EE Akola MIDC Div Akola
EE Akola MIDC Div Akola
Chikhali GC Indl Area M and R to PWSS Providing Strengthening and final asphaltic treatment to internal road at WTP Premises and other required misc work
2026_MIDC_1325435_1
TN NO 05 Chikhali GC Indl Area M and R to PWSS Providing Strengthening and final asphaltic
Open Tender
Civil Works
Percentage
90 days
EE Akola MIDC Div Akola
Please refer Tender documents.
8 documents required · 8 mandatory
₹7,080
₹15,900
19 Aug 2026
6 Aug 2026
18 Aug 2026
6 Aug 2026
17 Aug 2026
12 Aug 2026
10 Aug 2026 - 11 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Name Of Sub Estimate : Providing final asphaltic tretamnet to internal road along with road side plantation. | |||||
| 1.01 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth upto 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stackingof serviceable material to be used or auctioned upto a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. | 1,139 | Square Metre | 12 | ₹13,668 |
| 1.02 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 1000 metres, stacking serviceable and unserviceable materials separately etc. complete. | 104 | Cubic Metre | 430 | ₹44,720 |
| 1.03 | Conveying materials obtained from road cutting including all lifts, laying in layers of 20cm to 30cm. breaking clods, dressing to the required lines, curves, grades and section, watering and compacting to not less than 97%of standard Proctor density for a lead of over 50m. to 300m. inclusive from the site of excavation to the siteof deposition as directed. | 84 | Cubic Metre | 195 | ₹16,380 |
| 1.04 | Wet Mix Macadam--Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density. Laying By Grader/Paver. | 120 | Cum | 2,612 | ₹3,13,440 |
| 1.05 | Prime coat - Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including cleaning of road surface and spraying, primer at the rate of 0.60 kg/sqm using mechanical means. | 517.5 | Sqm | 35.35 | ₹18,293.63 |
| 1.06 | DENSE BITUMINOUS MACADAM:--Providing and laying dense bituminous macadam using crushed aggregate of grading 1, premixed with bituminous binder Bitumen of specified grade,@ 4.50 % by weight of total mix and filler, transported at site with VTS, laid over a previously prepared surface , finished to the required grade ,level, alignment,and rolling to achieve the desired density for 76/100 mm compacted thickness with drum mix type hot mix plant with SCADA having complying essential features of Hot mix plant as per IRC-27-2009 specified conditions and attachments such as electronic load sensor based belt conveyers, automatic synchronization of bitumen and aggregate fedder,built in dust controller system and PLC for Drum Mix plant ,Sensor paver, and Vibratory roller including prime/Tack coat etc. complete --Bitumen VG-30 grade with stone dust filler (VG-30 bulk bitumen rates are considered to arrive at rates). (Rates excluding GST) | 28 | Cum | 10,324 | ₹2,89,072 |
| 1.07 | BITUMINOUS CONCRETE:--Providing and laying bituminous concrete using crushed aggregate of grading 1, premixed with bituminous binder @5.40% by weight of total mix and filler, transported at site with VTS, laid over a previously prepared surface, finished to the required grade ,level, alignment, and rolling to achieve the desired density for 50mm compacted thickness with drum mix plant with SCADA, Sensor paver and Vibratory roller including prime/Tack coat etc. complete --Bitumen of specified grade with stone dust filler. (VG-30 bulk bitumen rates are considered to arrive at rates) (Rates excluding GST) | 13 | Cum | 12,112 | ₹1,57,456 |
| 1.08 | Earthwork in embankment with approved material having field soak CBR not less than 8 and laboratory soak CBR not less than 12 obtained by the Contractor from his borrow areas including all lifts and leads including laying in layers of 20cm to 30cm for power roller and 45cm to 60cm for vibratory compactor, breaking clods, and dressing to the required lines, curves and section including payment of royalty charges to the Govt. of Maharashtra. (Rates excluding GST) | 116 | Cum | 1,225.35 | ₹1,42,140.6 |
| 1.09 | Plantation of Mayurpankhi/Thuja foliage shrub having bag size of 13" x 13" and height is 1.00 mtr including excavation pit size 0.60 x 0.60 x 0.60m in earth, soil of all types, soft murum, including removing the excavated & unwanted material up to a required distance of 50 mtrs. , supplying of fresh garden soil and well decomposed farm yard manure. Also include mixing and filling of fresh garden soil and manure with watering. Maintenance of newly planted shrub for first 30 days. | 110 | No. | 763 | ₹83,930 |
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.31 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.41 MB
CHIKHALIASPHALTING.pdf
Tender Documents • 0.65 MB
BOQ_2270064.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .