| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC HOUSE NO 92 HOUSE NO 92 SECTOR 7 PANCHKULA 134109 | PANCHKULA | PANCHKULA | HARYANA | 134109 | ₹1.2 Cr | L1 | Accepted-AOC LOWEST |
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
27 May 2020, 5:00 pmClosed
Pawan Kumar Bansal
Executive Engineer, Constn. Divn. Hr.PWD B and R, Br., Chandigarh
Improvement of link road Thane-Ki-Sair in Panchkula Distt. (ID 8339) (Under SCSP Scheme).
2020_HRY_118295_3
PWD/CHD/CD-CHD/16897
Open Tender
Construction Works
Works
180 days
Chandigarh
Please refer Tender documents.
3 documents required · 3 mandatory
₹15,000
E.E., Constn. Division, PWD B and R Br.,
₹2.2 L
28 Oct 2020
8 May 2020
29 May 2020
8 May 2020
27 May 2020
8 May 2020
Amount
Milling of distress bituminous layer upto 20mm depth in a single pass with suitable milling machine (capable of milling @ 200-300 sqm area per Hr.) fitted with loading conveyor for loading the milled material directly on the trucks for safe disposal with all leads and lifts complete in all respects. Note: - The quantity of milled bituminous mix material shall be a recovery item as mention in BOQ item No. 28.
Dismantling Brick Work, Tile Masonry or Tile Lining and Tile Terracing, dry brick work {HSR 8.5 (i)}
Providing and laying 150 mm thick granular sub base consisting of drainage-cum-filter layer confirming to Table 400.1 Grading - VI of MoRT&H 5th edition, mixing in a mechanical mix plant at OMC, carriage of mix material to the site of work, spreading in uniform layer with motor grader on prepared surface and compacting with vibratory power roller to achieve desired density complete as per clause No. 401 of MoRT&H specifications. Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by engineer.
Providing & laying 75mm thick (Compacted) stone metal (G-I) 63 to 45mm gauge wearing coat to Water Bound Macadam in layer of 75mm each using screening type 'B' compacting with 3 wheeled steel roller/vibratory roller to achieve the desired density including lighting, guarding barricading and maintenance of diversion etc. as per clause No.404 of MoRT&H specifications of road & bridges (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respect. (N.S.) Note: - 1.Only crushed stone metal material should be used. No local earth/ natural occurring sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by ngineer.
Providing & laying 75mm thick (Compacted) stone metal (G-II) 53mm to 22.4mm gauge wearing coat to water bound macadam in layer of 75mm each using screening type ‘B’ compacting with 3 wheeled steel roller/vibratory roller to achieve the desire density including lighting, guarding barricading and maintenance of diversion etc. as per clause No.404 of MoRT&H specifications for road & bridge (5th Revision) of 2013 as per drawing and design directed by the Engineer complete in all respects.(N.S.) Note: - 1.Only crushed stone metal material should be used. No local earth/ natural occurring sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by engineer.
Providing and laying first coat surface dressing, including rolling with road roller etc. complete including cost of bitumen VG-10 grade using aggregate 13mm nominal size 1.00 cum and bitumen VG-10, 0.10 MT per hundred square metre. Clause 509 of MoRT&H specification.(5th edition ) 2013 (NS).
Providing and laying tack coat with bitumen VG-10 grade pressure distributor at the rate of 0.30 kg. per sqm. On the prepared bitumen/granular surface cleaned with mechanical broom including cost of bitumen as per clause No.503 (5th edition) 2013 as per MoRT&H specification (N.S.)
Providing & Laying 30 mm thick compacted Bituminous Concrete (BC) in one layer with 100-120 TPH batch type hot mix plant and with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with appropriate rollers to achieve the desired compaction as per clause No. 507 MoRT&H specification (5th Revision) 2013 for road and bridge works (5th Revision)2013 using minimum 5.4% to bitumen grade VG-30 as binder content by weight of total mix, complete in all respects including cost of bitumen instruction issued from time to time by MoRT&H regarding machinery & bitumen will be followed strictly. The use of self propelled mechanical paver fitted with electronic sensor device conforming to MoRT&H specification in mandatory. If bitumen required more than 5.4% as per job mix formula no extra payment will be made, extra bitumen required will be considered as incidental to work. Note: - Before carrying out bituminous work, coating & stripping of bitumen aggregate mix is to be performed in accordance with IS – 6241. If coating and stripping of bitumen aggregate mix is less than 95%, anti-stripping agent will be used by contractor. The anti – stripping agent should conform to the requirement as stipulated in IS 14982:2017. The cost so incurred will be considered as incidental to work and nothing extra shall be payable. The type and brand of anti-stripping agent along with procedure shall be approved by SE-in-charge in writing before start of work. A proper record of results be maintained and same shall be submitted along with bills by the contractor. Note: - Where there is only BC on existing black top, cracks shall be sealed as MoRT&H specification 5th revision clause No. 3004.3, which may consists of (i) Fog seal/ or (ii) crack filling and or (iii) patch work repair as required at site in accordance with clause No. 3004.3.2, 3004.3.3 and 3004.2 of MoRT&H specification 5th revision respectively. Proper measurement and consumption shall be entered in MB for cracks sealed but no payment on this account shall be made as crack filling is incidental to work.
Earth work excavation in ordinary soil exclusive of compensation of earth-earth-work undressed with a combined lead upto 15 metres including breaking of clods. (HSR 6.2b). Note: Disposal of surplus earth as desired by Engineer-In-Charge with all lead and lift will be incidental to earth and no payment will be made for disposal.
Supply collection and carriage if First class brick 22.86cm x11.11cmx6.86cm from approved kiln to site of work shall be made from good brick earth conforming to 3.5 of Haryana PWD specification 1990 edition in stacks of 50 bricks length, 2 bricks width and 10 bricks height parallel to the center line of the road Bricks shall be free from saline deposits and shall be sand molded. They shall be thoroughly brunt without vitrified and shall have uniform deep red, cherry or copper colour. They shall be regular and uniform in shape and size with sharp and squares arise and parallel faces. They must be homogeneous in texture and emit a clear ringing sound on being struck. They shall be free flaws, cracks , chops, stones, nodules or lime or kankar and other blemishes complete as per Haryana PWD specification No. 3.5.1990 First Edition.(NS)
Laying brick on end edging length-wise 22.86 cm deep and 6.83 cm wide including excavation of earth and refilling the excavated soil and compacting along brick edging complete in all respect with other than brick soiling. {HSR 24.6 (b)}
Earth work in excavation in foundations, trenches, etc. in all kinds of soils, not exceeding 2 meters depth including dressing of bottom and sides of trenches, stacking the excavated soil, clear from the edge of excavation and subsequent filling around masonry, in 15 cm layers with compaction, including disposal of all surplus soil, as directed within a lead of 30 meters. (HSR 6.6)
Excavation including handling of materials, within 15 meters inclusive of cost of explosive and dressing, compressed air T&P:- Pick work (HSR 7.1)
Cement concrete 1:4:8 with stone aggregate 40mm nominal size in foundation and plinth.(HSR 10.39)
Cement concrete 1:2:4 with stone aggregate 20mm nominal size in foundation and plinth.(HSR 10.41)
Cement concrete 1:1½:3 with stone aggregate 20 mm nominal size for reinforced concrete work in slabs with inclination not exceeding 25 degree with Horizontal, excluding steel reinforcement but including centering and shuttering, laid in position complete in all respect extra over Item Nos. 10.79 to 10.94, if 1:1 ½:3 mix is used, instead of 1:2:4. {HSR 10.82 + 10.95 (a)}
Cement concrete 1:2:4 with stone aggregate 20mm nominal size for reinforced concrete work for bed plates in square, rectangular, polygonal, circular and elliptical wells, excluding steel reinforcement but including centring and shuttering, laid in position complete in all respects.(HSR 10.94)
First class brick work laid in cement sand mortar 1:4 in foundation and plinth.(HSR 11.4)
Random Rubble masonry or polygonal rubble masonry (Kentish rag) or random or polygonal rubble, built to courses, in foundation and plinth in cement mortar 1:6(HSR 12.37 + Note)
Providing and fixing PVC Rain water pipe 6Kg Pressure of ISI mark in cement mortar during masonry work 100mm dia PVC pipe 6 Kg pressure. (HSR 13.89) (a)
Damp proof course 40mm thick of cement concrete 1:2:4 using stone aggregate with 2 coats of bitumen 20/30 penetration at 1.65 Kg. per sqm. laid hot and sanded (HSR 10.114-Note)
12mm thick cement plaster in cement mortar 1:4 (HSR 15.5)
Cement pointing raised 1:2 on stone walls(HSR 15.67)
Fe-500 EQR/TMT steel bars for R.C.C. works, where not included in the complete rate of R.C.C. including bending, binding and placing in position complete in all respect. Note: - Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work, excluding overlaps. From the length so measured, the weight of reinforcement shall be calculated in tones on the basis of IS : 1732. Wastage, overlaps, coupling, welded joints space bars, chairs, stay, hangers and annealed steel wire or other methods for binding and placing, shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement)(NS).
Providing and laying 80mm thick interlocking paver blocks ISI marked (IS code: 15658:2006) of all shapes and colours in design mix cement M-40 as per IRC:SP:63-2004, over a bed of 30 mm thick fine sand complete in all respects. [HSR 10.159 + Additional Cost of Cement]
Preparation of berms including filling of Earth work, excavation and cutting of earth in all kind of soils including dressing the bank, side slope to given levels and templates after breaking of clouds, including the cost of rolling and watering all allowances for labour hardness wetness irrespective of all lead and lift, but including Compensation for earth taken from private land, fields etc. and compacted to meet requirement of table 300-2 of MoRT&H specification clause No. 305 and to the entire satisfaction of the Engineer of the work conforming to PWD specification No. 6.2 and 6.3 and 3.2 and the other specification 1990 Ist edition. As per X-section attached at DNIT at Section -9. Note: - No earth work will be allowed to be taken from PWD B&R/ ROW except for surplus earth after approval from Engineer.
Providing & Marking center line / side line 2.5mm thick (minimum) with hot applied thermo-plastic road marking paint 10 cms wide/ 15cm wide complete in all respect such as furnishing all labour, materials, tolls equipments including all incidental costs necessary for carrying out in work at site confirming to the technical specification as clause No. 803 of MORT&H specification for road and bridge works (5th revision) of 2013/ Latest edition. Each container of the thermoplastic material shall have the name trademark or other means of identification of manufacturer, batch number, date of manufacture color maximum application temperature and maximum heating temperature. The thermoplastic paint material shall be of Asian Paint-Apcomark/Berger-Sigmarc/Prismo. The glass beads shall be of Potters/Sovitec/Fleolite. The thermoplastic material shall be sampled and tested in accordance with appropriate ASTM/BS method. The contractor shall furnish to the Engineer-in-Charge a copy of certified test reports from the manufacturer of the thermoplastic material meet all requirement of the specifications. The reflector zing glass beads shall meet the requirement of clause 803.4.2 and test methods mentioned in clause 803.4.2.4 shall be meticulously followed. The minimum thickness specified is exclusive of surface of glass beads the method of thickness measurement shall be in accordance with appendix B and C of BS:3262 (part-3). Note: - Before start of work the contractor shall give brand, batch number, manufacturing date of the material to be used along with a photocopy of bill duly signed by the contractor and get approved the same from Engineer-In-Charge before use.
Recovery items: The rates quoted against recovery items will not be included in the total amount rather it will be deducted while calculating financial statement of the agency. Material obtained from dismantling of existing brick work, bituminous layer and granular layers have been calculated taking assumption that 80% of theoretical material will be retrieved. The dismantled material can used in any of the item for the work after modification (bringing it to required specifications) after approval from employer. In case it is not possible to use this material on the work, the agency can take away this material. This material can be taken away by the agency at the price quoted by the agency but minimum price to be quoted is limited to reserve price as fixed and mentioned as under :- Good Bricks @ 4.50/-Each
Bricks Bats @ 400/-Per Cum
Bituminous mix material @ Rs. 1090.50 /- P.Cum. Note: All quantities of the above materials have been worked out on the basis of theoretical quantities laid on this road. However, agency may visit site before quoting rates and assess the extent of retrieved material. There shall be no measurement after actual dismantling and if material after dismantling is found on lesser side, no claim of agency on this score will be entertained and full recovery on the basis of quoted rate and quantity exhibited in the BOQ shall be made. The reserve rates are minimum rates to be used as base for quoting purchase rate by the agency. No rates below the reserve price will be entertained and reserve price will be considered for all purposes in case the agency quotes lesser than reserve price. Note: i) In case of any difference in the unit & nomenclature of any of the HSR items depicted in this DNIT and that given in HSR, the unit and nomenclature given in HSR shall be applicable. ii) In case of any difference in the unit of any Non-schedule items depicted in this DNIT and the conventional unit of that N.S. item as per practice in this department, the conventional unit as per practice shall be applicable.
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .