| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹95,000Admitted-Finance | ₹95,000 | L1 | Admitted-Finance |
| 2 | L2₹99,000Admitted-Finance | ₹99,000 | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | kaushal kishor L1 | ABDUL KAYYUM CONTRACTOR L2 |
|---|---|---|---|---|---|
| 1.00Dismantling and Auctioning of Brick work on as is where is basis based on assessment of work as per prevailing site (Reference Rate):- | |||||
| 1.01Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | |||||
| 1.02Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): 3. From brick work in cement mortar | |||||
| 1.03Demolishing mud phaska in terracing and disposal of material within 50 metres lead. | |||||
| 1.04Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. | |||||
| 1.05Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) | |||||
| 1.06Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead : 1. Of area 3 sq. metres and below | |||||
| 1.07Dismantling cement conglomerate / terrazzo floors 25 mm to 50 mm manually/ by mechanical means and disposal of material within standard lead as per direction of Engineer- in-charge. | |||||
| 1.08Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 2. 100 mm dia pipe | |||||
| 1.09 | By Mechanical Transport including loading, unloading and stacking
18. Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead up to 10 km for all lifts, complete as per directions of Engineer-in-charge.
(H1 will be considered as L1) | 1 | L/S | 95,000 ₹95,000 | 99,000 ₹99,000 |
Updated dates
Tender Value
₹1 L
EMD Value
₹10,000
Closing Date
29 Apr 2026, 2:00 pmClosed
Superintending Engineer
JC Bose UST
Dismantling of Guest House of Old Staff Quarter No. 6C Guest House as is where is basis in the JC Bose University of Science and Technology, YMCA, Faridabad.
2026_HRY_516009_1
JCB/UST/Emnt No.
Open Tender
Civil Works
30 days
Faridabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Yes
₹10,000
Yes
4 May 2026
18 Apr 2026
29 Apr 2026
18 Apr 2026
29 Apr 2026
18 Apr 2026
Dismantling and Auctioning of Brick work on as is where is basis based on assessment of work as per prevailing site (Reference Rate):-
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.
Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): 3. From brick work in cement mortar
Demolishing mud phaska in terracing and disposal of material within 50 metres lead.
Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.
Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix)
Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead : 1. Of area 3 sq. metres and below
Dismantling cement conglomerate / terrazzo floors 25 mm to 50 mm manually/ by mechanical means and disposal of material within standard lead as per direction of Engineer- in-charge.
Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 2. 100 mm dia pipe
By Mechanical Transport including loading, unloading and stacking 18. Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead up to 10 km for all lifts, complete as per directions of Engineer-in-charge. (H1 will be considered as L1)
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.50 MB
BOQ_594864.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid