Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | H1₹4.1 CrAdmitted-Finance 2 1909 KUDI BHAGATASANI HOUSING BOARD JODHPUR RAJASTHAN 342001 | JODHPUR | JODHPUR | RAJASTHAN | 342001 | -8.02% | ₹4.1 Cr | H1 | Admitted-Finance |
| 2 | H2₹3.7 Cr−₹34.8 L (8.50%)Admitted-Finance SHOP NO 05 SHYAM PLAZA NEAR SHIVRAJ STADIUM RANIWARA ROAD BHIMNAL DISTT JALORE | BHIMNAL | JALORE | RAJASTHAN | -15.84% | ₹3.7 Cr−₹34.8 L (8.50%) | H2 | Admitted-Finance |
| 3 | H3₹3.7 Cr−₹37.3 L (9.11%)Admitted-Finance | -16.40% | ₹3.7 Cr−₹37.3 L (9.11%) | H3 | Admitted-Finance |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹4.5 Cr
EMD Value
₹8.9 L
Closing Date
12 Feb 2026, 6:00 pmClosed
Executive Officer Municipal Board Bhinmal
Executive Officer Municipal Board Bhinmal
Construction of Nallah Diversion from Jakhob Talab and Neelkanth Mahadev Temple to Khajuriya Nallah for Drainage Improvement and Pond Aeration at Bhinmal
2026_DLB_530975_1
E12 5273
Open Tender
Civil Works
Percentage
365 days
Municipal Area Bhinmal
As per NIT and Bid Document
2 documents required · 2 mandatory
₹10,000
MD RISL
₹8.9 L
Yes
27 Feb 2026
22 Jan 2026
13 Feb 2026
22 Jan 2026
12 Feb 2026
22 Jan 2026
22 Jan 2026 - 12 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Cutting of trees, including cutting of trunks, branches and removal of stumps, roots stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit to required compaction as per MoRT&H specification clause 201. (Measurement of girth to be done at height of 1 m above ground level).Girth from 300 mm to 600 mm.for Waste water Drain | 20 | Nos | - | - |
| 2.01 | Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 50 metres as directed by Engineer.Cement Concrete Grade M-15 and above and PCC blocks | 120 | Cum | - | - |
| 3.01 | Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 50 metres as directed by Engineer.Bituminous courses | 280 | Cum | - | - |
| 4.01 | Dismantling of existing LT/HTelectric lines including poles/towers, ACSR conductors, guard wires, stay wire, insulators and other electrical items of the pole coming along the alignment of the road or in the plant premises and removal and transportation as well as disposal of all the items as per the direction of engineer incharge.(Serviceable material or can-dum material.) | 5 | Each | - | - |
| 5.01 | De-jointing and removing of already laid CI/DI/MS/AC pipes of following diameters in excavated trenches with care, without damaging pipes, CID joints, valves, pecials etc. and other materials and then refilling of soil after de-laying and de-jointing of pipelines with proper compaction and disposing of all surplus soil as directed within a lead of 50 mtr. This also include stacking the pipes with care and transporting the same to div./sub div. store or as directed by EIC with in the division. (Rates are Exclusive of Earth Work) 80 mm | 50 | Mtr | 0.9 | ₹45 |
| 6.01 | De-jointing and removing of already laid CI/DI/MS/AC pipes of following diameters in excavated trenches with care, without damaging pipes, CID joints, valves, pecials etc. and other materials and then refilling of soil after de-laying and de-jointing of pipelines with proper compaction and disposing of all surplus soil as directed within a lead of 50 mtr. This also include stacking the pipes with care and transporting the same to div./sub div. store or as directed by EIC with in the division. (Rates are Exclusive of Earth Work) 100 mm | 15 | Mtr | 0.9 | ₹13.5 |
| 7.01 | De-jointing and removing of already laid CI/DI/MS/AC pipes of following diameters in excavated trenches with care, without damaging pipes, CID joints, valves, pecials etc. and other materials and then refilling of soil after de-laying and de-jointing of pipelines with proper compaction and disposing of all surplus soil as directed within a lead of 50 mtr. This also include stacking the pipes with care and transporting the same to div./sub div. store or as directed by EIC with in the division. (Rates are Exclusive of Earth Work) 125 mm | 25 | Mtr | - | - |
| 8.01 | Providing, constructing coffer dam in river basin / dam storages as per type design including excavation, filling the middle portion with B.C. soil (in gunny bags if required). Providing impervious / semipervious materials on both sides of B.C. soil (in gunny bags if required) including ramming, compacting to the satisfaction of Engineer-in-charge till the completion of work including dismantling coffer dam after completion of works and disposing off the material as directed by the Engineer-in-charge. Note : Maximum top width payable shall be 2 Mtr. and maximum payable side slopes shall be 1.5 horizontal to 1 vertical, if the constructed top width of the side slopes are less, then the measurements at actual are payable. Extra top width or flat slopes are not payable. Contractor is free to use ballies, plastic sheets, piles, pipes, CGI sheets for supporting hearting materials instead of impervious/ semi-pervious hearting materials for which no extra payments shall be payable. 30% payment shall be withheld for dismantling of coffer dam. | 15 | Cum | - | - |
| 9.01 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. | 8,357.33 | Cum | - | - |
| 10.01 | Earth filling with available surplus soil excavated from foundations and taken only from outside of building plinth in layers not exceeding 20cm in depth, consolidating each deposited layer including ramming and watering and consolidation with lead up to 50 m and lift upto 1.5 m. | 2,944.15 | Cum | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.78 MB
BIDDOCUMENTE12_compressed.pdf
Tender Documents • 4.11 MB
BOQ_946448.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .