Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹12.3 LAdmitted-Finance | -25.25% | ₹12.3 L | L1 | Admitted-Finance |
| 2 | L2₹12.6 LAdmitted-Finance | -23.71% | ₹12.6 L | L2 | Admitted-Finance |
| 3 | L3₹12.7 LAdmitted-Finance | -23.13% | ₹12.7 L | L3 | Admitted-Finance |
| 4 | L4₹12.8 LAdmitted-Finance | -22.23% | ₹12.8 L | L4 | Admitted-Finance |
| 5 | L5₹13.6 LAdmitted-Finance | -17.50% | ₹13.6 L | L5 | Admitted-Finance |
Tender Value
₹16.5 L
EMD Value
₹16,515
Closing Date
20 Feb 2026, 3:00 pmClosed
Add.Chief Executive Officer Z.P.Pune WellaslayRd.C
Add.Chief Executive Officer Z.P.Pune WellaslayRd.C
11. Construction of internal road in Kasurdi.Tal -Daund
2026_RDPUN_1276822_11
ZPPune/South/e-Tender/64/25-26
Open Tender
Civil Works
180 days
Pune
Please refer Tender documents.
3 documents required · 3 mandatory
₹590
₹16,515
Yes
6 Mar 2026
12 Feb 2026
21 Feb 2026
12 Feb 2026
20 Feb 2026
12 Feb 2026
Excavation for catch / side water gutter in all sorts of soils to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff as directed all sorts of soils.
Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area
Supplying hard murum/ kankar at the road site, including conveying and stacking complete
Spreading hard murum/ soft murrum/ gravel or kankar for side width complet
Compacting the hard murum side widths including laying in layers on each side with vibratory roller including artificial watering etc. complete
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with Vibratory roller. to the required density. By Mechanical Means - Grading I (Using Screening Type A (13.2) mm Aggregate)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with vibratory roller to the required density. By Mechanical Means - Grading II (Using Screening Type B (11.2 mm) Aggregate)
Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM) road surface including all mataerials, preparing the existing road surface, spreading 40mm. stone metal layers 30% crusher broken metal + 70% Hand broken (by breaking rubble obtained by blasting) heating and spraying the bitumen of specified grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting with static roller having weight 8 to 10 MT. to achive the desired degree of compaction as per Technical Specification Clause 506 etc. complete. Including picking of existing WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates)
Providing and applying tack coat on the prepared surface heating by fames in Boiler and spraying bitumen with sprayer on Dry / Hungry B.T. surface 3 kg/10 sqm. (VG-30 bulk bitumen rates are considered to arrive at rates)
Open Graded Premix Surfacing- Providing and Laying OGC 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates premixed with bituminous binder transported to site with VTS , laid over a previously prepared surface, finished to the required grade, level, alignment, and rolling to achieve the desired compaction but excluding prime / tack and Seal coat. For Bitumen of specified grade--USING drum mix type hot mix plant with SCADA, Paver and Vibratory roller ( Over MPM Surface) (VG-30 bulk bitumen rates are considered to arrive at rates)(Non SCADA item)
Providing bituminous Type A liquid seal coat on bituminous surface including supplying all materials and bitumen of specified grade preparing existing road surface, heating and applying bitumen @ 0.98 KgSqm. by mechanical means, spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete. (VG-30 bulk bitumen rates are considered to arrive at rates)
BASIC TEST OF AGGREGATE. 1)Water Absorption, Specific Gravity,Impact Value, Crushing Value.
BASIC TEST OF AGGREGATE. 2)Sieve Analysis.
SOIL / MURUM. 2)Liquid limit & plastic Limit.
BITUMEN.1)Penetration, Softening Point, Flash & Fire Point, Specific Gravity
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
technical_2197196.pdf
techsummary_2197196.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.41 MB
Tendernotice_2.pdf
PDF • 0.05 MB
Tendernotice_3.pdf
PDF • 0.63 MB
Tendernotice_4.pdf
PDF • 0.39 MB
Tendernotice_5.pdf
PDF • 0.10 MB
Tendernotice_6.pdf
PDF • 0.37 MB
BOQ_2197196.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid