| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAccepted-Finance | ₹4.9 L | L1 | Accepted-Finance L1 |
| 2 | L2₹4.9 LRejected-Finance | ₹4.9 L | L2 | Rejected-Finance L2 |
| 3 | L3₹5.0 LRejected-Finance | ₹5.0 L | L3 | Rejected-Finance L3 |
| Sl No | Description | Qty | Unit | Hayagreeva Earth Movers L2 | T Vaithy L3 | Ganesan Contract Company L1 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantaling the Damaged Brick work in Cement Mortor including all cost etc complete. | 7 | M3 | 315 ₹2,205 | 324 ₹2,268 | 318 ₹2,226 |
| 1.10Earth work excavation for foundation in ordinary soil, light black cotton sandy loam and dry silt including shoring, strutting, baling or pumping out water wherever necessary and refilling the sides of foundation with excavated earth in layers of 15cm thick and depositing the surplus earth at places as directed by the departmental officers with initial lead and lift | ||||||
| 1.20 | Narrow Foundation | 19 | M3 | 200 ₹3,800 | 235 ₹4,465 | 231 ₹4,389 |
| 1.30 | Open Foundation | 3 | M3 | 115 ₹345 | 118 ₹354 | 115.5 ₹346.50 |
| 1.40 | Plain cement concrete 1:4:8 mix (One cement four m-sand and eight aggregate) using 40mm size ISS gauge HBBG metal including mixing, laying, consolidating, curing, cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification | 3 | M3 | 5,522 ₹16,566 | 5,632 ₹16,896 | 5,525 ₹16,575 |
| 1.50Supplying and errecting centering to sides and soffits including supports and strutting for drainage sides and culvert body wall sides using M.S Sheets of size 90cm x 60cm and B.G 10stifened with welded mild steel angles of size 25mm x 25mm x 3mm for boarding laid over( silver oak joists ) of size 10cm x 6.50cm spread at about 90cm including all labour charges and cost and conveyance of all materials to site etc. complete Complying with Standard Specification | ||||||
| 1.60 | for Column | 31 | M2 | 1,358 ₹42,098 | 1,385 ₹42,935 | 1,358 ₹42,098 |
| 1.70 | Grade Beam | 15 | M2 | 548 ₹8,220 | 559 ₹8,385 | 548 ₹8,220 |
| 1.80Reinforced cement concrete 1:1½:3 mix (One cement one and half m-sand three aggregate) using 20mm ISS gauge HBBG metal from the approved quarry including mixing, laying, consolidating, curing cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification | ||||||
| 1.90 | Up to Basement | 5 | M3 | 9,154 ₹45,770 | 9,336 ₹46,680 | 9,160 ₹45,800 |
Tender Value
₹6.0 L
EMD Value
₹5,950
Closing Date
27 Feb 2026, 3:00 pmClosed
THE COMMISSIONER, SALEM CITY MUNICIPAL CORPORATION
Salem City Municipal Corporation, Fort Main Road, Salem
CONSTRUCTION OF COMPOUND WALL AT VAIYAPURI HIGH SCHOOL IN DIVISION NO. 39.
2026_MAWS_657562_1
E3-Est No-189-B-2025-2026
Open Tender
Civil Works
60 days
Salem City Municipal Corporation
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹5,950
23 Jun 2026
14 Feb 2026
27 Feb 2026
14 Feb 2026
27 Feb 2026
14 Feb 2026
Dismantaling the Damaged Brick work in Cement Mortor including all cost etc complete.
Earth work excavation for foundation in ordinary soil, light black cotton sandy loam and dry silt including shoring, strutting, baling or pumping out water wherever necessary and refilling the sides of foundation with excavated earth in layers of 15cm thick and depositing the surplus earth at places as directed by the departmental officers with initial lead and lift
Narrow Foundation
Open Foundation
Plain cement concrete 1:4:8 mix (One cement four m-sand and eight aggregate) using 40mm size ISS gauge HBBG metal including mixing, laying, consolidating, curing, cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification
Supplying and errecting centering to sides and soffits including supports and strutting for drainage sides and culvert body wall sides using M.S Sheets of size 90cm x 60cm and B.G 10stifened with welded mild steel angles of size 25mm x 25mm x 3mm for boarding laid over( silver oak joists ) of size 10cm x 6.50cm spread at about 90cm including all labour charges and cost and conveyance of all materials to site etc. complete Complying with Standard Specification
for Column
Grade Beam
Reinforced cement concrete 1:1½:3 mix (One cement one and half m-sand three aggregate) using 20mm ISS gauge HBBG metal from the approved quarry including mixing, laying, consolidating, curing cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification
Up to Basement
Above Basement
Brick work in cement mortar 1:5 mix using Fly Ash bricks of 230x110x70mm (8 3/4" x 41/4" x 23/4") from approved quarry including cost and conveyance of all materials to site. Loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications
Supply and fabrication and placing in position of TMT steel roads to required size and length as directed by the departmental officers including cost of binding wire, cutting, bending and tying with proper position etc., including cost and conveyance of all materials to site and all labour charges etc., complete Complying with Standard Specification
Plastering with cement mortar 1:5 mix, 12mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete . complying with std. specifications
Strucco plastering 12mm thick using HBBG chips of size 10mm and below over a base plastering with cement mortar 1:5 mix, 12mm thick including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete . complying with std. specifications
White washing one coat using best freshly burnt shell lime in all floors including cost of lime blue powder, fevical type gum brushes, scaffolding charges etc., complete complying with standard specifications.
Painting two coats with ready mixed plastic emulsion paint of 1st class quality and of approved color over a priming coat including through scraping clean removal of dirt etc., complete and including necessary plaster of paris putty wherever required
Painting two coats with best synthetic enamel paint of approved Colour for new iron works the rate is inclusive of all materials, brushes and scaffolding charges etc., complete complying with standard specification(paint should be got approved by the Departmental Engineer befor use on work.
Supplying and fixing of metal coated sheets Aluminium zinc alloy (Galvalurne) in Gms/sqm total of Both sides AZ 1:50 as per ASTMA 792 or AS 1397) in Roofing of not less than 0.50mm thickness (over all). The material shall have yield stress of 550 mega Pascal for the sheets width including lip as side tap and 150mm as longitudinal lap for earth sheet with fixing accessories like self drilling screws caps having EDPM (Ethylene proyiene Di Monama) washers, PVC caps of matching colour with roofing sheets duly coating the sheets with top polyester coating with woth medium glass of egg shell finish of 20 micron thickness over a back and primer coat of 5 to 10 micron, each duly getting the colour scheme of sheets approved including all leads and lift etc, complete and as directed by the Engineer-in-charge (All labour and materials by the contractor) Note: Payment shall be made for the laid area and NO extra payment shall be made for overlaps
Supplying, fabrication and fixing of Ornamental grill for Garidar and Including cost of convayance of all materials and all labour charge for cutting, fabricating, walding etc, complete (including one coat of primer) and fixing in proper position with concrete packing by the direction of departmental engineers instruction etc, complete and as per standard specification.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.94 MB
BOQ_788729.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid