| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.6 LAccepted-AOC | ₹16.6 L | L1 | Accepted-AOC Less Quoted |
| 2 | L2₹16.8 L+₹21,604.27 (1.30%)Rejected-AOC | ₹16.8 L+₹21,604.27 (1.30%) | L2 | Rejected-AOC Above Quoted |
| Sl No | Description | Qty | Unit | A.HARI SATHISH KUMAR L2 | S.KOTHANDABANI L1 |
|---|---|---|---|---|---|
| 1.00Name of Work: Construction of 30000 Lit OHT at Gundukulam in Vippedu Panchayat in Kancheepuram Panchayat Union Under JJM Savings Fund / 2020-21 Estimate Amount : 16.75 Lakhs | |||||
| 2.00 | Earth work excavation & depositing on bank with an initial lead of 10 metre & initial lift of 2 metre in Hard shift clay, stiff block cotton, hard red earth shales, murrum, gravel, stoney earth, and earth mixed with small size boulders and hard gravelly soil (SS 20B) for foundation including shoring, strutting, baling out water providing danger light wherever necessary depositing the surplus earth on bank and other incedential charges etc., complete and as directed by departmental officers - First depth of 2m From 0 to 2 m below GL | 58.55 | cum | 234 ₹13,700.7 | 224 ₹13,115.2 Lowest |
| 3.00 | In hard stiff clay, stiff black cotton soil, hard red earth, sales, murrams, gravel, stoney earth, earth mixed with small sized boulders and hard gravelly soil S.S.20B - Second depth of 2m From 2m to 4 m below GL | 13.12 | cum | 244.65 ₹3,209.81 | 234.65 ₹3,078.61 Lowest |
| 4.00 | Sand filling for foundation with clear river sand including cost of sand, watering ,ramming and consolidation etc complete as directed by TWAD Bord officers | 8.75 | cum | 1,528.58 ₹13,375.08 | 1,518.58 ₹13,287.58 Lowest |
| 5.00 | Plain Cement Concrete 1:4:8 (one cement, four sand and eight hard granite broken stone of 40mm size ISS gauge) for foundation and footing including mixing, placing, ramming ,finishing curing etc. complete in accordance with standard specification and as directed by the departmental Officers. | 4.37 | cum | 4,837 ₹21,137.69 | 4,827 ₹21,093.99 Lowest |
| 6.00Reinforced Cement Concrete Mix M30 grade using 10mm & 20mm Hard blue granite Broken stone (machine crushed) excluding the cost of RTS rods for reinforcement and centering, strutting, shuttering but including cost of all materials mixing, laying, Vibrating the concrete with mechanical vibrators, ramming, consolidating, finishing and curing etc., Complete and as directed by the departmental Officers. | |||||
| 7.00 | Below 1.5m from GL | 13.52 | cum | 8,494 ₹1,14,838.88 | 8,464 ₹1,14,433.28 Lowest |
| 8.00 | 0m to 1.50m below GL | 1.75 | cum | 8,491 ₹14,859.25 | 8,461 ₹14,806.75 Lowest |
| 9.00 | 0m to 4.50m above GL | 2.83 | cum | 8,613 ₹24,374.79 | 8,583 ₹24,289.89 Lowest |
| 10.00 | 4.50 m to 7.32 m above GL | 2.23 | cum | 8,850 ₹19,735.5 | 8,820 ₹19,668.6 Lowest |
Tender Value
₹16.8 L
EMD Value
₹16,750
Closing Date
22 Jan 2024, 3:00 pmClosed
The Block Development Officer(VP) Kancheepuram
The Block Development Office Kancheepuram
Construction of 30000 Lit OHT at Gundukulam in Vippedu Panchayat Kancheepuram Panchayat Union Est Amt.Rs.16.75 Lakhs Under JJM Savings Fund / 2020-21
2024_RDTN_408097_1
RC No.6361/2022/A14 Dt.08.12.2023
Open Tender
Civil Works - Water Works
Lump-sum
180 days
Kancheepuram
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹16,750
3 Dec 2025
10 Jan 2024
22 Jan 2024
10 Jan 2024
22 Jan 2024
10 Jan 2024
Amount
Earth work excavation & depositing on bank with an initial lead of 10 metre & initial lift of 2 metre in Hard shift clay, stiff block cotton, hard red earth shales, murrum, gravel, stoney earth, and earth mixed with small size boulders and hard gravelly soil (SS 20B) for foundation including shoring, strutting, baling out water providing danger light wherever necessary depositing the surplus earth on bank and other incedential charges etc., complete and as directed by departmental officers - First depth of 2m From 0 to 2 m below GL
In hard stiff clay, stiff black cotton soil, hard red earth, sales, murrams, gravel, stoney earth, earth mixed with small sized boulders and hard gravelly soil S.S.20B - Second depth of 2m From 2m to 4 m below GL
Sand filling for foundation with clear river sand including cost of sand, watering ,ramming and consolidation etc complete as directed by TWAD Bord officers
Plain Cement Concrete 1:4:8 (one cement, four sand and eight hard granite broken stone of 40mm size ISS gauge) for foundation and footing including mixing, placing, ramming ,finishing curing etc. complete in accordance with standard specification and as directed by the departmental Officers.
Reinforced Cement Concrete Mix M30 grade using 10mm & 20mm Hard blue granite Broken stone (machine crushed) excluding the cost of RTS rods for reinforcement and centering, strutting, shuttering but including cost of all materials mixing, laying, Vibrating the concrete with mechanical vibrators, ramming, consolidating, finishing and curing etc., Complete and as directed by the departmental Officers.
Below 1.5m from GL
0m to 1.50m below GL
0m to 4.50m above GL
4.50 m to 7.32 m above GL
7.32 m to 10.98 m above GL
10.98 m to 14.64 m above GL
14.64 m to 18.30 m above GL
Supply and erection of steel centering, shuttering for soffits and sides including necessary supports and strutting for all RCC works using MS sheets of suitable size of BG10 stiffened with MS angle of size 25 X 25 X 3 mm for boarding laid over I type MS Truss of size 25 X 25 X 3mm about 90cm c/c and supported by 40mm GI pipes (Medium) spaced at 75cm c/c etc complete and as directed by the departmental Officers.
Plain Surface
Below GL
From GL to 3.30m
From 5.30m to 6.30m above GL
From 8.30m to 9.30m above GL
From 11.30m to 12.30m
Square Column:
Square Column Below GL and upto 3.30m above GL
3.31m to 4.30m ht
4.31m to 5.30m ht
5.31m to 6.30m ht
6.31m to 7.30m ht
7.31m to 8.30m ht
8.31m to 9.30m ht
9.31m to 10.30m ht
10.31m to 11.30m ht
11.31m to 12.30m ht
Curved Surface - upto 3.30m ht.
Supplying, cutting, bending, tying, fabricating and placing in position of steel rods for all RCC works including cost of steel and binding wire etc.( The steel should conform to the relevant ISspecification and supplied with test certificate Fe. 415 grade as per IS specification No.1786/1985 and as amended from time to time) delivery at site of work including loading, freight, unloading, stacking, transit insurance charges, taxes etc. complete.and as directed by the departmental officers.
Exterier Emulsion painting two coats with approved emulsion paint including cost and conveyance of all materials to and all labour charges etc.complete for 10 sqm
Providing and fixing RCC inner access ladder inRCC 1 : 11 / 2.\:3 (one cemnt, one and half sand and three agggregate) using 20 mm HGB stone for OHT including cost of reinforcement placing grill in position, centring, shuttering charges, mixing concrete curing etc., to required height and clear width of 45cm consisting of 2 nos. of vertical post of 10 cm x 15 cm and step slab of 25 mm x 25 mm etc., complete and as directed by the departmental officers
Providing 110mm PVC vent cowl arrangements mosquito proof nylon net and as directed by departmental officers
Supply and fixing of cut stone of size 0.30m x 0.30m x 0.15m in CM 1;3(one cement and three sand) below inlet pipe for Service Reservoir as directed by departmental Officers.
Providing manhole cover of size 0.60 x 0.60M in RCC 1:1.5:3 with suitable reinforcement and 50x50x6mm MS angle fixed along edges and as directed by departmental officers
Writing Name of the Work and Scheme details on the side wall of the OHT
Pipe connection arrangements for inlet,outlet,scour and overflow etc. including cost of pipes,specials,valve,labour charges for lifting, aligning, cutting, threading ,fixing and painting of GI pipes with two coats of approved quality enamal paint etc. complete as detailed below.
65mm GI pipes for inlet connection
65mm GI pipes for over flow & rain water harvesting pipe
50mm GI pipes for scour pipe
65mm GI pipe for delivery pipe
90mm PVC Threaded coupler
63mm PVC Threaded coupler
65mm dia GI Tee
65mm dia GI bend 90
65mm dia GI bend (short)
65mm GI coupler
65mm GI union
65mm GI Elbow
50mm GI union
50mm GI Elbow
65x50mm GI reducer
65mm GM gate valve
50mm GM gate valve
63mm PVC Bend
65 GI Flange Set
50 GI Flange Set
63 mm PVC 4Ksc Pipe
Refilling the Foundation with excaved earth including consolidation
Labour charges for GI pipe connection to the OHT, for inlet, outlet, overflow and scour arrangements including cutting and threading, earth work excavation & refilling.
Providing Hand rails over the Roof slab by using 32 mm GI Pipe with 40mm x 6mm MS Flat and fixied with 12mm dia Fastner Bolt 75mm long and as directed by departmental officers
Providing Hand rails over the Standing Platform by using 32 mm GI Pipe with 40mm x 6mm MS Flat and fixied with 12mm dia Fastner Bolt 75mm long and as directed by departmental officers
Supply,delivery, laying and jointing of 90mm OD PVC 4Ksc pipe inlcuding earth work excavation in all strata soil, refilling and hydraulic testing, adopting standard specification..
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
A.HARI SATHISH KUMAR
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .