standing tree adjacent to road wherever required, maintenance of 200m (hectometre stone) and kilometre stones, cutting of branches of trees, shrubs and trimming of grass and weeds etc., white washing of parapets including CD works, painting of guard stones and Re-Fidding of displaced guard stones etc. as per Direction of E/I for the period of Five Year from the actual completion of work. (Excluding G.S.T.) (as per performance Index Annexure-1) mentioned in GO No. 17/2024/sa-113/23-1- 2024-23-1099/113/2023 dated 16.01.2024 & Enc Letter no. 3689/C- OPRMC/MUL-2023-24 dated 17.02.2024) (III) Maintenance of Third Year (@0.50% of Total Work Amount of 1 to 23)
Maintenance of bituminous surface road and / or gravel road and / or WBM road including filling of pot holes and patch repair etc., restoration of rain cuts and dressing of side slopes / berms, making up of berms / shoulders, maintenance of drains, maintenance of guard rail and parapets, maintenance of road signs, speed breakers, standing tree adjacent to road wherever required, maintenance of 200m (hectometre stone) and kilometre stones, cutting of branches of trees, shrubs and trimming of grass and weeds etc., white washing of parapets including CD works, painting of guard stones and Re-Fidding of displaced guard stones etc. as per Direction of E/I for the period of Five Year from the actual completion of work. (Excluding G.S.T.) (as per performance Index Annexure-1) mentioned in GO No. 17/2024/sa-113/23-1- 2024-23-1099/113/2023 dated 16.01.2024 & Enc Letter no. 3689/C- OPRMC/MUL-2023-24 dated 17.02.2024) (IV) Maintenance of Fourth Year (@0.75% of Total Work Amount of 1 to 23)
Maintenance of bituminous surface road and / or gravel road and / or WBM road including filling of pot holes and patch repair etc., restoration of rain cuts and dressing of side slopes / berms, making up of berms / shoulders, maintenance of drains, maintenance of guard rail and parapets, maintenance of road signs, speed breakers, standing tree adjacent to road wherever required, maintenance of 200m (hectometre stone) and kilometre stones, cutting of branches of trees, shrubs and trimming of grass and weeds etc., white washing of parapets including CD works, painting of guard stones and Re-Fidding of displaced guard stones etc. as per Direction of E/I for the period of Five Year from the actual completion of work. (Excluding G.S.T.) (as per performance Index Annexure-1) mentioned in GO No. 17/2024/sa-113/23-1- 2024-23-1099/113/2023 dated 16.01.2024 & Enc Letter no. 3689/C- OPRMC/MUL-2023-24 dated 17.02.2024) (IV) Maintenance of Fifth Year (@1.00% of Total Work Amount of 1 to 23)
THE SHELTER (BID ID -5067922)
stage.html
html • 0.01 MB
tech_eval
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
166015060.xls
BOQ Document • 0.28 MB
166015061.pdf
Tender Document • 1.31 MB
AddendumPipauri_merged.pdf
Tender Document • 2.94 MB
166015063.html
Tender Document • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .