| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹34.9 LAccepted-AOC VILL P O BHADUL DIST BANKURA PIN 722155 | BHADUL | BANKURA | WEST BENGAL | 722155 | ₹34.9 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹37.7 LRejected-Finance | ₹37.7 L | L2 | Rejected-Finance Reject Due to Higher
Rate |
| 3 | L3₹42.9 LRejected-Finance 1 NO MOHISHILA COLONY DAKSHIN PARA ASANSOL 3 PASCHIM BARDHAMAN 713303 | PASCHIM BARDHAMAN | WEST BENGAL | 713303 | ₹42.9 L | L3 | Rejected-Finance Reject Due to Higher
Rate |
Tender Value
₹47.1 L
EMD Value
₹94,206
Closing Date
8 Apr 2026, 4:00 pmClosed
EE_Asansol Division_SS_PWDte
Office of the Executive Engineer, Asansol Division, Social Sector, P. W. Dte., Court Compound, S.B. Gorai Road, Asansol-4
Repair and Renovation of Auditorium Hall of Kanyapur Model Labour Welfare Centre Paschim Bardhaman for the Financial year 2025 26
2026_WBPWD_1021776_1
WBPWD/SS/EE/ASND/NIT_05/25-26
Open Tender
CIVIL WORKS
180 days
Kanyapur
Please refer Tender documents.
4 documents required · 4 mandatory
₹94,206
Yes
30 Jun 2026
12 Mar 2026
13 Apr 2026
12 Mar 2026
8 Apr 2026
19 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.
In ground floor | - | CuM | 447 | - |
| - | Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m
In ground floor including roof.
(a) upto 150 mm. thick | - | CuM | 939 | - |
| - | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars
In ground floor including roof. | 1 | CuM | 1,956 | ₹1,954.04 |
| - | (A) Stitching crack in brick wall by carefully cutting out face brick 125 mm. deep into the wall, cleaning the gap and filling up the same with precast cement concrete block carefully set in cement mortar (1:3) including mending good damages and finishing the surface to match with adjacent areas complete as per direction.
(ii) With reinforced cement concrete blocks (1:1½:3) with stone chips and nominal reinforcement.
(a) Block size 250 x 125 x 75mm. | - | Each | 102.94 | - |
| 5 | Taking out old damaged tarfelt from the roof, parapet etc. preparing the roof surfaces by removing all spoils, blisters, moss etc. from the working site and disposal of the same beyond the compound and cleaning the site in all respect as per direction of Engineer-in-Charge. | - | SqM | 12 | - |
| 6 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. | - | SqM | 19 | - |
| 7 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge | - | CuM | 166 | - |
| 8 | Labour for taking out door and window frame including shutter for repair or replacement of different parts of the frame & refixing the same including mending good all damaes complete. (Concrete and brick work for mending damage will be paid separately)
(a) Upto area 2.5 Sq.m | - | SqM | 119 | - |
| 9 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.
(a) Depth of excavation not exceeding 1,500 mm. | - | % CuM | 11,927 | - |
| 10 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)
(a) With earth obtained from excavation of foundation. | - | % CuM | 7,754 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.72 MB
BOQ_2511381.xls
BOQ • 0.43 MB
2911ii.pdf
Tender Documents • 0.50 MB
Download all tender documents and submit your bid