| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹14.5 LAccepted-AOC | 1 | Accepted-AOC LOWEST BIDDER | |
| 2 | 2₹15.6 L+₹77,469 (5.21%)Rejected-AOC | 2 | Rejected-AOC L2 BIDDER | |
| 3 | 3₹16.1 L+₹1.2 L (8.13%)Rejected-AOC MYOREPUR ANPARA ANPARA ANPARA SONBHADRA UTTAR PRADESH 231225 | SONBHADRA | UTTAR PRADESH | 231225 | 3 | Rejected-AOC L3 BIDDER |
Tender Value
₹14.7 L
EMD Value
₹29,000
Closing Date
28 Sept 2020, 12:00 pmClosed
SUPERINTENDING ENGINEER
SE OMC4 BTPS ANPARA
Upkeep of MCB, site offices, stores, compressor rooms, Battery room, lawns of A and B TPS switchyard Anpara
2020_RVUNL_506228_1
T-08/EMD-III/BTPS/2020-21
Open Tender
Electrical Works
Fixed-rate
365 days
ATP SWITCHYARD ANPARA
AS PER TENDER DOCUMENTS
3 documents required · 3 mandatory
₹1,180
DY CAO CFA AND BO BTPS ANPARA
₹29,000
12 Nov 2020
31 Aug 2020
30 Sept 2020
31 Aug 2020
28 Sept 2020
31 Aug 2020
Amount
PART-A1:The work in this part shall include upkeep of the following areas/locations of ‘A’ TPS switchyard
(a)Upkeep of MCB control room floor & panel/board. (b)Upkeep of Battery room in switchyard. (c)Upkeep of MCC room & charger room including panels. (d)Upkeep of PLCC/ Carrier room & panel. (e)Upkeep of testing lab, AE’s office, storeroom, shift engineer room, staircases & galleries of MCB. (f)Upkeep of 4 No. bathrooms/latrines. (g)Upkeep of Compressor room in switchyard. (h) Upkeep of 11 KV switchgear room, panels, operator room, store room, external verandah around 11 KV switchgear room
PART-A2: The works against this part shall include the following jobs pertaining to ‘A’ TPS switchyard. The quantities mentioned are maximum quantity & the quantity may vary widely. These works shall be done as & when required:
Upkeep of marshalling boxes, panels/cabinets of 400/132/33 KV switchyard & pressure tanks of 132 KV oil filled cables
Cleaning of oil pit (lxbxh)- 7x7x3.2 m
Cleaning of oil pit (lxbxh)- 4.5x4x5 m
Cleaning of oil pit (lxbxh)- 2.5x2x1.75 m
Cleaning of latrine pit
Cleaning of roads in 132/400 KV switchyard area
Cleaning of Cable gallery of MCB of 400/132 KV system including trenches of ATPS & BTPS.
PART-A3:The work in this part shall include upkeep of the following areas/locations of ‘B’ TPS switchyard
Cleaning of site offices, stores, toilet, compressor room, etc
PART-A4:The work in this part shall include upkeep of the online ABT monitoring system:
Cleaning of online ABT monitoring system of ATPS & BTPS
PART-A5: The works against this part shall include the following jobs pertaining to ‘B’ TPS switchyard. The quantities mentioned are maximum quantity & the quantity may vary widely. These works shall be done as & when required:
Cleaning of all roads within the BTPS switchyard once a month
Cutting of plants more than six inches in height adjacent to switchyard
PART-A6: The work in this part shall include Removal and disposal of grass, wild plants, shrubs, etc in 400KV Anpara ‘B’TPS switchyard including ICT-3, 33KV Reactor areas
Removal & Disposal of grass, wild plants, shrubs, etc as per scope of work for approx. 55,000.00 M2
PART-B1:(400/132/33/11KV Anpara ‘A’TPS, Switchyard.)
Cutting & Disposal of grass & wild plants, shrubs in 400/132/33 KV switchyard working area & around compressor room & 11 KV switchgear room as per scope of work for approx. 2,40,000.00 M2
Cutting & Disposal of grass & wild plants, shrubs in surrounding periphery area of 400/132/33 KV switchyard and corridor of unit 1 to 5 transmission lines as per scope of work for approx. 1,80,000.00 M2
Removal & Disposal the corpse of cows or any animals from A&B TPS switchyard.
PART-B2: (132KV Overhead structure of CWT-1 & 2 from 132KV switchyard to CW transformers)
Cutting & Disposal of grass, wild plants, shrubs, etc as per scope of work for approx. 40,000.00 M2
PART-B3 Trimming of trees (diameter 50mm, height above 2 meters ) up to a height of 500mmwhich grow under the live conductor starting from Turbine Hall to Switchyard and up to 10 meters on either side of the gantry .Diameter of trees shall be measured at 1000 mm from the ground.
50MM TO 100MM Dia
100 to 150 Dia
Above 150 mm Dia
PART-B4: (132 KV cable trench including LANCO area.)
Cutting & Disposal of grass, wild plants, shrubs, etc as per scope of work for approx. 30800.00 M2
PART-B5: (Maintenance of switchyard lawn area)
Maintenance of grass lawns including cutting of grass with lawn mower or foot drive thresher including watering and removing weed etc.
M/S B P ENTERPRISES
M/S RANJANI CONSTRUCTION CO.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .