Tender Value
₹86 L
EMD Value
₹6.3 L
Closing Date
6 Feb 2026, 3:00 pmClosed
C.E.3
Zone 3
Imp. Of R.M.C White Topping Road from Nuri lal Hata infront of 150 fit Road to 100 fit in ward 39 Zone 03
2025_NNKAN_1069683_3
374/A.A.3/25-26
Open Tender
Civil Works
Fixed-rate
Imp. Of R.M.C White Topping Road from Nuri lal H
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,375
₹6.3 L
8 Jul 2026
27 Jan 2026
6 Feb 2026
27 Jan 2026
6 Feb 2026
27 Jan 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of gsb granular sub base by providing well graded material spreding in uniform layers with mortar grader on prepared surface comp | - | cum | 3,671 | - |
| 2 | Earth work in excavation in trenches for foundation pipe cable etc ordinary soil (loan clay or sand )including lift up to 50mm and dressing of sides and ramming of bottum and disposal of surplus excavated earth . | - | cum | 170 | - |
| 3 | Earth work in cuttine in ordinary soil lead 30 mt. & lift 1.5 mtincl lab T&P etc all comp | - | cum | 115 | - |
| 4 | Laying of base concrete 1:6:12 with cement C.Sand & 40mm Brick ballast including mat.Lab.T&P,etc all complete. ) Providing and laying in cement concrete in 1:6:12 (1 cement: 6 fine sand: 12 graded brick aggregate 40 mm. nominal size) and curing complete, including cost of formwork in foundation and floors.Ch-5 (273) | - | cum | 4,380 | - |
| 5 | R.C.C. works with cement approved coarse sand and 2 cm (3/4") gauge approved stone ballast in the proportion 1:1.5:3 (1 cement:3 aggregate) in lintels of doors and windowa etc all comp | - | cum | 8,600 | - |
| 6 | Centering and shuttering including strutting propping etc and removal of foundations footings, bases of columns, etc all comp | - | Sqm | 390 | - |
| 7 | White Topping construction of thin topping with plane cement concrete (PCC-M40 ( payment over existing surface with approve grade cement at 430 kg per Cum and as per IRC ssp-76 etc all comp | - | cum | 9,803.72 | - |
| 8 | Construction of gully pit as per design on KNN etc all comp | - | Nos | 5,180 | - |
| 9 | Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not include in overall rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authrized overlapping shall be measured up to floor two level(over all Rate)12 mm to 32 mm. tor etc.all complete. Ch-10 (504 c) | - | Qtl | 7,200 | - |
| 10 | Disposal of earth up to 3 km loading and unloading etc all comp | 1 | cum | 116.96 | ₹116.84 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.31 MB
ULBT2.pdf
Tender Documents • 2.66 MB
BOQ_2049455.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .