| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.2 LAccepted-AOC | L1 | Accepted-AOC stands lowest bidder | |
| 2 | L2₹6.4 L+₹13,674 (2.19%)Rejected-Finance | L2 | Rejected-Finance DOES NOT STAND LOWEST BIDDER | |
| 3 | L3₹6.5 L+₹24,390 (3.92%)Rejected-Finance | L3 | Rejected-Finance DOES NOT STAND LOWEST BIDDER |
Tender Value
₹6.1 L
EMD Value
₹12,000
Closing Date
13 Jul 2019, 6:00 pmClosed
SE O and MC III BTPS OBRA
Office of SE O and MC III BTPS OBRA
Breakdown Preventive maintenance Overhauling commissioning and Shifting of damaged repaired new E.S.P transformers and daily Routine Monitoring of HVR ESP Transformer and cleaning of ESP top floor area in 5x200MW Units B Thermal Power Station Obra
2019_RVUNL_347300_1
T-14/SE-III/EMD-II/BTPS/19-20
Open Tender
Electrical Works
Fixed-rate
365 days
UPRVUNL OBRA
AS PER PQC
3 documents required · 3 mandatory
₹1,180
UPRVUNLTD P and AD BTPS OBRA
₹12,000
21 Mar 2020
24 May 2019
16 Jul 2019
24 May 2019
13 Jul 2019
24 May 2019
24 May 2019 - 13 Jul 2019
Shifting of repaired / damaged / new ESP transformer from place of storage near electrical workshop area to ESP ground floor or from ESP ground floor to Electrical workshop (approx 600mts).
Lowering down the ESP transformer from ESP top ( 35 mtr) to ground floor of ESP area .
Lifting the transformer from ESP ground floor up to the ESP Top floor (35 mtr) and placing it at the required place / platform
Dismantling and removal of damaged/faulty transformer connected to ESP field along with negative link rod its bushing, bushing chamber and associated works.
Replacement and commissioning of New/repaired ESP transformer along with negative link rod, its bushing, bushing chamber and associated works and connecting it to field.
Preventive maintenance, up keeping and cleaning of ESP transformer support insulators, isolator insulators, negative bushing and their chambers.{1 Trans, 4 nos. support insulators, 3 nos. isolator insulator, 2 nos. negative bushing and respective chambers of 1 ESP field = 1 Job.
Up keeping and cleaning of E.S.P top floor area.
Over hauling of ESP transformer and fault finding.
Daily Routine monitoring of HVR ESP Transformer & Associated Equipments at ESP Top of 5x200MW, BTPS.
M/s Neha Conditioning & Refrizration Services
M/S ARVIND ERECTORS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .