Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.6 LAccepted-AOC | 1 | Accepted-AOC L1 | |
| 2 | 2₹1.8 L+₹6,850 (4.00%)Rejected-AOC | 2 | Rejected-AOC L2 |
Tender Value
₹1.6 L
EMD Value
₹1,600
Closing Date
13 Aug 2020, 2:00 pmClosed
SE / M-II / TTPS
Superintending Engineer, Mechanical-II, Tuticorin Thermal Power Station, Tuticorin 628004.
TTPS Mech.II AHP Unit V BAH Scrapper Conveyor feeder 5B2 Renewal of wornout bottom slope plate and its support channels water leak testing in slag bath and normalising the feeder
2020_EB_173853_1
SE / M-II / TTPS / Spec.No.182/2020-21
Open Tender
Miscellaneous Works
Item Rate
15 days
TTPS
As per BQR conditions in NIT
7 documents required · 7 mandatory
₹0
₹1,600
Yes
2 Sept 2020
29 Jul 2020
14 Aug 2020
29 Jul 2020
13 Aug 2020
29 Jul 2020
Dismantling the SCF bars by loosening the tension shaft, removing the bars, and re-fixing after completion of work in position including hire charges for T&P's
Dismantling the SCF chain after dismantling all the scrapper bars in between ‘U’ shackles and erection one length of new/ same chain, U shackles including hire charges for T&P and consumables like cutting gas etc.,
Complete dismantling of submersible idler assembly with wheel from the slag bath of the SCF and re-fixing after completion of work including cost of consumables and hire charges for T&P's etc., complete.
Arresting the side plates at 4 to 5 location both in slag bath and slope side to prevent misalignment, cutting the wornout SS slag bath bottom and slope plate from its supports channels, removing, lowering, the same transport this scrap materials to stores., cost of gouging electrode, cutting gas, consumables and hire charges and T&P's etc.,
Cutting and releasing the wornout S.S channels of slag bath bottom and slope side, fixing new SS channels and welding the same with slope, bottom plates., cost of gouging electrodes, SS electrodes etc., hire charges for T&P's etc., complete.
Transporting the bottom and slope plates from stores, lifting and placing over its support channels, sizing the plates to site requirements, zero setting, welding the edges with SS support channels by SS electrodes as per the direction of Engineer in charge., cost of consumables like SS welding electrode, gouging electrode and hire charges for T&P's etc.,
Commissioning of SCF assembly by setting, aligning of slag bath idler wheel, bottom idler wheel assembly with respect to drive and driven shaft, making necessary correction in the above said items, setting corrections with trail run, run the feeder for 24 hours without any chain slippage and set the feeder in complete shape, welding at necessary locations and put the feeder in service., cost of consumables and hire charges for T&P's etc., complete.
INDU ERECTION
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .