| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 CrAccepted-AOC | ₹6.7 Cr | L1 | Accepted-AOC Accepted |
| 2 | L2₹7.1 Cr+₹32.2 L (4.77%)Rejected-AOC KANCHIPURAM | TAMIL NADU | 600069 | ₹7.1 Cr+₹32.2 L (4.77%) | L2 | Rejected-AOC Rejected |
Tender Value
₹9.2 Cr
EMD Value
₹9.2 L
Closing Date
17 Feb 2025, 3:00 pmClosed
Executive Officer
Bargur Town Panchayat
Construction of 2 MLD STP cum 10 KLD FSTP in Bargur town panchayat
2025_DTP_523939_1
267/2024/A1
Open Tender
Civil Works
Works
180 days
Bargur Town Panchayat
Please refer Tender Documents
3 documents required · 3 mandatory
₹0
₹9.2 L
Yes
Bargur Town Panchayat
22 Feb 2025
10 Feb 2025
17 Feb 2025
10 Feb 2025
17 Feb 2025
10 Feb 2025
11 Feb 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in Medium rock, and dense medium rock, not requiring blasting etc., as per SS 20 A. TNDSS NO: 23 & 24 VI (S2) VI,VII 9,10 with standard specifications. | 4,636 | CUM | 246.52 | ₹11,42,866.72 |
| 2 | Earthwork excavating and depositing on bank with initial lead of 10 metres and lift of 2 metres in all kinds of soil except medium rock, dense medium rock and hard rock requiring blasting including refilling the sides of foundation with excavated earth in layers of 15 cm thick, watering and consolidation and depositing the surplus earth with in the compound in places as shown by the departmental officers with initial lead and lift, cleaning, leveling the site etc., complete complying with standard specifications (Drain) | 660 | CUM | 184.89 | ₹1,22,027.4 |
| 3 | Removal of Excavated Excess Earth away from the site to 2K.M including loading and transportation charges etc, complete as per standard specification. For 1M3 | 3,653.9 | CUM | 103.2 | ₹3,77,082.48 |
| 4 | Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the earth as shown by the departmental officers in layers well rammed, watered and consolidated etc. complete complying with standard specification | 1,231 | CUM | 42.85 | ₹52,748.35 |
| 5 | Supplying and filling in foundation and basement with Crushed Stone dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 57 | CUM | 1,594.35 | ₹90,877.95 |
| 6 | Collection supply and filling of well gravel filling approved quarry including cost and Conveyance of all materials to site and all labour charges for filling etc., Complete. | 16 | CUM | 268.33 | ₹4,293.28 |
| 7 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 360 | CUM | 5,181.86 | ₹18,65,469.6 |
| 8 | Plain cement concrete 1:2:4 ( one cement, two sand, and four coarse aggregate ) using 20 mm ISS hard broken granite stone jelly for all plain cement concrete works excluding cost of shuttering, and centering including all labour charges and incidental charges for cost and conveyance of all materials to work site, mixing and laying concrete, finishing the surface nearly rough, compacting using vibrators, curing etc., complete complying with standard specification (Drain) | 108 | CUM | 7,537.32 | ₹8,14,030.56 |
| 9Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. | |||||
| 9.01 | For plane surfaces such as RCC floor slab, roof slab, beams, lintels, bed blocks, landing slab, waist slab, portico slabs and beams, etc. 0-1 M height | 3,226 | M2 | 494 | ₹15,93,644 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_623764.xls
BOQ • 0.40 MB
162974939.pdf
Tender Documents • 0.19 MB
162974943.html
Tender Documents • 0.06 MB
BID.pdf
Tender Documents • 1.03 MB
TENDER.pdf
Tender Documents • 0.17 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .