| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.1 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹16.2 L+₹9,593.56 (0.60%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹16.5 L+₹44,617.08 (2.77%)Rejected-AOC | L3 | Rejected-AOC L3 |
Tender Value
₹16.8 L
EMD Value
₹17,000
Closing Date
8 Jan 2024, 3:00 pmClosed
Block Development Officer (VP), Eriyur Block
Block Development Officer (VP), Eriyur Block
CONSTRUCTION OF 30000 LITERS OHT TANK 12.00M STAGGING HEIGHT WITH PIPELINE AT M.THANDA H/O SUNJALNATHAM.
2024_RDTN_405317_1
RocNo2801/2023/E2 Dated.20.12.2023 JJM(MVS) P03
Open Tender
Civil Works
Item Wise
180 days
Block Development Officer (VP), Eriyur Block
Can be seen in the tender documents
2 documents required · 2 mandatory
₹0
₹17,000
Yes
Block Development Officer (VP), Eriyur Block
3 Apr 2024
3 Jan 2024
8 Jan 2024
3 Jan 2024
8 Jan 2024
3 Jan 2024
3 Jan 2024
Amount
CONSTRUCTION OF 30000 LITERS OHT TANK 12.00M STAGGING HEIGHT WITH PIPELINE AT M.THANDA H/O SUNJALNATHAM.
Earthwork excavation for Foundation in all soils and sub soil as per SS20B for Foundation etc.complete. SS 20B
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm Thick well ramed, watered and compacted complete complying with standard specification.
For foundation
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing laying and curing etc complete
For Columns Base
Reinforced cement concrete 1:1. 5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete
Items 1.50m to 4.50m below GL
Items 0 to 1.50m below GL
Items 0.0m to 4.50m above GL
Items Above 4.51m to 7.32m
Items Above GL 7.33m to 10.98m
Items 10.98m to 14.64m above GL
14.64m 18.30m above GL
Supplying and erecting shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical
For Plan Surface
Below GL
From 0.00 to 3.30m
From 5.30m to 6.30m
From 8.30m to 9.30m above G.L
From 11.30m to 12.30m
Curved Surface
Upto 0-3.30m height
From 5.31 - 6.30m Height
Square column
Below GL
8.31 to 9.30m ht
10.31 to 11.30m ht
Painting two coats using ready mixed plastic emulsion paint inicuding priming coat including cost and conveyance of all materials to site and all labour charges etc comoplete
Supplying, fabricating and placing in position of MS steel or ribbed for steel for all Reinfor cement concrete works as per the design given including the cost of steel and binding wire in all floors etc., complete complying with stanard specification.
Supplying, Fabrication, delivery and placing in position MS steel ladder wide 0.45m made out of 50x50x6mm MS angle for sides and steps in 16mm MS plain rods fixed at 30cm c/c welded and jointed etc., Complete complying with stanard specification.
Supplying and fixing of RCC inner access ladder in RCC 1:1. 1/2:3mix etc.,Complete complying with stanard specification
Providing PVC ventilating arrangements mosquito proof nylon net with 110 mm PVC cowl and as directed by Departmental officers
Providing cut stone slab in CM 1:3 mix and as directed by Departmental officers
Providing manhole cover of size 0.60 X 0.60M in RCC 1:1. 1/2:3mix with suitable reinforcement and 5O x 5O x 6mm MS angle fixed along edges and as directed by Departmental officers
Provision for Pipe connection arrangements
65m dia GI pipes for inlet connection & outlet
65mm dia GI pipe for over flow and rain water harvesting pipes
50mm dia GI pipes for scour pipes
65mm dia GM gate valve
50mm dia GM gate valve
50 mm dia Flange set
65mm dia GI Tee
65mm dia GI coupling
65mm dia GI flange set
65mm dia GI Elbow
50mm dia GI Elbow
Refilling in Basement with excavated Earth in layers of not more than 15 cm. Thick well rammed, watered and consolidated complying with standard specifications etc., comlete.
Provison Plat form Arrangements (Sub Estimate)
Cement concrete 1:4:8 (one cement four sand and eight jelly) using 40.m.m. H.B.G.Jelly for foundation including watering where ever necessary and laid in iayers not more than 15.c.m. thick compacting etc. complete complying with standard specification
Brik work in CM 1:5 mix using good country bricks including cost and conveyance of all materials to site and all labour charge etc., complete
Plastering with cement 1:5 - 12 mm thic including cost and conveyance of all materials to site and all labour charges etc., complete.
Provision for soak pit arrangements
Provison for Pipe line (Sub Estimate)
Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2mts in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small size boulders and hard gravely soil as per SS 20B
Supply of HDPE Pipes including cost and conveyance of all materials to site and all labour charges etc., completed.
Labour charges for laying and joining HDPE Pipes including all labour charges for laying pipes in proper alingment and gradient including cost of solvent cement etc., complete.
Refilling with excavated earth after laying of pipes including all labour charges Solvent cement etc., complete.
Providing Name board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
S.Senthilkumar
OLPANDCO
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .