Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.7 LAccepted-AOC NO 15 NEW STREET EACHANGADU KIRUMAMPAKKAM PUDUCHERRY 607 402 | CUDDALORE | TAMIL NADU | 607402 | L1 | Accepted-AOC Accepted |
Tender Value
₹17.7 L
EMD Value
₹35,460
Closing Date
2 Feb 2021, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
The Executive Engineer, ID, PWD, Puducherry
O/o the Executive Engineer, ID, PWD, Puducherry.
Reconstruction of Two Numbers of sluices in Karasur Tank in Villianur Commune, Puducherry.
2021_PWDC2_7556_1
36/PW/IRRN/2020-2021
Open Tender
Civil Works
Item Rate
90 days
Puducherry
Please refer Tender Documents
3 documents required · 3 mandatory
₹525
₹35,460
21 Jul 2021
21 Jan 2021
3 Feb 2021
21 Jan 2021
2 Feb 2021
21 Jan 2021
90 days
Amount
Earth work in excavation for foundation of structures as per drawings and technical specifications, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material - Oridnary Soil - Mechanical Means - Depth upto 3 metres including the cost of labour hire charge of hydraulic excavator and overhead charges.
Earth work in excavation for foundation of structures as per drawings and technical specifications, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material - Oridnary Soil - Mechanical Means - 3 metres to 6 metres depth including the cost of labour, hire charge of hydraulic excavator and overhead charges.
Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead - in cement mortar
Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead - nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead - in cement mortar
Supply of Quarry rubbish including stacking to department gauge for premeasurement and spreading required thickness
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
Centring and shuttering including strutting , propping etc. and removal of form work for - retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
Centering and shuttering including strutting , propping etc and removal of form for - Suspended floors , roofs , landings , balconies and access platform
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns,piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping,bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc. upto floor five level, excluding the cost of centering ,shuttering and finishing - 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Reinforced cement concrete work in beams, suspended floors , roofs having slope up to 15degree landings , balconies , shelves , chajjas , lintels , bands , plain window sills , staircases and spiral stair cases upto floor five level excluing the cost of centering ,shuttering, finishing and reinforcement , with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Steel reinforcement for R.C.C.work including straightening , cutting , bending , placing in position and binding all complete upto plinth level - Thermo -Mechanically treated bars (TISCON / VIZAG / IISCO / SAIL / JSW) Fe - 415 or more
Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc .complete - 40mm thick with 20mm nominal size stone aggregate
12mm cement plaster of mix -1:6 ( 1 cement : 6 fine sand)
Making of bound wall with HDPE cement bags filled with stone dust for discharge regulations, breach closing/diversion arrangement. The rate includes the cost of empty HDPE bags, cost of stone dust, labour charges for filling the bags and placing in position for its purpose in or under foul condition etc., complete as directed by the Engineer - in - Charge.
RR Masonry: Supplying with gravel for apron and rivetment
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size ) upto plinth level with - cement mortar 1:6 (1 cement : 6 coarse sand)
Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. ( Excluding cost of stone)
Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand) - flush/ruled pointing
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50m and lift upto 1.5m
For Sluice Shutter Replacement Providing the screw gearing plug to the tank sluice with (Karuvelan) country wood of size 200mm dia x 400mm length turning for 250mm length for taper major dia 200mm, minor dia 50mm fixing for MS flat guard to the plug with screw to the plug with screw and the plug and screw gear assembly shall be screwed with 50mm diameter MS rod of required length and screw gearing assembly consist of C.I base plate of size 300mm x 300mm x30mm fixed over 2 Nos. of rolled steel beam section ISLB 150mm x 75mm ranging from 1.2m to 1.5m length. A hexogonel nut fixed over the C.I Plate capstain nut assembly shall be 20mm. The rate includes cost of all materials, labour charges or fixing the steel beams, steel channel in position with R.C.C 1:2:4. The rate includes cost of painting two coats with black enamel paint over two coats of steel primer. The cost of labour charges, material charges, fixing charges and transportation charges and operating key etc., as directed by the Engineer - in - Charge.
Providing and fixing best country wood Karuvelan or equivalent for bottom (Saradikattai) having overall length of400mm for the opening of 100mm x 100mm and major side of 200mm x 200mm with MD flat guard, handly, locking arrangements as directed by the Engineer - in - Charge.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .