Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 CrAccepted-AOC | ₹1.9 Cr | L1 | Accepted-AOC Being Lowest |
| 2 | L2₹2.0 Cr+₹9.0 L (4.71%)Rejected-Finance | ₹2.0 Cr+₹9.0 L (4.71%) | L2 | Rejected-Finance Other than L1 |
| 3 | L3₹2.0 Cr+₹13.0 L (6.80%)Rejected-Finance OPP BSF GATE NO 3 AZARA GUWAHATI 17 ASSAM | ₹2.0 Cr+₹13.0 L (6.80%) | L3 | Rejected-Finance Other than L1 |
| 4 | Rejected-Technical | - | - | Rejected-Technical Bidder does NOT fulfils NIT criteria, the bidder was asked to submit shortfall docs by 29 Jun 2026. Till date no reply recd yet. |
| Sl No | Description | Qty | Unit | M/s Dhani Enterprise L3 | M/S SUNRISE ENTERPRISE L1 | M/S DEBAJIT BORTHAKUR L2 |
|---|---|---|---|---|---|---|
| 0.00NOTE:- (Applicable for all parts/items/):- The bidders/contractors are advised to read tender documents, all drawings & all corrigendum/ amendments and General conditions of contracts before entry/quoting the rates. | ||||||
| 1.00SCHEDULE 'A' PART-I, LUMPSUMP PRICE TO BE QUOTED BY CONTRACTOR | ||||||
| 1.10 | Construction of Single Officer Living Accn for Capt (06 Nos DUs, G+2) with permanent specifications, RCC framed construction, complete all as specified and as shown on drawings. | 1 | Lump-sum | 1,14,00,000 ₹1,14,00,000 | 1,07,00,000 ₹1,07,00,000 Lowest | 1,11,00,000 ₹1,11,00,000 |
| 1.20 | Construction of Servant Quarter for Single Officer Living Accn for Capt 03 Nos (Single Storey) with permanent specification, RCC framed construction, complete all as specified and as shown on drawings. | 1 | Lump-sum | 15,36,372 ₹15,36,372 | 10,00,000 ₹10,00,000 Lowest | 10,00,000 ₹10,00,000 Lowest |
| 1.30 | Construction of Garage for Single Officer Living Accn for Capt 06 Nos (Single Storey) with permanent specification, RCC framed construction, complete all as specified and shown on drawings. | 1 | Lump-sum | 14,01,542 ₹14,01,542 | 22,00,000 ₹22,00,000 | 10,00,000 ₹10,00,000 Lowest |
| 2.00 | Lumpsum price worked out by the tenderer for SITE CLEARANCE, SITE DEVELOPMENTS & EARTH WORKS as listed in Schedule ‘A’ Part-II | 1 | Lump-sum | 1,69,418.7 ₹1,69,418.7 Lowest | 2,00,000 ₹2,00,000 | 3,00,960.52 ₹3,00,960.52 |
| 3.00 | Lumpsum price worked out by the tenderer for INTERNAL ELECTRIFICATION as listed in Schedule ‘A’ Part-III | 1 | Lump-sum | 6,59,593 ₹6,59,593 Lowest | 6,90,000 ₹6,90,000 | 6,59,937.39 ₹6,59,937.39 |
| 4.00 | Lumpsum price worked out by the tenderer for INTERNAL WATER SUPPLY as listed in Schedule ‘A’ Part-IV | 1 | Lump-sum | 1,72,618 ₹1,72,618 | 1,20,000 ₹1,20,000 Lowest | 1,29,222.78 ₹1,29,222.78 |
| 5.00 | Lumpsum price worked out by the tenderer for ROAD/PATH/CULVERT as listed in Schedule ‘A’ Part-V | 1 | Lump-sum | 10,54,064 ₹10,54,064 | 8,90,000 ₹8,90,000 Lowest | 12,00,000 ₹12,00,000 |
| 6.00 | Lumpsum price worked out by the tenderer for EXTERNAL WATER SUPPLY as listed in Schedule ‘A’ Part-VI | 1 | Lump-sum | 2,38,270 ₹2,38,270 | 1,10,000 ₹1,10,000 Lowest | 1,36,859.76 ₹1,36,859.76 |
Tender Value
₹2.1 Cr
EMD Value
₹2.9 L
Closing Date
27 Apr 2026, 6:00 pmClosed
CE SHILLONG ZONE
HQ CE SHILLONG ZONE, SE FALLS SHILLONG MEGHALAYA
PROVN OF SINGLE LIVING ACCN FOR OFFRS AT NARANGI MIL STN UNDER GE NARANGI
2026_MES_757267_1
89868/NAR/E8
Open Tender
Civil Works
Lump-sum
600 days
GE NARANGI
As per tender documents and NIT
2 documents required · 2 mandatory
₹2,000
Yes
GE NARANGI
₹2.9 L
Yes
14 Aug 2026
23 Mar 2026
29 Apr 2026
23 Mar 2026
27 Apr 2026
20 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | SCHEDULE 'A' PART-I, LUMPSUMP PRICE TO BE QUOTED BY CONTRACTOR | - | - | - | - |
| - | Construction of Single Officer Living Accn for Capt (06 Nos DUs, G+2) with permanent specifications, RCC framed construction, complete all as specified and as shown on drawings. | - | Lump-sum | - | - |
| - | Construction of Servant Quarter for Single Officer Living Accn for Capt 06 Nos (Single Storey) with permanent specification, RCC framed construction, complete all as specified and as shown on drawings. | - | Lump-sum | - | - |
| - | Construction of Garage for Single Officer Living Accn for Capt 06 Nos (Single Storey) with permanent specification, RCC framed construction, complete all as specified and shown on drawings. | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for SITE CLEARANCE, SITE DEVELOPMENTS & EARTH WORKS as listed in Schedule ‘A’ Part-II | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for INTERNAL ELECTRIFICATION as listed in Schedule ‘A’ Part-III | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for INTERNAL WATER SUPPLY as listed in Schedule ‘A’ Part-IV | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for ROAD/PATH/CULVERT as listed in Schedule ‘A’ Part-V | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for EXTERNAL WATER SUPPLY as listed in Schedule ‘A’ Part-VI | - | Lump-sum | - | - |
| - | Lumpsum price worked out by the tenderer for EXTERNAL ELECTRIFICATION as listed in Schedule ‘A’ Part-VII | - | Lump-sum | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.88 MB
BOQ_848234.xls
BOQ • 0.52 MB
TENDER-MERGE89868.pdf
Tender Documents • 35.90 MB
TDdrawingMerge.pdf
Additional Documents • 20.35 MB
MainDrawingsMerge.pdf
Additional Documents • 6.69 MB
CorrigendumNo7-89868.pdf
PDF • 0.13 MB
CorrigendumNo5-89868.pdf
PDF • 0.13 MB
CorrigendumNo4-89868.pdf
PDF • 0.13 MB
CorrigendumNo3-89868.pdf
PDF • 0.13 MB
CorrigendumNo2-89868.pdf
PDF • 0.13 MB
CorrigendumNo1-89868.pdf
PDF • 0.13 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .