| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.4 CrAccepted-AOC KHOITADIH PROJECT BILPAHARI BARDHAMAN BARDHAMAN 713378 WEST BENGAL INDIA | BARDHAMAN | BARDHAMAN | WEST BENGAL | 713378 | ₹1.4 Cr | L1 | Accepted-AOC TC recommendation |
| 2 | L2₹1.4 Cr+₹3.3 L (2.36%)Rejected-Finance PANDANESWAR BARDHAMAN BARDHAMAN 713346 WEST BENGAL INDIA | BARDHAMAN | BARDHAMAN | WEST BENGAL | 713346 | ₹1.4 Cr+₹3.3 L (2.36%) | L2 | Rejected-Finance TC recommendation |
Tender Value
₹1.4 Cr
EMD Value
₹1.7 L
Closing Date
30 Apr 2024, 12:00 pmClosed
General Manager
Office of The General Manager Bankola Area, PIN-713363
Installation and commissioning of 05 nos. of 1000mm wide conveyor Belt in Panel No. TB2, TB3, PB2, PB3 of RVIIB seam of CM Project at Nakrakonda Kumardihi B Colliery under Bankola Area
2024_ECL_306484_1
ECL/GM/BA/E TENDER/24-25/EnM/01 Dt 10.04.2024
Open Tender
Electrical and Maintenance Works
Item Rate
180 days
Nakrakonda Kumardihi B Colliery
Please refer to NIT document
5 documents required · 5 mandatory
₹1.7 L
6 Aug 2024
11 Apr 2024
1 May 2024
11 Apr 2024
30 Apr 2024
11 Apr 2024
11 Apr 2024 - 15 Apr 2024
Amount
Item Description/ Heading
Transportation & installation of complete drive drum, driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-392mtr @68Kg/mtr =26.65MT+6 times Tail end shifting (extension)-6MT= total weight =53.25 MT
Fitting of tail end , mid belt and discharge scraper.
Belt laying including transporting of belt, jointing, tensioning, trail run etc
Foundation, bolting for fitting of drive unit , discharge unit , loop take up & tail end etc =120nos
Cleaning of coal & unused materials before installation job
Making, fabrication, transportation and fitting of Load table
Fencing of drive ,loop take up & tail end .
Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding, gas cutting etc. considering cost of consumables.
Dismantling of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+load table 01nos-1MT+ motor, winch starter & switch & cables etc.-2MT+1000mm wide conveyor structure with top, bottom roller & foot stool-392mtr @68Kg/mtr =26.65 MT= total weight = 48.25 MT
Taken out and coiling of belt
Cost of M.S. Nut bolts & washers
Cost of Belt fastener/joint E-35 Comb and grip type suitable for Mato make machine available in mines
Drive base frame , Loop take up base & discharge base cement concrete
Transportation & installation of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-260mtr @68Kg/mtr = 17.68MT+4 times Tail end shifting (extension)-4MT= total weight = 42.28MT
Fitting of tail end , mid belt and discharge scraper.
Belt laying including transporting of belt, jointing, tensioning, trail run etc
Foundation bolting for fitting of drive unit , discharge unit , loop take up & tail end etc =120nos
Cleaning of coal & unused materials before installation job
Making, fabrication, transportation and fitting of Load table
Fencing of drive ,loop take up & tail end .
Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding, gas cutting etc. considering cost of consumables.
Dismantling of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+load table 01nos-1MT+ motor, winch starter & switch & cables etc.-2MT+1000mm wide conveyor structure with top, bottom roller & foot stool-392mtr @68Kg/mtr =17.68 + 4 times Tail end shifting (shortening)-4MT= total weight = 43.28 MT
Taken out and coiling of belt
Cost of M.S. Nut bolts & washers
Cost of Belt fastener/joint E-35 Comb and grip type suitable for Mato make machine available in mines
Drive base frame , Loop take up base & discharge base cement concrete
Transportation & installation of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-392mtr @68Kg/mtr =26.65MT+6 times Tail end shifting (extension)-6MT= total weight =53.25 MT
Fitting of tail end , mid belt and discharge scraper.
Belt laying including transporting of belt, jointing, tensioning, trail run etc
Foundation bolting for fitting of drive unit , discharge unit , loop take up & tail end etc =120nos
Cleaning of coal & unused materials before installation job
Making, fabrication, transportation and fitting of Load table
Fencing of drive ,loop take up & tail end .
Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding, gas cutting etc. considering cost of consumables.
Dismantling of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+load table 01nos-1MT+ motor, winch starter & switch & cables etc.-2MT+1000mm wide conveyor structure with top, bottom roller & foot stool-392mtr @68Kg/mtr =26.65 MT= total weight +6 times Tail end shifting (shortening)-6MT= total weight =54.25 MT
Taken out and coiling of belt
Cost of M.S. Nut bolts & washers
Cost of Belt fastener/joint E-35 Comb and grip type suitable for Mato make machine available in mines
Drive base frame , Loop take up base & discharge base cement concrete
Transportation & installation of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-494mtr @68Kg/mtr =33.6MT+8 times Tail end shifting (extension)-8MT= total weight =62.2 MT
Fitting of tail end , mid belt and discharge scraper.
Belt laying including transporting of belt, jointing, tensioning, trail run etc
Foundation bolting for fitting of drive unit , discharge unit , loop take up & tail end etc =120nos
Cleaning of coal & unused materials before installation job
Making, fabrication, transportation and fitting of Load table
Fencing of drive ,loop take up & tail end .
Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding, gas cutting etc. considering cost of consumables.
Dismantling of complete drive drum driven drum with gear motor base frame -10.5MT+discharge unit-2.5MT+tail end -1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+load table 01nos-1MT+ motor, winch starter & switch & cables etc.-2MT+1000mm wide conveyor structure with top, bottom roller & foot stool-494mtr @68Kg/mtr =33.6MT+8 times Tail end shifting (shortening)-8MT= total weight =63.2 MT
Taken out and coiling of belt
Cost of M.S. Nut bolts & washers
Cost of Belt fastener/joint E-35 Comb and grip type suitable for Mato make machine available in mines
Drive base frame , Loop take up base & discharge base cement concrete
Total impact of GST for the purpose of CTC
SWAPAN KUMAR AKHULI
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .