| Sl No | Description | Qty | Unit | SHABI ENGINEERS L2 | UNITED ENGINEERING CONSTRUCTION L3 | TAJ ENTERPRISES L4 | M/s Prakash & Brothers L1 |
|---|---|---|---|---|---|---|---|
| 1.00Replacement of 40MVA T/F-2nd C&R panel and & procurement of Material for auto-operation and overhauling of cooling fan at 132KV S/S Jahanabad under Electricity Transmission Division-Fatehpur. | |||||||
| 1.01 | Complete dismantling of old 40MVA T/F 2nd C&R Panel at 132KV S/S Jahanabad with safety and shifting in to store Room. Contractor will arrange all Labour,T&P nad hydraulic crane at his own cost. | 1 | Job | 4,920 ₹4,920 | 4,999 ₹4,999 | 5,005 ₹5,005 | 8,000 ₹8,000 |
| 1.02 | Opening of termination of old Electromechanical panel of 40MVA T/F-2nd after tracing each cable from different equipment connected to that bay and adjacent panel (132KV TBC Panel ) also as no drawing available. | 1 | Job | 4,909 ₹4,909 | 4,999 ₹4,999 | 5,010 ₹5,010 | 8,000 ₹8,000 |
| 1.03 | Proper & safe erection of Transformer C&R panel as per technical
specification including shifting of material/equipment from store to erection site including all other associated work to complete the job satisfactorily. All labour, T&P and hydraulic crane will be provided by contractor at his own cost. | 1 | Job | 7,786 ₹7,786 | 7,989 ₹7,989 | 8,005 ₹8,005 | 5,000 ₹5,000 |
| 1.04 | Laying of 4Cx2.5sqmm size of control cable for interconnection of some equipment s whichever required for laying of new control cable. | 0.5 | Km | 5,910 ₹2,955 | 5,989 ₹2,994.50 | 6,490 ₹3,245 | 2,000 ₹1,000 |
| 1.05 | Earthing of T/F control and relay panel from MS Flat including applying one coat of red oxide and two coat of green enamel paint and all other work to complete the job satisfactorily. | 13 | RMT | 298 ₹3,874 | 300 ₹3,900 | 310 ₹4,030 | 200 ₹2,600 |
| 1.06 | Proper & safe termination with proper tying of different size of control cable as per connection schedule with lugs for connection of 40MVA T/F 2nd C&R Panel. This job also including making necessary holes in gland plate of box where ever required. Supply and fixing of cable gland of appropriate size supply and providing ferrule and nos of each core and Lugs with crimping tool and cable tie. will be provided by contactor at his own cost. (The rate of
termination of cable includes the all core of cable at both end with lug.Contractor will arrange all technician, labour, T&P at his own cost.Connection schedule will be provided by contractor. (Drawing of oldElectromechanical Panel is Not available.) | 1 | Job | 5,786 ₹5,786 | 5,999 ₹5,999 | 6,500 ₹6,500 | 15,000 ₹15,000 |
| 1.07 | Supply of Power Contactor of L&T make, model MNX-9 required for auto operation of Cooling Fan. Sample to be collected from respective Sub-stations. | 10 | Nos | 2,980 ₹29,800 | 2,998 ₹29,980 | 3,010 ₹30,100 | 1,000 ₹10,000 |
| 1.08 | Supply of Over Load Relay of L&T make, model MN 2 having 0.6 to 1A required for auto operation of Cooling Fan. Sample to be collected from respective sub-stations. | 8 | Nos | 2,990 ₹23,920 | 2,998 ₹23,984 | 3,020 ₹24,160 | 1,500 ₹12,000 |
| 1.09 | Supply of Add-On Block of L&T make, model MNX-A2 required for auto operation of Cooling Fan. Sample to be collected from respective Sub-staions. | 6 | Nos | 880 ₹5,280 | 898 ₹5,388 | 905 ₹5,430 | 500 ₹3,000 |
Updated dates
Tender Value
₹1.2 L
EMD Value
₹1,500
Closing Date
8 Apr 2026, 4:00 pmClosed
Executive Engineer
220KV ETD Fatehpur
For Replacement of 40MVA TF2nd C and R panel and procurement of Material for auto operation and overhauling of cooling fan at 132KV SS Jahanabad under ETD Fatehpur
2026_UPTCL_1127619_1
E-T-20/ETD(F)/2025-26
Open Tender
Electrical Works
15 days
132 KV SS Jahanabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
Executive Engineer
₹1,500
18 Apr 2026
20 Mar 2026
9 Apr 2026
20 Mar 2026
8 Apr 2026
20 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
Replacement of 40MVA T/F-2nd C&R panel and & procurement of Material for auto-operation and overhauling of cooling fan at 132KV S/S Jahanabad under Electricity Transmission Division-Fatehpur. | - | - | - | - | |
| 1.01 | Complete dismantling of old 40MVA T/F 2nd C&R Panel at 132KV S/S Jahanabad with safety and shifting in to store Room. Contractor will arrange all Labour,T&P nad hydraulic crane at his own cost. | - | Job | - | - |
| 1.02 | Opening of termination of old Electromechanical panel of 40MVA T/F-2nd after tracing each cable from different equipment connected to that bay and adjacent panel (132KV TBC Panel ) also as no drawing available. | - | Job | - | - |
| 1.03 | Proper & safe erection of Transformer C&R panel as per technical
specification including shifting of material/equipment from store to erection site including all other associated work to complete the job satisfactorily. All labour, T&P and hydraulic crane will be provided by contractor at his own cost. | - | Job | - | - |
| 1.04 | Laying of 4Cx2.5sqmm size of control cable for interconnection of some equipment s whichever required for laying of new control cable. | - | Km | - | - |
| 1.05 | Earthing of T/F control and relay panel from MS Flat including applying one coat of red oxide and two coat of green enamel paint and all other work to complete the job satisfactorily. | - | RMT | - | - |
| 1.06 | Proper & safe termination with proper tying of different size of control cable as per connection schedule with lugs for connection of 40MVA T/F 2nd C&R Panel. This job also including making necessary holes in gland plate of box where ever required. Supply and fixing of cable gland of appropriate size supply and providing ferrule and nos of each core and Lugs with crimping tool and cable tie. will be provided by contactor at his own cost. (The rate of
termination of cable includes the all core of cable at both end with lug.Contractor will arrange all technician, labour, T&P at his own cost.Connection schedule will be provided by contractor. (Drawing of oldElectromechanical Panel is Not available.) | - | Job | - | - |
| 1.07 | Supply of Power Contactor of L&T make, model MNX-9 required for auto operation of Cooling Fan. Sample to be collected from respective Sub-stations. | - | Nos | - | - |
| 1.08 | Supply of Over Load Relay of L&T make, model MN 2 having 0.6 to 1A required for auto operation of Cooling Fan. Sample to be collected from respective sub-stations. | - | Nos | - | - |
| 1.09 | Supply of Add-On Block of L&T make, model MNX-A2 required for auto operation of Cooling Fan. Sample to be collected from respective Sub-staions. | - | Nos | - | - |
stage.html
html • 0.04 MB
technical_2103201.pdf
techsummary_2103201.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.37 MB
Tenderformno20.pdf
Tender Documents • 0.37 MB
BOQ_2103201.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid