Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹25.9 CrAccepted-AOC BAKRON KA WADA NEAR NEELAM CINEMA JODHPUR ROAD BALOTRA BARMER RAJASTHAN 344022 | BALOTRA | BARMER | RAJASTHAN | 344022 | ₹25.9 Cr Quoted ₹26.1 Cr | L1 | Accepted-AOC 1ST LOWEST BIDDER |
| 2 | L2₹26.6 Cr+₹49.1 L (1.88%)Rejected-Finance L 87 STREET NO 7C MAHIPALPUR EXTENSION NEW DELHI 110037 | NEW DELHI | NEW DELHI | DELHI | 110037 | ₹26.6 Cr+₹49.1 L (1.88%) | L2 | Rejected-Finance Being 2nd lowest bidder |
| 3 | L3₹29.8 Cr+₹3.7 Cr (14.4%)Rejected-Finance 401 THE GRAND MALL OPP STATE BANK ZONAL OFFICE S M ROAD AMBAWADI AHMEDABAD 380015 | AHMADABAD | GUJARAT | 380015 | ₹29.8 Cr+₹3.7 Cr (14.4%) | L3 | Rejected-Finance Being 3rd lowest bidder |
| 4 | Rejected-Technical | - | - | Rejected-Technical NOT APPROVED |
| 5 | Rejected-Technical | - | - | Rejected-Technical NOT APPROVED |
| Sl No | Description | Qty | Unit | Brahma Infra L1 | NSC Projects Pvt. Ltd. L2 | Dineshchandra R.Agrawal Infracon Pvt.Ltd L3 |
|---|---|---|---|---|---|---|
| 1.00 | Demolition of concrete of any description and in any position not otherwise specifically provided for as directed by Engr-in-charge.( Note : The concrete shall be demolished in panels /as required at site . In panels the concrete shall be cut sharply around all the four edges/edges as per site by diamond cutter upto the full depth of concrete, before demolition of panels without disturbing the existing concrete in adjacent panels. | 16,996 | Cum | 1,000 ₹1,69,96,000 | 550 ₹93,47,800 Lowest | 800 ₹1,35,96,800 |
| 2.00 | Earth work in excavation by mechanical means (Hydraulic excavator) over areas not exceeding 1.5m in depth, getting out in hard and dense soil (WBM/GSB) complete all as specified and as directed. | 7,689 | Cum | 150 ₹11,53,350 | 120 ₹9,22,680 Lowest | 120 ₹9,22,680 Lowest |
| 3.00 | Earth work in excavation by mechanical means (Hydraulic excavator) over areas not exceeding 1.5m in depth, getting out in any type of soil complete all as specified and as directed. | 17,788 | Cum | 150 ₹26,68,200 | 120 ₹21,34,560 | 110 ₹19,56,680 Lowest |
| 4.00 | Removing demolished concrete debris (retrieved from PQC/DLC) to the crusher plant, not exc 5km distance including loading, Unloading, depositing and stacking at the destination , complete all as specified and as directed. | 12,876 | Cum | 160 ₹20,60,160 | 250 ₹32,19,000 | 140 ₹18,02,640 Lowest |
| 5.00 | Removing the surplus/unserviceable concrete debris obtained from item No. 1 here-in-before and item No 7 here-in-after loading and unloading and depositing outside MoD land. Disposal of debris outside MoD land disposal of debris outside MoD land is the responsibility of contractor and no extra payment will be allowed for lead and lift for removal and deposition of debris beyond the MoD land complete all as specified and directed. | 8,035 | Cum | 200 ₹16,07,000 | 300 ₹24,10,500 | 160 ₹12,85,600 Lowest |
| 6.00 | Removing the excavated soil to a distance including loading and unloading and depositing outside MoD land. Disposal of debris outside MoD land is the responsibility of contractor and no extra payment will be allowed for lead and lift for removal and disposal of debris beyond the MoD land complete all as specified and directed.. | 17,788 | Cum | 200 ₹35,57,600 | 300 ₹53,36,400 | 140 ₹24,90,320 Lowest |
| 7.00 | M&L for crushing of demolished concrete obtained from item No.1 above by using stone crusher to required grade (grade V of Table 400-1of MoRTH specifications for Road and Bridge works, 2013) including stacking the crushed material for reuse as in GSB complete all as specified all as directed. | 12,876 | Cum | 700 ₹90,13,200 | 900 ₹1,15,88,400 | 400 ₹51,50,400 Lowest |
| 8.00 | Rolling and consolidating formation surface in cutting to the required gradient and camber including filling in depression and hollow, watering, leveling etc. complete using power roller exceeding 8 tonne and not exceeding 12 tonne capacity complete all as specified and as directed.
Note:- Rolling and consolidating formation surfaces in cutting to the required gradient and camber under optimum moisture conditions to achieve at least 98% of maximum dry density determined using modified proctor density method as per revelant IS code. | 6,283 | 10 Sqm | 100 ₹6,28,300 Lowest | 100 ₹6,28,300 Lowest | 120 ₹7,53,960 |
| 9.00 | M&L for laying and compacting 150 mm thick (compacted thickness) Granular Sub Base Course (GSB) grading as per Grade V using pulverised demolished concrete obtained from item no.7 herein before, including adding any deficient material to obtain the desired grading as specified Table 400-1 of MoRTH specifications for Road and Bridge works, 2013, in a single layer over compacted subgrade with naturaI sand, crushed gravel, crushed stone, crushed slag' or combination there of as per the grading required The materials are mechanically mixed, spread and leveling on the subgrade by using motor grader of adequate capacity, and rolling with vibratory roller of capacity 80-100 KN static weight for achieving required compaction density of atleast 98% of the Maximum Dry Density. Consolidating to required gradient and camber with finished surface tolerances as per Table 900-1 of MoRTH specifications for Road and Bridge works, 2013. complete all as specified and directed.
Note:- 1) The rate includes pulverization, grading as per GSB grade V and lead of crushed material to the laying location. | 4,043 | 10 Sqm | 600 ₹24,25,800 Lowest | 600 ₹24,25,800 Lowest | 1,600 ₹64,68,800 |
| 10.00 | M&L for laying and compacting 250 mm thick (compacted thickness) Granular Sub Base Course (GSB) grading as per Grade V using pulverised demolished concrete obtained from item No. 07 herein before,including adding any deficient material to obtain the desired grading as specified Table 400-1 of MoRTH specifications for Road and Bridge works, 2013, in two layers of 125mm each(compacted thickness) over compacted subgrade with naturaI sand, crushed gravel, crushed stone, crushed slag' or combination there of as per the grading required The materials are mechanically mixed, spread and leveling on the subgrade by using motor grader of adequate capacity, and rolling with vibratory roller of capacity 80-100 KN static weight for achieving required compaction density of atleast 98% of the Maximum Dry Density. Consolidating to required gradient and camber with finished surface tolerances as per Table 900-1 of MoRTH specifications for Road and Bridge works, 2013. complete all as specified and directed.
Note:- 1) The rate includes pulverization, grading as per GSB grade V and lead of crushed material to the laying location. | 1,158 | 10 Sqm | 1,000 ₹11,58,000 Lowest | 1,000 ₹11,58,000 Lowest | 2,700 ₹31,26,600 |
Tender Value
₹31.3 Cr
EMD Value
₹15 L
Closing Date
29 May 2026, 6:00 pmClosed
CE (AF) WAC PALAM
HQ CE (AF) WAC PALAM DELHI CANTT-10
STRUCTURAL REHABILTATION OF CERTAIN CONCRETE SLABS ON BISON LOOPS, TAXIWAY INCLUDING LINKS OF ALL BPS, SUN SHELTER AND SURROUNDING AREA AT AF STN SURATGARH
2026_MES_759008_1
CEWAC/SUR/T-26/2025-26
Open Tender
Civil Works
Item Rate
630 days
GE (AF) SURATGARH
Please refer Tender documents.
9 documents required · 9 mandatory
₹3,000
GE (AF) SURATGARH
₹15 L
Yes
HQ CE (AF) WAC PALAM DELHI CANTT
24 Jul 2026
1 May 2026
1 Jun 2026
1 May 2026
29 May 2026
22 May 2026
12 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolition of concrete of any description and in any position not otherwise specifically provided for as directed by Engr-in-charge.( Note : The concrete shall be demolished in panels /as required at site . In panels the concrete shall be cut sharply around all the four edges/edges as per site by diamond cutter upto the full depth of concrete, before demolition of panels without disturbing the existing concrete in adjacent panels. | 16,996 | Cum | - | - |
| - | Earth work in excavation by mechanical means (Hydraullic excavator) over areas not exceeding 1.5m in depth, getting out in hard and dense soil (WBM/GSB) complete all as specified and as directed. | 7,689 | Cum | - | - |
| - | Earth work in excavation by mechanical means (Hydraullic excavator) over areas not exceeding 1.5m in depth, getting out in any type of soil complete all as specified and as directed. | 17,788 | Cum | - | - |
| - | Removing demolished concrete debris (retrieved from PQC/DLC) to the crusher plant, not exc 5km distance including loading, Unloading, depositing and stacking at the destination , complete all as specified and as directed. | 12,876 | Cum | - | - |
| - | Removing the surplus/unserviceable concrete debris obtained from item No. 1 here-in-before and item No 7 here-in-after loading and unloading and depositing outside MoD land. Disposal of debris outside MoD land disposal of debris outside MoD land is the responsibility of contractor and no extra payment will be allowed for lead and lift for removal and deposition of debris beyond the MoD land complete all as specified and directed. | 8,035 | Cum | - | - |
| - | Removing the excavated soil to a distance including loading and unloading and depositing outside MoD land. Disposal of debris outside MoD land is the responsibility of contractor and no extra payment will be allowed for lead and lift for removal and disposal of debris beyond the MoD land complete all as specified and directed.. | 17,788 | Cum | - | - |
| - | M&L for crushing of demolished concrete obtained from item No.1 above by using stone crusher to required grade (grade V of Table 400-1of MoRTH specifications for Road and Bridge works, 2013) including stacking the crushed material for reuse as in GSB complete all as specified all as directed. | 12,876 | Cum | - | - |
| - | Rolling and consolidating formation surface in cutting to the required gradient and camber including filling in depression and hollow, watering, leveling etc. complete using power roller exceeding 8 tonne and not exceeding 12 tonne capacity complete all as specified and as directed.
Note:- Rolling and consolidating formation surfaces in cutting to the required gradient and camber under optimum moisture conditions to achieve at least 98% of maximum dry density determined using modified proctor density method as per revelant IS code. | 6,283 | 10 Sqm | - | - |
| - | M&L for laying and compacting 150 mm thick (compacted thickness) Granular Sub Base Course (GSB) grading as per Grade V using pulverised demolished concrete obtained from item no.7 herein before, including adding any deficient material to obtain the desired grading as specified Table 400-1 of MoRTH specifications for Road and Bridge works, 2013, in a single layer over compacted subgrade with naturaI sand, crushed gravel, crushed stone, crushed slag' or combination there of as per the grading required The materials are mechanically mixed, spread and leveling on the subgrade by using motor grader of adequate capacity, and rolling with vibratory roller of capacity 80-100 KN static weight for achieving required compaction density of atleast 98% of the Maximum Dry Density. Consolidating to required gradient and camber with finished surface tolerances as per Table 900-1 of MoRTH specifications for Road and Bridge works, 2013. complete all as specified and directed.
Note:- 1) The rate includes pulverization, grading as per GSB grade V and lead of crushed material to the laying location. | 4,043 | 10 Sqm | - | - |
| - | M&L for laying and compacting 250 mm thick (compacted thickness) Granular Sub Base Course (GSB) grading as per Grade V using pulverised demolished concrete obtained from item No. 07 herein before,including adding any deficient material to obtain the desired grading as specified Table 400-1 of MoRTH specifications for Road and Bridge works, 2013, in two layers of 125mm each over compacted subgrade with naturaI sand, crushed gravel, crushed stone, crushed slag' or combination there of as per the grading required The materials are mechanically mixed, spread and leveling on the subgrade by using motor grader of adequate capacity, and rolling with vibratory roller of capacity 80-100 KN static weight for achieving required compaction density of atleast 98% of the Maximum Dry Density. Consolidating to required gradient and camber with finished surface tolerances as per Table 900-1 of MoRTH specifications for Road and Bridge works, 2013. complete all as specified and directed.
Note:- 1) The rate includes pulverization, grading as per GSB grade V and lead of crushed material to the laying location. | 1,158 | 10 Sqm | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.99 MB
BOQ_854713.xls
BOQ • 0.33 MB
Tender.pdf
Tender Documents • 8.33 MB
doc02865420260520165754.pdf
PDF • 15.95 MB
Letter.pdf
PDF • 0.70 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .