| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.9 LAccepted-AOC | ₹10.9 L | L1 | Accepted-AOC Bid Accepted. Hence, Lowest Bidder L1 |
| 2 | L2₹10.9 LRejected-AOC | ₹10.9 L | L2 | Rejected-AOC Bid Rejected. Hence, Highest Bidder L2. |
| Sl No | Description | Qty | Unit | SRI NANDHAA CONSTRUCTIONS L2 | A GANESAN L1 |
|---|---|---|---|---|---|
| 1.00 | Construction of Boys Toilet at P.U.Middle School Veerachimangalam H/O Veerachimangalam Panchayat..
Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and balling out water whenever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc., including levelling the sites complete complying with standard specifications. | 40.35 | Cum | 280 ₹11,298 | 263 ₹10,612.05 |
| 2.00 | Cement concrete 1:4:8 mix ( one cement four sand and eight aggregate)using 40mm gauge hand broken granite tone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted, etc., complete comply
laterite, soft rock or kankar not requiring blasting | 9.57 | Cum | 5,430 ₹51,965.10 | 5,420 ₹51,869.40 |
| 3.00 | Refilling in foundation and basement with excavated earth in layers of not more than 15 cm thick well rammed watered and compacted including & conveyance and all labour charges etc., | 14.93 | Cum | 60 ₹895.80 | 46 ₹686.78 |
| 4.00 | Plain Cement Concrete 1:2:4 (one cement, two M.Sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
HBG metal excluding cost of reinforcement and centering but including cost of mixing, laying, finishing, curing etc | 1.35 | Cum | 6,718 ₹9,069.30 | 6,718 ₹9,069.30 |
| 5.00 | Brick work in cm 1:5 mix (one cement and five sand) using II class bricks of size including curing, finishing and cost & Conveyance of all materials etc., complete.Basement | 8 | Cum | 6,120 ₹48,960 | 6,103 ₹48,824 |
| 6.00 | Superstructure | 8.02 | Cum | 6,250 ₹50,125 | 6,196 ₹49,691.92 |
| 7.00 | Supplying and erecting centering for sides and soffits of RCC works of plane surfaces mentioned below including strutting 3m high using mild steel sheets stiffened with M.S angles Below GL | 18.22 | Sqm | 547 ₹9,966.34 | 547 ₹9,966.34 |
| 8.00 | Above GL | 15.74 | Sqm | 1,095 ₹17,235.30 | 1,095 ₹17,235.30 |
| 9.00 | Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete | 0.55 | MT | 91,905 ₹50,547.75 | 91,905 ₹50,547.75 |
| 10.00 | RCC 1:1½:3 mix using 20 mm ISS HBG metal for RCC works excluding centering, shuttering, and reinforcement grill but including laying, ramming, curing etc., complete
Upto Ground Level | 5.18 | Cum | 9,153 ₹47,412.54 | 9,153 ₹47,412.54 |
Tender Value
₹12.6 L
EMD Value
₹13,000
Closing Date
5 Feb 2026, 3:00 pmClosed
The Project Director, DRDA, Tiruppur
DRDA, Tiruppur
Pkg No. 06/PMKKKY/Mines and Minerals/2025-26 in Dharapuram Block of Tiruppur District
2026_RDTN_649072_6
Roc No. 5033/2025/A10 Dated.20.01.2026
Open Tender
Civil Works
90 days
Tiruppur
Please Refer Tender Documents
3 documents required · 3 mandatory
₹0
₹13,000
DRDA, Tiruppur
12 May 2026
30 Jan 2026
5 Feb 2026
30 Jan 2026
5 Feb 2026
30 Jan 2026
2 Feb 2026
Construction of Boys Toilet at P.U.Middle School Veerachimangalam H/O Veerachimangalam Panchayat.. Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and balling out water whenever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc., including levelling the sites complete complying with standard specifications.
Cement concrete 1:4:8 mix ( one cement four sand and eight aggregate)using 40mm gauge hand broken granite tone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted, etc., complete comply laterite, soft rock or kankar not requiring blasting
Refilling in foundation and basement with excavated earth in layers of not more than 15 cm thick well rammed watered and compacted including & conveyance and all labour charges etc.,
Plain Cement Concrete 1:2:4 (one cement, two M.Sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. HBG metal excluding cost of reinforcement and centering but including cost of mixing, laying, finishing, curing etc
Brick work in cm 1:5 mix (one cement and five sand) using II class bricks of size including curing, finishing and cost & Conveyance of all materials etc., complete.Basement
Superstructure
Supplying and erecting centering for sides and soffits of RCC works of plane surfaces mentioned below including strutting 3m high using mild steel sheets stiffened with M.S angles Below GL
Above GL
Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete
RCC 1:1½:3 mix using 20 mm ISS HBG metal for RCC works excluding centering, shuttering, and reinforcement grill but including laying, ramming, curing etc., complete Upto Ground Level
Coloumn above grade beam
Supplying and fixing of Indian type water closet including all charges etc.
Supplying and fixing in position white / colour glazed European Water Closet of best quality and approved make with 100 mm "P" or "S" trap connecting with CI pipe of 100mm dia / PVC pipe of 110mm dia, double flapped rigid PVC black seat and seat cover with CP brass hinges including cost of white cement, cement for packing, spun yarn, teak wood plugs, brass screws, etc.
Supplying and fixing of Squatting Pan Urinal Inculding all labour charges etc
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work.
Plastering with cement mortar 1:4 mix 20mm thick in all floors complying with standard specifications.
Plastering with cement mortar 1:5 (one cement and five sand)12mm thick in all floors complying with standard specifications.
Paving the flooring with special type of flooring tiles (Cement based Hydraulically pressed Anti skid tiles (20mm thick) in CM 1:3, 20mm thick
Dadooing the walls with colour glazed tiles in cement mortar 1:2 mix (One cement and two sand) 10mm. Thick using best quality of glazed tiles of size 15cm x 15cm x 6mm. Including pointing with white cement using 0.40kg Per square metre including finishing the joints and pointing flush with tile surface etc., complete including plastering the walls with cement mortar 1:5 mix (One cement and five sand ) 12mm. thick as base coat for the tiles including scaffolding, setting, curing, etc., complete complying with standard specifications as directed by the departmental officers.
Towards the cost of steel door of size 0.75mx 1.80 m including all charges etc.
Distembering two coats with best approved oil bound distember including cost of painting priming coat over new plastered surface and conveyance of all materials to site and all labour charges
Supplying and fixing of Cuddappah slab as Partition for Urinal including cost of slab and all labour charges for fixing the same in position charges etc,. Complete
Exterior Emulsion Two coats over priming coat including cost and conveyance of all materials and labour charges etc complete. metal including mixing curing etc.,
Painting two coats using Ist quality readymix enamel paint of approved colour over new iron work including cost and conveyance and all labour charges etc.
Towards to labour charges for Fixing of Following size doors in position Inculding all labour charges etc. on the sidewall of SR as
Provision for supplying and fixing RCC Jolly
Provision for Name board
Construction of Girls Toilet at P.U.Middle School Veerachimangalam H/O Veerachimangalam Panchayat.. Earth work excavation for foundation in all clauses of soils and sub soils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and balling out water whenever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc., including levelling the sites complete complying with standard specifications.
Cement concrete 1:4:8 mix ( one cement four sand and eight aggregate)using 40mm gauge hand broken granite tone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted, etc., complete comply laterite, soft rock or kankar not requiring blasting
Refilling in foundation and basement with excavated earth in layers of not more than 15 cm thick well rammed watered and compacted including & conveyance and all labour charges etc.,
Plain Cement Concrete 1:2:4 (one cement, two M.Sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. HBG metal excluding cost of reinforcement and centering but including cost of mixing, laying, finishing, curing etc
Brick work in cm 1:5 mix (one cement and five sand) using II class bricks of size including curing, finishing and cost & Conveyance of all materials etc., complete.Basement
Superstructure
Supplying and erecting centering for sides and soffits of RCC works of plane surfaces mentioned below including strutting 3m high using mild steel sheets stiffened with M.S angles Below GL
Above GL
Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete
RCC 1:1½:3 mix using 20 mm ISS HBG metal for RCC works excluding centering, shuttering, and reinforcement grill but including laying, ramming, curing etc., complete Upto Ground Level
Coloumn above grade beam
Supplying and fixing of Indian type water closet including all charges etc.
Supplying and fixing in position white / colour glazed European Water Closet of best quality and approved make with 100 mm "P" or "S" trap connecting with CI pipe of 100mm dia / PVC pipe of 110mm dia, double flapped rigid PVC black seat and seat cover with CP brass hinges including cost of white cement, cement for packing, spun yarn, teak wood plugs, brass screws, etc.
Supplying and fixing of Squatting Pan Urinal Inculding all labour charges etc
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work.
Plastering with cement mortar 1:4 mix 20mm thick in all floors complying with standard specifications.
Plastering with cement mortar 1:5 (one cement and five sand)12mm thick in all floors complying with standard specifications.
Paving the flooring with special type of flooring tiles (Pre Polished Concrete Anti skid tiles (20mm thick) in CM 1:3, 20mm thick
Dadooing the walls with colour glazed tiles in cement mortar 1:2 mix (One cement and two sand) 10mm. Thick using best quality of glazed tiles of size 15cm x 15cm x 6mm. Including pointing with white cement using 0.40kg Per square metre including finishing the joints and pointing flush with tile surface etc., complete including plastering the walls with cement mortar 1:5 mix (One cement and five sand ) 12mm. thick as base coat for the tiles including scaffolding, setting, curing, etc., complete complying with standard specifications as directed by the departmental officers.
Towards the cost of steel door of size 0.75mx 1.80 m including all charges etc.
Distembering two coats with best approved oil bound distember including cost of painting priming coat over new plastered surface and conveyance of all materials to site and all labour charges
Supplying and fixing of Cuddappah slab as Partition for Urinal including cost of slab and all labour charges for fixing the same in position charges etc,. Complete
Exterior Emulsion Two coats over priming coat including cost and conveyance of all materials and labour charges etc complete. metal including mixing curing etc.,
Painting two coats using Ist quality readymix enamel paint of approved colour over new iron work including cost and conveyance and all labour charges etc.
Towards to labour charges for Fixing of Following size doors in position Inculding all labour charges etc. on the sidewall of SR as
Provision for supplying and fixing RCC Jolly
Provision for Name board
GST Amount for providing Service to Government Contract Works for the above Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.85 MB
BOQ_778293.xls
BOQ • 0.34 MB
06pkg.pdf
Tender Documents • 1.44 MB
Download all tender documents and submit your bid