| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹49.2 LAccepted-AOC | ₹49.2 L Quoted ₹49.8 L | L1 | Accepted-AOC AOC |
| 2 | L2₹51.0 L+₹1.2 L (2.34%)Rejected-Finance | ₹51.0 L+₹1.2 L (2.34%) | L2 | Rejected-Finance HIGHER THAN L1 BIDDER |
| 3 | L3₹52.0 L+₹2.2 L (4.38%)Rejected-Finance | ₹52.0 L+₹2.2 L (4.38%) | L3 | Rejected-Finance HIGHER THAN L1 BIDDER |
| 4 | L4₹53.4 L+₹3.6 L (7.12%)Rejected-Finance | ₹53.4 L+₹3.6 L (7.12%) | L4 | Rejected-Finance HIGHER THAN L1 BIDDER |
| 5 | L5₹54.7 L+₹4.9 L (9.76%)Rejected-Finance | ₹54.7 L+₹4.9 L (9.76%) | L5 | Rejected-Finance HIGHER THAN L1 BIDDER |
| Sl No | Description | Qty | Unit | RAJA RAM AND COMPANY L2 | M/S MAA TARA TREATMENT PROJECT L3 | LOKESH BUILDERS L1 | JOG CONSTRUCTION L6 | ASIA BUILDER L7 | FATEHPUR CONSTRUCTION COMPANY L8 | ARORA BROTHERS L4 | M/S BASANT CONSTRUCTION COMPANY L5 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Dismantling floor hearth or wall tiling including cement mortar bedding (but not backing) complete all as specified and directed. | 478 | Sqm | 22 ₹10,516 Lowest | 25 ₹11,950 | 30 ₹14,340 | 30 ₹14,340 | 55 ₹26,290 | 66 ₹31,548 | 44 ₹21,032 | 45 ₹21,510 |
| 2.00 | Demolition of brick work or stone/boulders masanory built in cement mortar including all quoins, arches, pillars etc, but excluding ashler facing, dressed stone work and precast concrete articals complete all as specified and directed. | 1 | Cum | 300 ₹300 Lowest | 350 ₹350 | 900 ₹900 | 400 ₹400 | 650 ₹650 | 600 ₹600 | 1,000 ₹1,000 | 1,050 ₹1,050 |
| 3.00 | Taking down cement plaster on wall including raking out joint, hacking for key scrubbing down with water etc complete all as specified and directed. | 800 | Sqm | 22 ₹17,600 Lowest | 25 ₹20,000 | 60 ₹48,000 | 30 ₹24,000 | 55 ₹44,000 | 55 ₹44,000 | 70 ₹56,000 | 75 ₹60,000 |
| 4.00 | Dismantling PVC water tanks and remove to store capacity exc 500 Ltrs and n exc 1000 Ltrs complete all as specified and directed. | 16 | Each | 180 ₹2,880 Lowest | 200 ₹3,200 | 500 ₹8,000 | 200 ₹3,200 | 400 ₹6,400 | 411 ₹6,576 | 550 ₹8,800 | 560 ₹8,960 |
| 5.00 | Taking up or down steel tubing and connections of 15 mm bore complete all as specified and directed. | 100 | RM | 8 ₹800 Lowest | 9 ₹900 | 20 ₹2,000 | 23 ₹2,300 | 20 ₹2,000 | 20 ₹2,000 | 25 ₹2,500 | 30 ₹3,000 |
| 6.00 | Taking up or down 20 mm dia steel tubing and connection including removal of fittings of any type and material complete all as specified and directed. | 40 | RM | 10 ₹400 Lowest | 11 ₹440 | 25 ₹1,000 | 25 ₹1,000 | 21 ₹840 | 24 ₹960 | 30 ₹1,200 | 40 ₹1,600 |
| 7.00 | Taking down chowkhat or frames with shutter (without taking off shutters from the frame) n. exc 1.5 sqm complete all as specified and as directed. | 45 | Each | 65 ₹2,925 Lowest | 66 ₹2,970 | 100 ₹4,500 | 100 ₹4,500 | 100 ₹4,500 | 144 ₹6,480 | 120 ₹5,400 | 130 ₹5,850 |
| 8.00 | Taking down chowkhat or frames with shutter (without taking off shutters from the frame) exc 1.5 sqm n exc 4 sqm each complete all as specified and as directed. | 63 | Each | 80 ₹5,040 Lowest | 88 ₹5,544 | 150 ₹9,450 | 140 ₹8,820 | 100 ₹6,300 | 100 ₹6,300 | 170 ₹10,710 | 175 ₹11,025 |
| 9.00 | Dismantling of 75 to 100 mm dia CI pipes/fittings jointed in cement mortar fixed to wall or laid in trenches and taking out if required complete all as specified and directed. | 80 | RM | 15 ₹1,200 Lowest | 17 ₹1,360 | 60 ₹4,800 | 30 ₹2,400 | 20 ₹1,600 | 22 ₹1,760 | 120 ₹9,600 | 70 ₹5,600 |
| 10.00 | Dismantling of wrought iron or mild steel work of any description not otherwise provided for complete all as specified and directed. | 0.95 | Qtl | 240 ₹228 Lowest | 555 ₹527.25 | 500 ₹475 | 400 ₹380 | 600 ₹570 | 600 ₹570 | 500 ₹475 | 560 ₹532 |
Tender Value
₹48.6 L
EMD Value
₹97,300
Closing Date
27 Jun 2026, 6:00 pmClosed
Lt Col, Vikramjeet Singh Reen
GE I Kanpur Cariappa Road Cantt Kanpur 208004
SPL REPAIR TO BLDG NO P-145/1 TO 8 (SINGLE JCOs LIVING ACCN) OF 8 RAJ RIF UNDER GE (I) KANPUR AND SPL REPAIR TO BLDG NO P-58/1 TO 8 (SINGLE LIVING ACCN) OF 326 LT AD REGT (COMP) UNDER GE (I) KANPUR
2026_MES_770234_1
GE(I)/KAN/T-07 OF 2026-27
Open Tender
Civil Works
Item Rate
180 days
KANPUR
AS PER TENDER DOCUMENTS
8 documents required · 8 mandatory
₹500
GE(I) KANPUR
₹97,300
Yes
10 Sept 2026
6 Jun 2026
4 Jul 2026
6 Jun 2026
27 Jun 2026
20 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling floor hearth or wall tiling including cement mortar bedding (but not backing) complete all as specified and directed. | 478 | Sqm | - | - |
| 2 | Demolition of brick work or stone/boulders masanory built in cement mortar including all quoins, arches, pillars etc, but excluding ashler facing, dressed stone work and precast concrete articals complete all as specified and directed. | 1 | Cum | 2 | ₹2 |
| 3 | Taking down cement plaster on wall including raking out joint, hacking for key scrubbing down with water etc complete all as specified and directed. | 800 | Sqm | 3 | ₹2,400 |
| 4 | Dismantling PVC water tanks and remove to store capacity exc 500 Ltrs and n exc 1000 Ltrs complete all as specified and directed. | 16 | Each | 4 | ₹64 |
| 5 | Taking up or down steel tubing and connections of 15 mm bore complete all as specified and directed. | 100 | RM | 5 | ₹500 |
| 6 | Taking up or down 20 mm dia steel tubing and connection including removal of fittings of any type and material complete all as specified and directed. | 40 | RM | 7 | ₹280 |
| 7 | Taking down chowkhat or frames with shutter (without taking off shutters from the frame) n. exc 1.5 sqm complete all as specified and as directed. | 45 | Each | 8 | ₹360 |
| 8 | Taking down chowkhat or frames with shutter (without taking off shutters from the frame) exc 1.5 sqm n exc 4 sqm each complete all as specified and as directed. | 63 | Each | 9 | ₹567 |
| 9 | Dismantling of 75 to 100 mm dia CI pipes/fittings jointed in cement mortar fixed to wall or laid in trenches and taking out if required complete all as specified and directed. | 80 | RM | 10 | ₹800 |
| 10 | Dismantling of wrought iron or mild steel work of any description not otherwise provided for complete all as specified and directed. | 0.95 | Qtl | 11 | ₹10.45 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.24 MB
TenderdocumentsT07.pdf
Tender Documents • 1.61 MB
BOQ_862568.xls
BOQ • 2.91 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .