| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.7 LAccepted-AOC | 1 | Accepted-AOC quoted lowest bid | |
| 2 | 2₹2.0 L+₹29,540 (17.6%)Rejected-Finance | 2 | Rejected-Finance Higher bid | |
| 3 | 3₹2.0 L+₹32,940 (19.7%)Rejected-Finance | 3 | Rejected-Finance Higher bid |
Tender Value
₹2.0 L
Closing Date
23 Aug 2024, 12:00 pmClosed
EXECUTIVE ENGINEER
E 400 KV S/S DIVISION GREATER NOIDA
REPLACEMENT REPLACEMENT FEEDERS TRANSFORMERS OTHER ISOLATORS WORK AT 400 KV S/S SUBSTATION GREATER NOIDA
2024_UPTCL_946825_1
T-1/2024-25EE/400KV/GN
Open Tender
Miscellaneous Works
Lump-sum
90 days
400 KV S/S SUBSTATION GREATER NOIDA
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
EXECUTIVE ENGINEER
Exempted
28 Aug 2024
17 Aug 2024
23 Aug 2024
17 Aug 2024
23 Aug 2024
17 Aug 2024
Defective 220kV single tarantula conductor jack bus will be dismantled of Y & 13 Phase of 220 kV Noida Sector 20 Ckt 2 and Y phase of 220 kV RC Green Ckt 2 bays (Approx. Length 35 meter of 01 section respectively).
Defective 220kV single tarantula conductor jack bus will be dismantled of Y & 13 Phase of 220 kV Noida Sector 20 Ckt 2 and Y phase of 220 kV RC Green Ckt 2 bays (Approx. Length 35 meter of 01 section respectively).Defective 220kV single tarantula conductor jack bus will be dismantled of Y & 13 Phase of 220 kV Noida Sector 20 Ckt 2 and Y phase of 220 kV RC Green Ckt 2 bays (Approx. Length 35 meter of 01 section respectively).
Defective 220kV twin moose conductor Jack Bus will be dismantled of R phase of 220 kV side of 500MVA ICT 5th (Approx. Length 20 meter of 01 section respectively).
Stringing of twin moose conductor Jack bus will be done R phase will be done R phase of 220 kV side of 500MVA ICT S (Approx. Length 35 meter of 01 section respectively).
Stringing of single moose conductor Jack bus will be done of Y & B Phase of 220 kV Noida Sector 20 Ckt 2 and Y phase of 220 kV R C Green Ckt 2nd bays (Approx. Length 35 meter of 01 section respectively)
Stringing of twin moose conductor Jack bus will be done R phase will be done R phase of 220 kV side of 500MVA ICT S (Approx. Length 35 meter of 01 section respectively).
Stringing of twin moose conductor Jack bus will be done R phase will be done R phase of 220 kV side of 500MVA ICT S (Approx. Length 35 meter of 01 section respectively). replaced in MOM Box by New (if required) of mentioned Isolators. For Overhauling, alignment work & proper lubrication will be done of 220 kV bus & line isolators of various bays. Final testing of isolator for proper operation manually including setting right of aux. contacts in Mom box. Status of mentioned isolators will be checked in Bus bar relay for healthy operation.
Opening of damage jumper/dropper (220 kV) and Jumpering of single/twin moose conductor will be done of 220 kV Feeders & Transformers bay at 400 kV S/S Greater Noida.
Shifting of new ACSR Moose Conductor from store to switch yard and dismantled materials from site to store. (distance approx. 300Meter).
Opening of damage jumper/dropper (220 kV) and Jumpering of single/twin moose conductor will be done of 220 kV Feeders & Transformers bay at 400 kV S/S Greater Noida.
Defective& damaged NO & NC contact will be replaced by new (if required) of 220kV bus & line isolators of varioud 220 kV line & Transformer Bays. Defective parts will be replaced in MOM Box by New (if required) of mentioned Isolators. For Overhauling, alignment work & proper lubrication will be done of 220 kV bus & line isolators of various bays. Final testing of isolator for proper operation manually including setting right of aux. contacts in Mom box. Status of mentioned isolators will be checked in Bus bar relay for healthy operation.
Defective& damaged NO & NC contact will be replaced by new (if required) of 220kV bus & line isolators of varioud 220 kV line & Transformer Bays. Defective parts will be replaced in MOM Box by New (if required) of mentioned Isolators. For Overhauling, alignment work & proper lubrication will be done of 220 kV bus & line isolators of various bays. Final testing of isolator for proper operation manually including setting right of aux. contacts in Mom box. Status of mentioned isolators will be checked in Bus bar relay for healthy operation.
Dismantling of indoor unit of 03 nos. air conditioner for cleaning, checking and repairing
132 KV S/S Taj (03x5.5)
132 KV S/S Bhimanagri (02x5.5)
Cleaning chechking of indoor of 05 nos. air conditioner
132 KV S/S Taj (03x5.5)
132 KV S/S Bhimnagri (02x5.5)
Repairing of leakage of indoor unit 05 nos. air conditioner
132 KV S/S Taj (03x5.5)
132 KV S/S Bhimnagri (02x5.5)
Cleaning of inside surface of air supply duct of air conditioner system spread in fall ceiling of control room building using high power vaccum air compressor, robotic camera, air hammer, special nozzles and air sweep with all other accessories required for inspection of ducts before and after cleaning
132 KV S/S Taj (03x5.5)
132 KV S/S Bhimnagri (02x5.5)
Repair and reconnecting, overhauling of fan motors of above unit
132 KV S/S Taj (03x5.5)
132 KV S/S Bhimnagri (02x5.5)
Meena Elect & Engg. Works
Perfect Power Transformer Associates
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .