| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹36.6 LAccepted-AOC GRAM LOHATI SARIYA RUDAUTI AYODHYA | ₹36.6 L | L1 | Accepted-AOC Accepted-Finance |
| 2 | L2₹38.0 L+₹1.4 L (3.81%)Rejected-Finance NA | NA | NA | 121004 | ₹38.0 L+₹1.4 L (3.81%) | L2 | Rejected-Finance Not Lowest |
| 3 | L3₹38.3 L+₹1.7 L (4.60%)Rejected-Finance | ₹38.3 L+₹1.7 L (4.60%) | L3 | Rejected-Finance Not Lowest |
| 4 | L4₹39.3 L+₹2.7 L (7.24%)Rejected-Finance | ₹39.3 L+₹2.7 L (7.24%) | L4 | Rejected-Finance Not Lowest |
| 5 | L5₹40.2 L+₹3.6 L (9.84%)Rejected-Finance GRAM RUDRAPUR NAGWA KHAS DISTRICT DEORIA | ₹40.2 L+₹3.6 L (9.84%) | L5 | Rejected-Finance Not Lowest |
Tender Value
₹57 L
EMD Value
₹4.8 L
Closing Date
24 Mar 2026, 12:00 pmClosed
Superintending Engineer Deoria Circle PWD Deoria
Office of The Superintending Engineer Deoria Circle PWD Deoria
Construction of missing link of Vishunpur Baghi and Holi Ballia in Dist Deoria
2026_CEGKP_1126125_17
969/76yat-Deo Circle/26 Dated 28.02.2026
Open Tender
Civil Works
Percentage
180 days
Deoria
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,714
₹4.8 L
Deoria
27 Aug 2026
17 Mar 2026
24 Mar 2026
17 Mar 2026
24 Mar 2026
17 Mar 2026
23 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5(Excluding GST) | - | Cum | 85 | - |
| 2 | Granular Sub-base with Well Graded Material (Table 400-1)
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader / tractor mounted appropriate equipment on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per clause 401.(Excluding GST) | - | Cum | 4,040 | - |
| 3 | Cement Treated Base (4% Cement OPC) Providing,laying and spreading material on a prepared Sub Base, cement @ 4% by wet to the spread material manually mixing in place Rotavator and compacting with the road roller at OMC to achieve the desired unconfined Compressive strength and to form a Layer of Base.as per Technical specification clause 405.(Excluding GST) | - | Cum | 4,780 | - |
| 4 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous granular surface cleaned with mechanical broom.(Excluding GST) | - | Sqm | 18 | - |
| 5 | Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 80-100 kN static rollar capacity, finished to required level and grades to be fallowed by seal coat as per technical specification clause 508.(Excluding GST) | - | Sqm | 212 | - |
| 6 | Providing and laying seal coat by manual means with VG-10 Grade Bitumen sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510 (Including all taxes required and hire charges of road roller & including Cost of bitumen )(Excluding GST) | - | Sqm | 75 | - |
| 7 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.(Excluding GST) | - | Cum | 78 | - |
| 8 | 600MM Dia Hume pipe Culvert Excavation of Foundation in ordinary soil (Ioam clay or sand) including lift upto 1.50 meter and lead up 30meter and including filling, watering and ramming of excavated earth into trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer in charge up to a distance of 30 meters from the foundation trenches. (Excluding Royality) as per S.I. No. 251.(Excluding GST) | - | Cum | 65 | - |
| 9 | Concrete with 4cm (1.5"). Gauge brick ballast, fine sand of 1.25 fineness modulous and cement in proportion of 1:4:8 in foundation and under floor, including supply of all materials, labour and T&P etc. required for proper completion of the work, As per S.I.No.-275.(Excluding GST) | 1 | Cum | 8,700 | ₹8,691.3 |
| 10 | Laying (40mmSSB) Bedding on well compacted sand moorum or approved granular material as per clause 1105(ii) | - | Cum | 3,735 | - |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 24.62 MB
Tendernotice_2.pdf
PDF • 7.62 MB
Tendernotice_3.pdf
PDF • 0.69 MB
BOQ_2100423.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .