Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.6 LAccepted-AOC MIRZAPUR MIRZAPUR | MIRZAPUR | MIRZAPUR | UTTAR PRADESH | 231001 | L1 | Accepted-AOC L1 | |
| 2 | L2₹4.8 L+₹21,898.61 (4.76%)Rejected-Finance MIRZAPUR | UTTAR PRADESH | 231001 | L2 | Rejected-Finance L2 |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
29 Dec 2023, 9:00 amClosed
Executive Engineer, MLCD Mirzapur
Executive Engineer, Minor Lift Canal Division, Mirzapur
Reconstruction of Staff Room at Dubeypur Pump Canal
2023_UPIDM_868946_2
07/EEMLCDMZP/2023-24/LOT 04
Open Tender
Civil Works
Item Wise
45 days
Tahsil Sadar, Blo-City, Dubeypur
Please refer Tender documents.
2 documents required · 2 mandatory
₹680
₹10,000
29 Jan 2024
23 Dec 2023
29 Dec 2023
23 Dec 2023
29 Dec 2023
23 Dec 2023
Amount
Dismantling R.B. work including stacking of dismantled materials as directed by Engineer-in-charge within a distance of 60 M.
Dismantling brick work in cement mortar including stacking of materials as directed by Engineer-in-charge within a distance of 60 M.
Earth Work in excavation of foundation with all type of soil including all labour cost T&P etc. required for proper completion of the work.
Preparation of sub grade for appron including all labour cost T&P etc. required for proper completion of the work.
Supply and laying of local sand in foundation including cost of all material, labour and T&P etc. required for proper completion of work.
P.C.C. 1:3:6 with Cement , Course sand and Stone ballast Size 25 to 50 mm including all material, labour cost T&P etc. required for proper completion of the work.
Centering and Shuttering of RCC work including cost of all material, labour T&P etc. Required for proper completion of work.
Cutting ,bending, binding and placing of reinforcement in position including cost of all labour, material and T & P ,binding wire for proper completion of work.
Providing and laying of R.C.C. 1:1.5:3 with Cement , Course sand and dalla grit Size 12.5 to 20 mm including all material, labour cost T&P etc. required for proper completion of the work.
Class 150 (Ist class) brick masonry work with 1:4 CM. including all material, labour cost T&P etc. required for proper completion of the work. (70% New Brick)
Cement Plaster with 1:3 CM on birck works including all material, labour cost T&P etc. required for proper completion of the work.
Finishing wall with white coloured two coat of Birla/ jk wall Putty including cost of all material, T&P etc. required for proper completion of the work.
Finishing wall with Water proofing cement paint including cost of all material, T&P etc. required for proper completion of the work.
Providing and Fitting Steel Door including cost of all material, labour and T&P etc.(Size2.10*1.20)
Providing and Fitting Steel Window including cost of all material, labour and T&P etc. (Size1.00*0.90)
Painting of Steel Door, Window and including cost of all material, labour and T&P etc.
Brick on edge with M-150 brick (1:4) laid in cement mortar consisting of one part of cement & four part of coarse sand and pointed with cement mortar 1:2 over and 8 cm thick base concrete excluding supply of all materials but including labour T&P etc. required for proper completion of work.
Earth work Filling with all type of soil including Proper dressing & manual compaction and all lead beyond 1.0 Km. and upto 2.0 Km. Distance, labour T&P etc.
CHANDRIKA PRASAD YADAV
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .